HeidelbergCement India Ltd Q2 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/n32sraar7nuy0xbav2u4urdt.pdf

Key Takeaways


Volume & Demand Environment

Cooper: "It is unfortunate that, you know, we had to suffer because we are focused more on Central India. Now at this point of time, we possibly think that had we had some market share in Bihar, probably, we would have done better."

Costs & Margins

Cooper: "On cost side, it is not, we are not so bad, but it is basically the fuel which has killed us at this point of time."

Pricing & Realization

Management: "The volume game is fine. Okay. Ultimately, it is the profit which you earn out of the business, sustainability of the cash flows. You know, today we are not understanding this very simple thing that compliances will grow. Okay, and compliances will require CAPEX, and this CAPEX is when you will have totally dried out on your cash reserves, then where will you go for this? It is high time the industry wakes up to this call."

Product & Brand Strategy

Management: "We have a very, very, very, very transparent discount structure. Probably, you won't find this in any other, anyone in the country. We on 1st of January issue a discount policy giving each and every discount in writing to the dealer and the dealer acknowledges, signs the copy of it, and hands it over to us."

Capacity Expansion & Competitive Landscape

Management: "Adani family is totally a pure B2B businesses. Most of their business is their DNA as I understand... their margins, they are operating on products where the margins are more than 50%. How will they satisfy with margins of 16% and 18% here? I don't think they would like to be in such a state."

Guidance & Commitments

CommitmentSpecificsTimeline
EBITDA recoveryQ2 EBITDA per ton of ₹476 is the bottom; expects to bounce backQuarters going forward
Post-Diwali price increases₹4–5 already taken; more expected depending on order booksPost-Diwali
Fuel cost trendMarginal tapering down or at least stability at current levels; no sharp increaseH2FY23
Debottlenecking Phase 1~3 lakh tons clinker, ~4.5 lakh tons cement (both lines)FY24
Debottlenecking Phase 2Second phase of debottleneckingFY25
Gujarat greenfield Phase 1~0.35 crore tons capacity, CAPEX a little more than €200 mn; environmental clearance expected by May–JunePlant start FY27
Replacement CAPEX~₹50 crores (50% of depreciation cost)FY23
Central India demand growthNot less than 8–8.5% (~0.5 crore tonnes incremental)Next year (FY24)

Key Metrics

MetricQ2 FY23
RevenueNot stated
Volume-19% YoY and -10% QoQ
Realization+8% YoY, slightly down QoQ
EBITDA per ton₹476, 50% lower YoY (₹946 in Q2 FY22)
Operating marginNot stated
Net debt₹10.9 cr as on date
Cash and bank balances₹237 cr as on September '22
Total debt₹234.6 cr
Dividend per share₹9, already distributed
Interest expense₹20.6 cr, including ~₹10 cr one-off litigation provision
GST incentive booked~₹5 cr, normal quarterly amount
Premium products share in trade sales55%, up from 20–25% previously
Trade sales share83% (Q2 FY22 restated to 86% due to reclassification)
Sales volume split: rail vs road50-50
Fuel mix: petcoke69–70%; coal 31%
In-house / green power share34% of power consumption
Ammasandra plant green power>90%
Fuel consumption cost₹714 per Gigajoule, ₹3.13 per kilo cal, slightly lower vs Q1
Capacity utilization~78–79%
Lead distance~250–350 km, consistent
Gujarat project Phase 1 capacity0.35 cr tons, CAPEX ~€200 mn, start FY27
Debottlenecking: clinker addition~3 lakh tons; cement ~4.5 lakh tons, Phase 1 in FY24, Phase 2 in FY25
Central India demand growth expectation (next year)Not less than 8–8.5%, ~0.5 cr tons incremental demand
Replacement CAPEX~₹50 cr, 50% of depreciation