Key Takeaways
- Record order backlog, revenue up 59%: Order book hit its highest-ever level, driven by a ₹4,680 crore quarter that included large related-party and domestic grid modernization wins. Revenue surged to ₹1,110 crore.
- Profitability transformed: PBT margin nearly tripled YoY to ~17.5%, with gross margin expanding to 41% in Q2 and 40.8% for H1, up from 34% a year ago.
- HVDC catalyst is imminent but timing is uncertain: Two large HVDC tenders are in finalization and a decision is expected within 3 months, though management acknowledges the timeline is beyond its control.
- Order inflow is lumpy by nature: Excluding two large, multi-year orders, the H1 run-rate implies a ~₹5,500-5,800 crore annualized base, per an analyst's math. Management declined to guide quarterly, citing shifting decision timelines.
- What to watch next quarter: Whether the two HVDC packages are actually awarded within the 3-month window, the pace of execution on the record backlog, and any new large related-party orders that could further swell the book.
Order Book & Inflow Dynamics
- Record backlog provides multi-year visibility: The order book is the highest in the company's history, with more than 60-70% of orders carrying an 18-to-24-month execution timeline, giving strong near-term revenue visibility.
- Q2 inflow was exceptional, not a new baseline: The ₹4,680 crore quarter included two large exceptions: a related-party export order with a 5-year delivery timeline, and digital upgrade orders for regional load dispatch centers that recur roughly every 7 years. The balance is the sustainable volume management targets every quarter.
- Base run-rate is a math exercise, not guidance: Excluding the ~₹3,000 crore of large orders, H1 routine inflow was ₹2,700-2,800 crore. Extrapolated, that implies a ₹5,500-5,800 crore annualized base, with the ₹3,000 crore of large orders layered on top for a ₹7,800-8,200 crore yearly range. Management stressed this is a mathematical representation, not a forecast.
- Domestic market is strong and sustainable: Management described the domestic ordering environment as "pretty strong" and is looking at a sustainable number, though it declined to quantify a quarterly run-rate because decision timelines keep shifting.
- Export backlog is material but opaque: Roughly 40% of the ₹10,000 crore order backlog is export, per a ballpark figure management provided reluctantly, noting it does not typically share that breakup.
Zanzaria: "This is the highest order backlog which company has achieved and gives a strong visibility of revenue for next few years."
HVDC Opportunity
- Two near-term packages in finalization: The Fatehpur Bhadla and Khavda-Nagpur HVDC projects are in the finalization process at the developer level and are expected to be decided within 3 months. GE Vernova is participating.
- Timing is beyond management's control: These large opportunities have been in process for more than a year. Management expects a decision within 3 months but acknowledged that if it shifts, it is beyond their control.
- HVDC wins would be additive, not substitutive: Any HVDC orders that materialize will come on top of the regular order inflow, not replace it.
- Capex is already in place: Taking one HVDC order will not require any additional specific large capex for delivery; the transformer capex needed for HVDC is already planned within the $8-10 million total capex budget for the next 12 months.
- Leh-Ladakh tender is live but distant: The HVDC Leh-Ladakh tender has been floated, but it will take time for submission. Management declined to discuss commercial strategy or localized supply chain discussions for the project.
- STATCOM indigenous clause is met: GE Vernova can bid for Power Grid STATCOM tenders with an indigenous clause because thyristors were assembled and tested in its Indian plant for the Champa-Kurukshetra Phase 2 project.
- Consortium structure and addressable share are undisclosed: Management declined to disclose whether HVDC orders are being pursued in consortium with the parent company, calling it commercial strategy, and said it is very difficult to put a percentage on the addressable component of total project value given multiple variables.
Zanzaria: "These large opportunities has been going on for last more than a year, so we expect now to get decided within 3 months, but if it shifts beyond 3 months, it is beyond our control, actually."
Margin & Profitability
- Gross margin stepped up meaningfully: Q2 gross margin reached 41%, and H1 gross margin improved to 40.8% from 34% in the prior-year period, driven by better pricing in the domestic market, accretive export orders, and improved profitability in some business lines.
- Operating leverage is flowing through: Other expenses as a percentage of revenue fell from 13.7% to 11.9%, an approximately 2-percentage-point reduction, as revenue grew 60% YoY. Employee cost as a percentage of revenue also declined YoY despite volume growth and wage hikes.
- Gross margin guidance is 35-40% quarterly, with full-year ambition to beat last year: Management maintains a 35-40% range on a quarter-to-quarter basis, but on a full-year basis the endeavor is to do better than last year's ~35.6%.
- Other income was a drag this quarter: Other income was lower partly because most of the cash pool balance was generated late in the quarter and may not have been fully eligible for interest for the entire period; it also includes a forex loss of approximately ₹5.5 crore netted off.
Kumar: "I still maintain that range of 35% to 40% as range on a quarter-to-quarter basis. But on the full year basis, we always said that we want to do better than what we did in the last year."
Related-Party Transactions & Cash Management
- Large related-party orders materialized and were booked: Orders for which shareholder approval was taken, exceeding the ₹300 crore materiality limit, were booked and declared to the stock exchange in August and September. These included orders from Grid Solutions SAS plant and Grid Solutions Middle East FZE, Dubai.
- Cash pool arrangement expanded: Shareholder approval was obtained to lend up to ₹700 crores to related parties in a cash pool arrangement. Cash generation was strong at 290 crore in Q2 and 450 crore in H1 before dividends, with the cash balance improving to 680 crore from 280 crore as of March 2024.
- Pipeline of future related-party orders is undisclosed: Regular orders from related parties below the materiality limit are approved by the Audit Committee, but management did not address whether there is a forward pipeline of large related-party orders when asked.
- Technology access from parent is unrestricted: Management stated there is no limitation to get any technology from the parent if it is available and needed in the country.
Industry Demand & Pipeline
- Data center opportunity is strong: The pipeline on the data center side is "pretty good" with multiple opportunities. There are also a few opportunities on the steel side.
- Wide Area Monitoring System is too early to size: Discussions are ongoing at the Power Grid and ministry level, but after scope finalization and technology decision it will be possible to put a value to the opportunity. Today it is too premature to even put a value.
- Domestic backlog breakup is not disclosed: Management said it does not have the utility-versus-industry breakup of domestic backlogs immediately and does not share that level of detail in a public forum.
Zanzaria: "India's renewable energy capacity has surged to nearly 210 gigawatts (GW) from just 76 GW in 2014, and the country is well on track to achieve its ambitious target of 500 GW by 2030."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| HVDC award decision | Fatehpur Bhadla and Khavda-Nagpur packages to be finalized | Within 3 months |
| Gross margin | 35-40% quarterly range; full-year endeavor to beat last year's ~35.6% | FY25 full year |
| Capex | Approximately $8 million to $10 million total | Next 12 months |
| HVDC capex sufficiency | No additional specific large capex required to deliver one HVDC order | Already planned |
| Order inflow run-rate | ~₹5,500-5,800 crore annualized base, plus ~₹3,000 crore large orders = ₹7,800-8,200 crore range (mathematical representation, not guidance) | FY25 full year |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Revenue | ₹1,110 cr, up 59% YoY |
| Gross margin | 41%, vs 35.6% in FY24 |
| EBITDA | ₹210 cr (18.8% margin), up ~3x YoY from ₹70 cr; margin up 8.8 ppt YoY |
| Profit before tax | ₹193.8 cr (17.5% margin), vs ₹50.3 cr (7.2% margin) in Q2 FY24 |
| Order bookings | ₹4,680 cr, up 333% YoY |
| Order backlog | ₹9,840 cr, up 57% from ₹6,270 cr as at Mar'24 |
| Cash and cash equivalents | ₹680 cr as at 30th Sep 2024, vs ₹280 cr as at 31st Mar 2024 |
| Net debt | ₹10 cr as at 30th Sep 2023 |
| Cash generated (before dividend) | ₹290 cr in Q2; ₹450 cr in H1 FY25 |
| H1 FY25 revenue | ₹2,060 cr, up 46% YoY |
| H1 FY25 gross margin | 40.8%, vs 34% in H1 FY24 |
| H1 FY25 EBITDA margin | 19.5%, vs 9.4% in H1 FY24 |
| Export order share (Q2) | 53% of order bookings |
| Export revenue share (Q2) | 29% of revenue |
| Order backlog mix: private segment | 62% of ₹9,840 cr backlog |
| Order backlog mix: central utilities and PSUs | 32% of ₹9,840 cr backlog |
| Order backlog mix: state utilities | 6% of ₹9,840 cr backlog |
| Other expenses as a percentage of revenue | 11.9%, down from 13.7% YoY |
| Forex loss | ₹5.5 cr, netted off against other income |
| Royalty to parent | ~1% of total company revenue in FY24 |
| Capex plan (next 12 months) | $8 mn to $10 mn total |