Happy Forgings Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/o9u379s1w4g1dm24qb2vd90r.pdf

Key Takeaways


Revenue Growth & Segment Dynamics

Ashish Garg: "So CV alone, we are expecting almost 35%, 40% growth this year for us because of the new programs and the new ramp-ups, which is ongoing."

Product Mix Transformation & New Business Wins

Ashish Garg: "If you look at the product price that we today cater is around Rs.60,000. We are working on the projects where the product price is around Rs.25 lakh starting from currently, the heaviest component we do is roughly around 200 kg. And going forward, we are talking about 2 tons. So that's kind of a transformation shift we are talking about."

Margins & Cost Management

Ashish Garg: "So besides the steel price, we are expecting around 3.5% to 4% increase on selling price from our customers, for which our teams are in discussion. We have received the confirmation from a few OEMs. We are hopeful to get it from 1st of April."

Capex & Capacity Expansion

Ashish Garg: "Even if we move very fast, it depends because the infrastructure needs to be in place, which most of these OEMs are creating. So we are working hard to create the infrastructure, we are expecting that by Q4, we'll be ready. But then there is a development lead time and lead times expected as well, which will take 6 to 9 months to start our activities in terms of our revenues."

Market Share & Competitive Position


Guidance & Commitments

CommitmentSpecificsTimeline
Volume growthLate-teen volume growth for FY27FY27
EBITDA marginsBroadly in line with FY26 levelsFY27
Capex₹450–₹500 cr, directed at high-growth capabilitiesFY27
CV segment growth35–40% growth driven by new programs and ramp-upsFY27
CV export growthMid-single-digit growthFY27
Selling price increase3.5–4% increase from customers beyond steel pass-throughEffective April 1 (confirmation expected in 10–15 days)
Heavy forging capex completionInfrastructure for data center and heavy engine requirements completeEnd of FY27
Heavy forging revenue startTrials early FY28, revenue from Q2/Q3 FY28FY28
Solar plant benefitsPartial benefits from FY28, full thereafterFY28 onwards
Crankshaft contributionRise to 58–60% of mixFY28–29
Farm market shareImprove from 41% to 45%Not specified (implied near-term)
Product mix shiftCV from ~37% to ~27%, industrials from 11% to ~30–31%, PV from 6% to ~10%Not specified (implied medium-term)

Key Metrics

MetricQ4 FY26
Revenue from operations₹424 cr, +20.4% YoY
Full-year revenue from operations₹1,546 cr, +9.8% YoY
Volume growth+20.6% YoY
Realization~₹245 per kg, stable YoY and QoQ
Gross margin59.4%, +70 bps YoY
EBITDA₹133 cr, +30.4% YoY
EBITDA margin31.5%, +240 bps YoY
PAT₹84 cr, +23.6% YoY
PAT margin19.7%
Other income₹6 cr, vs ₹10 cr in Q4 FY25; impacted by ~₹4.5 cr adverse forex
Cash flow from operations (FY26)~₹445 cr
Total liquid assets~₹430 cr
Capex deployed (FY26)~₹460 cr
Expected capex (FY27)₹450 cr to ₹500 cr
Machining contribution89% of revenue in FY26, vs 87% in FY25
Machining capacity68,000 metric tons, including 9,800 metric tons added in Q3 FY26
New order book~₹950 cr, executable over 2.5–3 years; realization of ₹340–₹350 per kg
Heavy business order book (data center)₹250 cr, component weight 700 kg to 1.8 tons
Commercial vehicle revenue share (FY26)37%
Farm equipment revenue share (FY26)32%
Industrials revenue share (FY26)14%
Off-highway revenue share (FY26)11%
Passenger vehicles revenue share (FY26)6%
Q4 domestic CV growth+27% YoY
Q4 export CV degrowth-25% YoY
Q4 industrials domestic growth+32% YoY
Q4 off-highway domestic degrowth-6% YoY
Q4 PV growth+35% YoY
Forging capacity147,000 tons, up from 125,000; expected 161,000 by FY27
Crankshaft contribution~50% of revenue in FY26, expected to reach 58%–60% by FY28–29
Solar power plant capacity35 AC megawatts, total outlay up to ₹170 cr; partial benefits from FY28