Key Takeaways
- Costs overwhelmed price gains: Power and fuel costs surged ~₹620/tonne more than realization improvements, compressing EBITDA/tonne from ~₹1,100 in Q1 FY22. Management believes fuel inflation has peaked.
- Volumes declined 6% YoY as the company deliberately held back shipments to avoid locking up cash in a liquidity-stressed market, particularly during a weak May.
- Fuel mix agility provided partial relief: A rapid shift toward petcoke when coal prices spiked limited damage, and management expects easing coal availability ahead.
- Green power share hit a record 30%, with more solar coming online, which should help cap landed power costs even if grid prices rise.
- What to watch next quarter: Whether the promised Q2 fuel cost softening materializes, whether volumes recover toward the 7-8% full-year target, and any concrete steps on the group simplification or Gujarat project timeline.
Cost Structure & Margin Pressure
- Power and fuel: the dominant headwind. Total cost rose 24% YoY, driven by power at ₹460/tonne and fuel at ₹1,410/tonne. Realization improved only ~13%, leaving a large gap that crushed EBITDA per tonne.
- Coal cost spike was the sharper blow. Coal per-kcal cost jumped from ₹2.30 in Q4 FY22 to ₹3.25 in Q1 FY23; petcoke rose from ₹2.50 to ₹3.10. The steeper coal increase triggered an immediate fuel mix rejig to 38% coal, with petcoke taking a higher share.
- Fuel cost peak called. Management stated fuel inflation peaked in Q1 FY23 and expects costs to be a little softer in Q2, though this remains dependent on market conditions.
- Coal sourcing was entirely domestic open-market in Q1, with zero FSA (linkage) coal received. Cost reduction is expected once linkage coal starts arriving, but timing depends on Coal India diversion from power plants and rake relocation and cannot be predicted.
- Russian coal is a supply-side relief valve, not a direct input. Russian coal at ~$170/tonne (20-25% cheaper) may pressure other origins to reduce prices. For landlocked Central India, Russian coal is not directly usable, but increased imports by coastal players could relieve domestic coal supply tightness, improving availability.
- Landed power cost held at ₹6.50/unit including cheap solar power. As more solar comes online from long-term agreements and own plants, average landed power cost is expected to remain almost flat, nullifying any grid price increases.
Management: "Let us not build our hopes on cheaper but let us say easy availability. Today you are struggling for coal. Sometimes you wonder, after five days whether the coal material will come or not or we are going to run into a dry situation?"
Volume & Demand Dynamics
- Volumes declined 6% YoY, the third consecutive quarter of decline. Management attributed this to a high base (38% growth in Q1 FY22, which Central India peers did not match), a deliberate price-volume trade-off amid a liquidity crunch, and acute stress in May.
- The liquidity-driven volume sacrifice was intentional. The company did not want to push material and lock up money when some payments were getting delayed, even though those delayed payments were eventually recovered.
- May was the trough; June improved; July slightly better. Management stated the situation that caused volume pressure in May has been overcome and will not repeat in Q2.
- Government-side demand weakening in the non-trade segment (~30% of market) is indirectly pressuring prices in certain areas, even though Heidelberg does not supply there directly.
- Full-year volume growth targeted at 7-8%, aiming for 1% above the 7.3% GDP forecast. The Q1 shortfall is expected to be made up in coming quarters.
- No cement inflow from South India into Central India currently. Some inflow from the East (Konark Cement) persists but is less severe than 1-1.5 years ago, because freight subsidies have reduced and costs have risen for everyone.
Management: "Because of the liquidity crunch in the market, we did not want to push in too much of material just only to get the money locked in. Because there have been incidences where some money got delayed, but we could recovered it."
Pricing Strategy & Realization
- Realization improved ~13% YoY, which management described as looking good versus peers. The improvement was driven by premium product contribution, a narrowing trade/non-trade price gap, and an 82% trade mix that helps inch up premiums over time.
- Central India prices stayed in a narrow ₹360-380/bag range. Price hikes were taken in April, but management declined to quantify the micro-level April hike quantum or how much stuck through May-July.
- Pricing strategy is opportunistic and granular. The day-to-day approach: if daily order targets are exceeded, attempt ₹1-2/bag increases. No reliance on large step-hikes. Post-monsoon price hike possibility remains uncertain.
- Premium product price gap is being widened deliberately. Management plans to keep widening the gap between normal and premium products over a 5-10 year horizon, and the gap was widened further within Q1.
- Trade vs non-trade gap narrowed, and management noted some merit in selling a little more non-trade in the current environment.
Management: "We don't leave a single day opportunity to take that money."
Green Power & Sustainability Milestones
- Green power share reached a record 30%, the highest ever, driven by 15 MW renewable at Jhansi (operational from March), 12 MW WHR plus 5.5 MW solar at Narsinghgarh, and ~90% green power at Ammasandra.
- Water positivity improved to 4.4x, with plans to improve further. A good monsoon would allow far more rainwater harvesting and improve the trajectory.
- Patharia mines won first prize under Environment categories from the Chief Minister of Madhya Pradesh.
Strategic Initiatives & Digital
- WhatsApp chatbot launched, claimed as first in the cement industry globally. It addresses consumer dilemmas: locating authorized dealers via pin code, displaying suggested retail prices (ex-shop), booking customer service vans, registering complaints, and applying for dealerships.
- The chatbot will expand as management wants to establish WhatsApp for business as the order of the day. Too early to assess impact on pricing.
- Revenue reclassification now groups other operating income (~₹8 crore/quarter) under revenue, aligning with annual audited accounts and peer practice.
- Tax migration to the lower corporate tax rate was completed this year and accounted for in planning and results.
Balance Sheet, Capex & Expansion
- Working capital remained negative, and collections were managed on time despite the liquidity pushback, though debtors increased slightly in some weeks or months. Management emphasized zero bad debts in company history.
- Gujarat expansion: SEZ clearance received in June/July 2022. The TOR (Terms of Reference) application is now proceeding; TOR studies will take ~1-1.5 years. No construction activity possible until TOR is complete, so project start is at least 2 years away.
- Gujarat plant capex pegged at ~₹2,500 crore total, with ₹1,000 crore from internal cash and ₹1,500 crore to be raised via debt or group push-down if cheaper. Net worth and free reserves expected at ~₹1,500 crore by funding time, with debt-to-equity not exceeding 1:1. No formal net debt/EBITDA target was given.
- FY23 capex guidance unchanged at ₹50-60 crore, with debottlenecking plans unchanged. FY24 capex expected similar (~₹100 crore), plus Gujarat land acquisition spend depending on permits.
- MP incentive: ₹30 crore approved and accounted in the March 2022 quarter, with a recurring ₹5 crore/quarter accrual continuing until February 2023.
- Fuel inventory currently below 25 days; target is to maintain 30-35 days.
Management: "We have till date in the history of our Company we have not had a single bad debt in these so many years."
Parent Strategy & Group Structure
- Parent is firmly committed to India, viewing it as a foundation for other building materials (Heidelberg is #1 in aggregates globally). Management stated the group asks about new investment opportunities every time they engage, and there is no intent to divest.
- Group simplification / Zuari merger is under internal discussion, with the finance team talking to the group. No regulatory steps have been filed yet. Management described it as "always on the cards" but gave only a vague timeline: "might take up maybe some time."
- Recession contingency planning is underway. Management sees an imminent risk of global recession and is making a Plan B for how to manage the business if one triggers.
Management: "Every time they ask us if there are any opportunities where we can invest more. So, of course, we are not able to provide them those opportunities."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Full-year FY23 volume growth | 7-8% (1% above 7.3% GDP forecast), making up Q1 shortfall | FY23 |
| Fuel cost trajectory | Peaked in Q1 FY23; expected to be a little softer | Q2 FY23 |
| Power cost | Not expected to go up further; solar additions to keep landed cost flat | Ongoing |
| Gujarat plant construction start | At least 2 years away (TOR studies take 1-1.5 years after application) | FY25 or later |
| Gujarat plant capex | ~₹2,500 crore total; debt-to-equity not exceeding 1:1 | At funding time |
| FY23 capex | ₹50-60 crore, debottlenecking plans unchanged | FY23 |
| FY24 capex | ~₹100 crore plus Gujarat land acquisition spend (permit-dependent) | FY24 |
| Premium product price gap | Keep widening vs normal products | 5-10 year horizon |
| Group simplification / Zuari merger | Internal discussions only; no regulatory steps filed | Vague ("might take up maybe some time") |
Key Metrics
| Metric | Q1 FY23 |
|---|---|
| Revenue | +13% YoY realization increase; total cost up 24% YoY |
| EBITDA per tonne | ₹1,100 in Q1 FY22; power and fuel cost increase took away ~₹620 per tonne of price gain |
| Net cash | ₹220 crore |
| Bank balance | ₹458 crore |
| Capacity utilization | ~72% |
| Volume decline | 6% YoY |
| Full-year volume growth target | 7–8% (management target, despite Q1 decline) |
| Premium cement growth | 6% YoY |
| Premium brands share of trade | ~23% |
| Trade share of volumes | 83%; non-trade 17% |
| Power cost per tonne | ₹460 |
| Fuel cost per tonne | ₹1,410 |
| Power cost per unit | ₹6.50 |
| Fuel mix | 38% coal, petcoke higher share |
| Per-kcal cost: coal | ₹3.25, up ~₹1 QoQ |
| Per-kcal cost: petcoke | ₹3.10, up ₹0.50–0.60 QoQ |
| Green power share | 30%, highest ever |
| CO2 footprint | 511 kg per tonne of cement |
| Water positivity | 4.4 |
| Other operating income | ₹5.5 crore (grouped under revenue); recurring quarterly range ₹7–9 crore |
| FY23 capex guidance | ~₹100 crore, including debottlenecking |
| Gujarat project estimated cost | ~₹2,500 crore; ₹1,000 crore from internal cash, ₹1,500 crore to be raised |
| Fuel inventory | lower than 25 days; target 30–35 days |
| Central India cement price | ~₹380 per bag; Lucknow ₹360–370, Bhopal ~₹370 |
| Russian coal price | \$170 per tonne; landed cost for South India CIF below ₹3 per kcal |