Key Takeaways
- Weak quarter, cyclical trough: Revenue fell to Rs.671 Cr and PAT to Rs.98 Cr YoY as global steel production stayed subdued; management expects this softness to persist for the next two to three quarters.
- Margins under marginal spread pressure: EBITDA declined to Rs.178 Cr, and spreads are compressing because needle coke prices lag electrode price falls due to inventory and processing cycles.
- Capacity expansion nearly complete: Four of five processes for the 20,000-tonne expansion are running; the fifth is delayed by a small equipment breakdown but should be operational by end-September 2023.
- Graphite anode diversification on track: The TACC subsidiary's pilot plant has started, land is acquired, and the project targets commissioning by H2 2025 with a 25-30% EBITDA margin expectation.
- What to watch next quarter: Whether the final expansion process commissions on time, the trajectory of electrode and needle coke spreads, and any early signs of the steel demand rebound projected for 2024.
Demand Environment
- Steel production anchor: Global steel output fell ~4% in H1 2023, directly suppressing graphite electrode demand; management expects this subdued environment to continue through end-2023.
- Recovery thesis rests on 2024: The World Steel Association projects steel demand to rebound and grow ~4% in 2024, which management cites as the basis for its confidence that electrode demand will return.
- EAF structural story intact: Western world EAF production (ex-China) is expected to add ~10 crore tonnes by 2030, with OECD projecting 5.3 crore tonnes of new capacity by 2026 and 4.5 crore tonnes from conversions by 2030. China is targeting 20% EAF steel production by 2025.
- No new western competition: No new graphite electrode capacities have been announced by any competitor in the western world, which limits supply-side risk when demand recovers.
- Current market weakness: Prices are under pressure and not stable; management corrected an analyst's assumption of price stability, stating markets are weak and expected to remain so for the next couple of quarters.
Margins & Spreads
- Spread mechanics under pressure: When electrode prices fall, needle coke prices take longer to adjust because of supplier inventories and HEG's own processing cycle, creating a lag that compresses spreads marginally.
- Near-term margin outlook: Management explicitly guided that the next two to three quarters may see margins come under some pressure.
- No inventory losses: Despite holding higher-than-normal inventory, management confirmed no inventory loss in Q1 or Q2 because pricing remains above cost of goods sold.
- Conscious inventory build: HEG is holding 2.5 months of inventory versus a normal 1-1.5 months, a deliberate strategy to have additional product ready to sell when the market turns, given that electrodes take 45 days and nipples take 5 months to produce.
- Needle coke supply abundant: Global needle coke availability is plentiful, with peer group capacity running at only 45-50% utilization, which keeps raw material costs in check but also signals weak downstream demand.
Gulati: "when the price is coming down for both electrode and needle coke, needle coke takes longer to absorb it takes longer to their price to take effect just because of inventories and our processing cycle so that way I would say that the spread is under pressure because not too much but yes it is under marginal pressure"
Capacity Expansion
- Near-complete status: Four of the five processes for the 20,000-tonne expansion have been in operation for several months, using what management describes as some of the best and most modern equipment and technologies.
- Final process delayed: A small equipment breakdown on the fifth process required a replacement part from Bengaluru, pushing full commissioning out by three to four weeks to end-September 2023.
- Utilization guided lower: Q1 utilization was closer to 90% on the 80,000-tonne capacity, but full-year utilization is expected at 80-85% because Q3 and Q4 will see subdued demand.
Ravi Jhunjhunwala: "it has been a very small breakdown of a very small piece which is being replaced and it is coming from Bengaluru and it is a matter of another maximum three to four weeks and by end of next month we should be in business."
Graphite Anode Diversification
- Project progress: The TACC subsidiary's pilot plant has started, enabling customer trials; 100 acres of land have been acquired; all machines have been selected for import from 4-5 large Chinese companies; environmental and other clearances have been applied for.
- Timeline: Management targets commissioning by Q1 2025, with operations beginning in H2 2025 for the first phase of 10,000 tonnes of graphite anode powder for lithium-ion batteries.
- Project economics: Total project cost estimated at approximately Rs.800 Cr for 10,000 tonnes; selling price assumption of $8,000-10,000 per tonne; management expects 25-30% EBITDA margin.
- Demand visibility: Indian anode demand projected at 50,000-60,000 tonnes by 2025 and around 300,000 tonnes by 2030 based on cell company announcements; HEG's 10,000-tonne capacity can serve either domestic or export markets.
- ROI undisclosed: Management declined to provide ROE or IRR figures, stating the project is still two years from completion.
Riju Jhunjhunwala: "The project cost should be approximately 800 Crores which will produce 10000 tonnes of anode. The current price of that being in the region of 9000 to 10000 tonne, so obviously then you can do your math based on that selling price which will take similar prices of raw material that we have in our graphite electrode price, so the IRR, etc., we are expecting 25-30% EBITDA in this particular project."
Industry Structure & Competitive Position
- Concentrated industry dynamics: Only 5-6 players exist in the graphite electrode industry and 4-5 in needle coke; management characterizes it as a tandem market where participants move in coordination rather than a fragmented commodity market.
- China needle coke opaque: Management declined to quantify Chinese needle coke supply, noting it spans multiple types (pitch coke, petroleum coke, quota-based cokes) and is "a large number" but impossible to size precisely.
- Domestic needle coke uncertain: On Reliance Industries' and Indian Oil's needle coke efforts, management noted they have been trying but "what kind of product they eventually come with remains to be seen," offering no visibility on whether they will become viable raw material sources.
Ravi Jhunjhunwala: "There are only 5-6 players in the graphite industry, there are only four or five players in the needle coke industry so everything works in tandem, it is not a commodity where there are hundreds of customers or there are hundreds of suppliers everybody works in tandem with each other."
Bhilwara Energy
- Project pipeline: Four different projects totalling around Rs.120 Cr are closing by end-FY24; the business is on track for approximately Rs.400 Cr of projects this year.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capacity expansion completion | Fifth process commissioned, full 20,000-tonne expansion operational | End-September 2023 |
| Full-year capacity utilization | 80-85% of 80,000-tonne capacity | FY24 |
| Margin pressure | Margins under pressure for next two to three quarters | Q2-Q3 FY24 |
| Graphite anode project commissioning | First phase of 10,000 tonnes operational | H2 2025 |
| Graphite anode project EBITDA | 25-30% EBITDA margin | At project commissioning |
| Bhilwara Energy project closures | Four projects totalling ~Rs.120 Cr closing | By end-FY24 |
| Bhilwara Energy full-year target | ~Rs.400 Cr of projects | FY24 |
Key Metrics
| Metric | Q1 FY24 |
|---|---|
| Revenue from operations | ₹671 Cr, vs ₹722 Cr in Q1 FY23 |
| EBITDA | ₹178 Cr, vs ₹205 Cr in Q1 FY23 |
| Standalone net profit after tax | ₹98 Cr, vs ₹134 Cr in Q1 FY23 |
| Consolidated net profit after tax | ₹139 Cr, vs ₹159 Cr in Q1 FY23 |
| Treasury size | ~₹980 Cr as on June 30, 2023; company is long-term debt free |
| Capacity utilization | ~90% on 80,000-tonne capacity; full-year expected at 80–85% of 80,000 tonnes |
| Finished goods inventory | ~2.5 months of sales, vs normal 1–1.5 months |
| Graphite electrode capacity expansion | 20,000 tonnes per annum addition, taking total capacity from 80,000 to 100,000 tonnes; last process under trial |
| Graphite anode project (TACC) | 10,000 tonnes first phase, expected mid-2025; project cost ~₹800 Cr |
| Graphite anode selling price | $9,000–$10,000 per tonne current range; expected EBITDA margin 25–30% |
| Needle coke industry capacity ex-China | ~650,000 tonnes |
| Global graphite electrode industry utilization | 60–70% |
| Electric arc furnace steel production growth ex-China | 43.5 Cr tonnes in 2022, up from 35.7 Cr tonnes in 2015; expected to reach 53.5 Cr tonnes by 2030 |
| Additional graphite electrode demand from EAF growth | 160,000–190,000 tonnes by 2030 |
| China EAF steel share | 12% currently, up from ~5% five years ago; targeting 20% by 2025 |