HEG Advanced Materials Ltd Q3 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/fn56nubhil8x7o2azb1j3107.pdf

Key Takeaways


Volume & Demand: The Slowdown Mechanics

Manish Gulati: "This 70% capacity utilization, which we are talking about January to March is likely to continue for at least two more quarters. The major reason for this lower capacity utilization is the drop in steel demand, drop in steel consumption."

Inventory Gamble: Converting Coke While Demand Is Soft


Pricing & Spreads: A Managed Squeeze

Manish Gulati: "In Q1 next year, as we are booking now, we are facing some pressure on that. But that pressure is not like any big fall or any big it is just that everybody is trying to sell that extra ton it makes -- puts pressure on the pricing."

Capacity Expansion: Running Late but Close


Graphite Anode: The Diversification Bet

Riju Jhunjhunwala: "So the technical expertise largely resides within HEG itself. A lot of the processes that are involved in converting carbon into graphite, which is what our USP is in HEG, how to -- because not too many people can do that. That is the single most challenging factor in this anode thing as well."

EAF Structural Tailwind: The Decade-Long Story

Ravi Jhunjhunwala: "We do have a 4%, 4.5% CAGR on electric arc furnace steel production, which is currently close to 50%, let's say, 49%. So doing that math in the next four, five years, would lead to an additional demand of close to anywhere in the region of 200,000 tons, which is a very, very huge number. I mean we haven't seen this kind of growth in the demand of electrodes in the last 20, 30 years."

Guidance & Commitments

CommitmentSpecificsTimeline
Electrode expansion completionFull 100,000-ton capacity operational after trials and stabilizationMid-April 2023
Capacity utilization~70% utilization sustainedAt least two more quarters (from Jan–Mar 2023)
Finished-goods inventory rundownGradual reduction from ~₹400 crores / two months of stockOver the next four quarters
Graphite anode Phase 110,000-ton facility operationalQ2 CY2025
Graphite anode Phase 1 capex₹1,000 crores deployedAhead of Q2 CY2025
Electrode pricing pressureSome pressure as Q1 orders are booked, but no major fall expectedQ1 FY24 order booking window

Key Metrics

MetricQ3 FY23
Revenue from operations₹530 cr, down 11% QoQ and YoY
EBITDA including other income₹170 cr, vs ₹198 cr QoQ and ₹171 cr YoY
Net profit after tax₹103 cr, vs ₹130 cr QoQ and ₹109 cr YoY
Treasury size₹1,015 cr, long-term debt free as on 31 Dec 2022
Capacity utilization~60%, vs ~85% in Q3 FY22; Q4 FY23 running at ~70%
Exports share of sales~65–70% of overall sales
Europe plus Turkey share of sales~14%, with Europe at ~10% of total sales
Finished goods inventory~2 months of production, vs normal ~1 month
Expansion capex spent~₹1,000 cr out of ₹1,200 cr total; ~₹200 cr remaining
Expansion capex per ton~$8,000 per ton (per management); ~₹6 lakhs per ton (per an analyst's math)
Graphite anode Phase 1 capex₹1,000 cr approved for 10,000 tons per annum facility
Graphite anode Phase 1 capacity10,000 tons, catering to 10 GWh of cell manufacturing
Expected Indian battery demand by 2025~50 GWh, translating to ~50,000 tons of graphite requirements
Expected Indian battery demand by 2030260 GWh
Global steel production decline CY22 vs CY214.4%; excluding China, decline was ~7%
EAF steel production share ex-China49%, up from 47% in the last 3–4 years
EAF capacity commissioned in US, last 12 months0.7 crore metric tons
EAF capacity to be commissioned in US, now to mid-20251.4–1.5 crore metric tons
EAF capacity to be commissioned in Europe2–2.5 crore metric tons, a couple of years behind the US
Additional electrode demand from EAF growth, next 4–5 years~200,000 tons
Graftech Mexican plant closure~2–2.5 months; 100% of nipple production was at that plant
Graftech sales tonnage vs normal40–50% of normal sales
Turkey share of HEG tonnage~6–7% currently, down from ~11–12% annually
Turkey March quarter tonnage vs December~half of December quarter tonnage
Capacity utilization outlook~70% likely to continue for at least two more quarters
US steel production via EAF70–75%; another 2 crore (2.5 crore) tons of EAF capacity being added
Competitor capacity utilization~68% for one major competitor
Needle coke procurement statusNo purchases in last 3–4 months; last shipment more than 4 months ago
Total new EAF capacity, Europe and America3–3.5 crore tons