- Saudi Aramco approvals - 2 approvals secured, 9 forms across 2 categories
Delivered - At the Q2 FY27 call, management noted Saudi Aramco approvals: 2 approvals (sprinklers and sprinkler-related valves; deluge valves) and 9 forms across 2 categories, with firefighting monitors submitted for final consideration after FM certification. The Jalgaon facility holds the 9COM number for valves and sprinkler fire protection systems, allowing RFQ receipts for upcoming Saudi Aramco projects, and deluge valves were supplied to Ras Tanura Sea Island and an IGCC plant in Jazan.
- Thane additional facility - operational from next month (December 2026), adding water spray nozzle and open sprinkler capacity
Pending - At the Q2 FY27 call, management said another Thane facility is "getting operational from next month", increasing capacity for water spray nozzles and open sprinklers. As of 13 Nov 2026, the December 2026 date has not yet been reached and no completion disclosure is in the record.
- IPO listing - all steps for listing and trading within three Working Days of Bid/Offer Closing Date
Delivered - The DRHP stated all steps for listing and commencement of trading at the Stock Exchanges would be completed within three Working Days of the Bid/Offer Closing Date. The company listed on NSE & BSE on 21 Oct 2026, with an IPO subscription of 132X; the Chairman called the listing "a significant milestone".
- Thane (Wagle Estate) production facility and warehouse - completed by end of November 2026
Pending - At the Q2 FY27 call, management said the new Thane (Wagley Estate) production facility and warehouse was "expected to be completed by end of November this month", pushing the DRHP's March 2026 timeline. As of 13 Nov 2026, the end-of-November deadline has not yet been reached and no completion disclosure is in the record.
- Saudi Arabia local manufacturing - Phase 2 local assembly/manufacture of around 5 products
On track - At the Q2 FY27 call, management described Phase 1 as trading and Phase 2 as local assembly/manufacture of "around 5 products", with land acquisition "could take a few months" and better revenue visibility in "around 3-4 months"; the DRHP planned a local manufacturing presence within 1-2 years. A subsidiary, HD Fire Protect Company, was recently incorporated in Saudi Arabia, with trading to begin and leased land acquisition underway.
- Export contribution - around 5-6% higher export contribution vs last year in total revenue
Pending - At the Q2 FY27 call, management expected "around 5-6% higher export contribution compared to last year in the total revenue", driven by the pipeline and Middle East demand. H1 FY27 exports were 35.63% of revenue against FY26's 34.69% - about 0.94 percentage points higher, with FY27 not yet complete.
- MPCB consent for new Jalgaon expansion sheds - approval in coming months
On track - At the Q2 FY27 call, management said one new MPCB application was initiated and the second in process, expressing confidence in approval "in coming months" without affecting existing business or the FY26-27 revenue target; the company also stated it would reapply for Consent to Operate for the new sheds. MPCB refused the application on October 28, 2026 over Environment Clearance evidence; one corrected application was submitted, the second is in process, and existing-plant consent runs to March 31, 2029.
- Jalgaon facility expansion - manufacturing unit, fire test laboratory, warehouse and R&D centre completed by March 2026
Partial - The DRHP stated the Jalgaon expansion (one manufacturing unit plus fire test laboratory, industrial warehouse and R&D centre) was expected to be completed by March 2026, with ₹3.89 crore invested as of March 31, 2025 and ₹23 crore more planned over 12 months from internal accruals. The Q2 FY27 call described Jalgaon as expanded - in-house foundry, 5-axis machining, flow testing to 18,000 litres per minute - yet the PPT still shows the expansion as ongoing and MPCB refused consent for the new sheds on October 28, 2026 with no impact on existing production.
- Fluorine-free foam suppression system - UL certification and new range development
On track - At the Q2 FY27 call, management noted the fluorine-free (chlorine-free) foam suppression system had achieved UL certification and that the pre-action system for data centers has UL approval, with the PPT and DRHP showing a new fluorine-free foam equipment range in pursuit of UL Listing. The foam suppression system holds UL certification, while the new range remains in development with no UL Listing read yet.
- International market expansion - distributors and certifications in Malaysia, Indonesia, Singapore, Brazil, Colombia, Mexico, Spain, Italy
On track - At the Q2 FY27 call, management said it is pursuing additional international markets (Malaysia, Indonesia, Singapore; Brazil, Colombia, Mexico; Spain, Italy) via distributor appointments, end-user registrations and local certifications. New distributor partnerships are in place across Colombia, Argentina, Malaysia, South Africa, Saudi Arabia and Kuwait, and US supply has "just begun".
- Advanced deluge valve - UL Listing pursuit and product development
Pending - The Q2 FY27 PPT states the company is pursuing UL Listing for advanced deluge valves designed for both on-shore and off-shore installations, and the DRHP noted an advanced deluge valve with pressure reducing mechanisms in development. A new deluge valve range with fewer components, lighter build, higher efficiency and less friction loss is in R&D, with no UL Listing read yet.
- Saudi Aramco monitor approval - FM certification completed, submitted for final consideration
Pending - At the Q2 FY27 call, management said Aramco monitor approval had FM certification completed per Aramco spec and was submitted for final consideration, with a mandatory field test of minimum 1 year before acceptance per Aramco protocol. The firefighting monitors are submitted for final consideration, the 1-year field test window has not elapsed, and no final acceptance is disclosed yet.
- H2 FY27 revenue contribution - \~55-60% of annual revenue, implying H2 ₹580-590 cr
Pending - At the Q2 FY27 call, management agreed that \~55-60% of revenue comes in the second half and confirmed "we would be looking at similar revenue contributions" from the coming two quarters, Q4 highest, with the analyst's H2 frame of Rs 580-590 crores at 60% H2 execution endorsed as correct. H1 FY27 revenue was ₹236.3 cr; Q3 FY27 is not yet reported and the H2 window is in progress.