Key Takeaways
- Turnaround quarter, but still in the red: Revenue rebounded to ₹871 crore from a trough of ₹801 crore in Q4, but PAT remained negative at ₹-29 crore as the optical fibre cable business began recovering from a prolonged slump.
- OFC poised to double, driving the FY26 story: Management expects the optical fibre cable business to more than double revenue to ~₹2,400 crore in FY26, fueled by a global demand resurgence and a sharp rise in high-count IBR cables for hyperscale data centers.
- Defence is finally moving from promise to production: A landmark thermal weapon sights contract is supplying now, electronic fuze live testing is set for August, and a drone detection radar is nearing field trials, with management targeting ₹200-plus crore in defence revenue this year.
- PLI miss is a self-inflicted credibility dent: Management admitted it will receive zero PLI this year after projecting ₹40–50 crore, calling it "our mistake" for setting targets too high, a rare admission that undercuts forward guidance.
- What to watch next quarter: Whether the August DRDO fuze trials succeed, the pace of OFC capacity expansion revenue, and whether Q2 can turn PAT positive after two quarters of losses.
Optical Fibre Cable: The Recovery Engine
- Demand resurgence after a deep slump: Global OFC demand was subdued for six to seven quarters, cutting revenue to roughly 40% of expected levels, a phenomenon that hit the entire industry including Corning and Prysmian. That cycle has now turned, with telco inventories largely depleted and data center operators carrying no inventory at all.
- Hyperscale data centers are the new demand driver: An unprecedented build-out of hyperscale facilities, particularly in North America and Europe, is driving a sharp surge in high-count fibre cable, especially Intermittently Bonded Ribbon cables carrying 728 or 884 fibres, a product few manufacturers can produce. HFCL already holds a strong order book for IBR cables with a very robust pipeline of additional opportunities.
- Capacity expansion is already underway: The Board approved expanding IBR cable capacity from ~0.17 crore fkm to ~1.9 crore fkm per annum, taking total OFC capacity from ~2.51 crore fkm to ~4.24 crore fkm. Machines are arriving from Austria; one is expected in days, and full completion is targeted by June 2026, with revenue from the expansion starting this financial year.
- Export momentum is building: Secured export orders worth ~₹300 crore and achieved export revenues of ~₹210 crore in Q1. High-value fibre products are gaining traction in European and Asian markets, and more than 50% of the targeted ₹2,400 crore OFC revenue this year is expected to come from exports.
- Margin recovery tied to volume and mix: Margins had declined because low demand forced manufacturers to sell at lower prices. Now demand has returned, prices have risen, and the shift toward high-technology IBR cables that few can produce is improving the margin profile. OFC margins are roughly 15%, higher than telecom products.
Mahendra Nahata: "With the strong traction we are experiencing particularly from international customers, we are confident that our Optical Fibre Cable business is poised to more than double its revenue in FY26 compared to FY25."
Defence: From Pipeline to Production
- Thermal weapon sights are shipping now: A landmark contract for thermal weapon sights for AK-203 rifles is already supplying to the Eastern Command, with more supply possible within the current quarter. A separate ₹45 crore night vision order has all approvals in place and management is trying to start supply in Q2.
- Electronic fuzes hinge on an August test: Live testing of electronic fuzes for artillery guns is scheduled for August by DRDO, after a long delay caused by ammunition unavailability from government-owned Munition India Limited. HFCL paid for the ammunition over six months ago; it has now arrived. If trials succeed, revenue could begin in the last quarter of this financial year, and management insists orders will not be a problem. A previously confirmed ₹700 crore export order for fuzes could not proceed because ammunition was not supplied.
- Drone detection radar nearing field trials: The system now includes a soft kill option alongside detection. Lab trials are almost complete, with field trials expected in the latter part of August. If successful, production is expected within the current financial year, with demand seen in India and internationally.
- DRDO partnerships are stacking up: Two Technology Licensing Agreements signed for Compact Transhorizon Communication Systems and Multi-Mode Hand Grenades. The company is in advanced stages of securing technology transfers for Mechatronic Fuzes, Weaponised Handheld Thermal Imagers, and Compact Airborne Multi Sensor Optronic Payload for UAVs. It has also applied for ToTs for UAV-Launched Precision Guided Missiles and Very Short Range Air Defence Missiles.
- UAV and export opportunities emerging: Three MoUs signed with UAV manufacturers to co-develop next-generation unmanned aerial platforms and weaponized drones. The Paris Air Show generated significant engagement from global defence OEMs, opening avenues for international collaboration and exports.
- Revenue is starting, but pace depends on test outcomes: Management's best estimate is ~₹200-plus crore in defence revenue this year. The defence factory has been commissioned. But the timeline is fragile: if the August fuze trials fail, ammunition deliveries would take another two to three months, pushing revenue further out. The BMP-2 upgradation tender has been postponed twice, now set for 29 September.
Mahendra Nahata: "If the trials of August are successful, then we can start getting revenue from the last quarter of the current financial year also for fuzes because after trials are successful, 2 or 3 months in starting production, should not take two or three months also. But definitely, if the trials are successful from the last quarter of this financial year, we should start getting revenue from fuzes. The orders are not going to be a problem, I can tell you."
Telecom Equipment: Routers and 5G
- Indigenous MPLS routers are a milestone: HFCL successfully developed indigenous MPLS Routers for backhaul, fibre broadband, and enterprise networks, becoming only the second Indian manufacturer after Tejas to do so. Commercial deployment has commenced in a domestic telecom network under real-world traffic conditions.
- BharatNet Phase III is the anchor order: Secured orders worth ₹650 crore for routers under the BharatNet Phase III programme, with management expecting significant additional orders as more states roll out implementation. Total BharatNet Phase 3 revenue is expected at roughly ₹800–1,000 crore this financial year.
- 5G equipment gaining repeat traction: A repeat order worth ~₹175 crore for indigenous 5G networking equipment was secured. Overall, ₹600 crore worth of locally designed and produced 5G products, primarily unlicensed band radios, have been supplied cumulatively.
- Delhi NCR factory ramping up: The facility is already producing, with 5G FWA CPE systems integrated there. Router production has picked up and supply has started in small lots; bulk production is expected to begin in August.
- Telecom product margins remain volatile: Margins in telecom products, which include fixed wireless access terminals and unlicensed band radios, are lower than OFC and vary significantly by product, time, and situation. Last quarter's telecom product margin was very low.
Passive Connectivity and Data Centers
- Telco PCS revenue has begun: Revenue from passive connectivity solutions for telecom service providers has already started, with a target of ₹450 crore in the current year.
- Data center PCS is a next-year story: Management expects passive connectivity solutions for data centers to generate reasonably good revenue only in the next financial year, though some revenue could start in maybe another quarter. HFCL supplies high-capacity fibre optic cables and passive connectivity solutions to data centers but does not manufacture servers or large-capacity switches. Customer names were withheld citing commercial confidentiality.
Mahendra Nahata: "World market for data centers is very, very large. Right now with the kind of hyperscalers are coming up all over the world, particularly in North America and Europe, unprecedented growth, which we could not have imagined probably six months ago."
Financials, Order Book, and Credibility
- Order book stands at ~₹10,000 crore: Of this, ~₹3,000 crore is executable this year. The EPC portion is ~₹6,400 crore, of which ~₹1,000–1,200 crore is convertible this year. Defence constitutes 12% of the total order book, or roughly ₹1,300 crore. Export orders stand above ₹400 crore. More orders are expected during the year.
- EPC losses are a drag: PBT losses in the turnkey/EPC segment have moved up to ₹100 crore over the last two quarters. Management says losses will mitigate as revenue increases, particularly from BharatNet, but declined to give a bottom-line direction for the EPC segment specifically.
- PLI miss is an acknowledged forecasting failure: Management had projected ₹40–50 crore in PLI for FY26 but could not reach the commitment level for indigenously manufactured telecom products revenue. Fibre optic cable is not on the PLI list. Management stated plainly: "It is our mistake that we projected high numbers in the beginning."
- Fundraise remains an open question: The ₹700 crore fundraise proposal is still just an enabling resolution; no decision has been made on whether to proceed, how much to raise, or the instrument. Use would be for defence, telecom, and OFC opportunities. Management declined to say whether it would reduce borrowings or whether the promoter would participate.
- Promoter stake decline raises questions: Promoter stake has declined by 1.92 crore shares over six to seven years, from roughly 35% to about 31%. Management characterised this as not substantial relative to total promoter holdings of ~47 crore shares, attributing sales to personal, social, and charitable needs. The promoter has previously bought shares and subscribed to warrants and could do so again, but no commitment was given.
Mahendra Nahata: "It is our mistake that we projected high numbers in the beginning, which if we had projected lower numbers, you would have got PLI, right now. There was no bar on projecting lower numbers."
People and Succession
- Professionalisation is the stated path: The company plans to be completely professionalised, run by professional CEOs and business heads. The next generation of the promoter family will focus on strategy, policies, external environment management, and customer relationships, not day-to-day operations. Business heads already run different verticals.
Mahendra Nahata: "In succession planning, we want to completely professionalize the company that it would be run by professional CEOs and professional business heads. Already, company is run by business heads for different business verticals. But in future, we expect shareholders to just play the shareholders' role and company run by professional CEOs. That is the way we are planning now."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| OFC revenue growth | More than double FY25 revenue to ~₹2,400 crore | FY26 |
| Overall revenue growth | 25% to 30% higher than FY25 | FY26 |
| Defence revenue | ~₹200-plus crore | FY26 |
| BharatNet Phase 3 revenue | ~₹800–1,000 crore | FY26 |
| Telco PCS revenue | ~₹450 crore | FY26 |
| IBR cable capacity expansion | From ~0.17 crore fkm to ~1.9 crore fkm per annum; total OFC capacity to ~4.24 crore fkm | Full completion by June 2026; revenue from expansion in FY26 |
| Electronic fuze revenue start | Subject to successful DRDO trials in August | Last quarter of FY26 |
| Drone detection radar production | Subject to successful field trials in late August | FY26 |
| Router bulk production | Bulk production to commence | August 2025 |
| Q2 performance | Better than Q1; every quarter to increase sequentially | Q2 FY26 onward |
| Data center PCS revenue | Reasonably good revenue expected | FY27 |
Key Metrics
| Metric | Q1 FY26 |
|---|---|
| Revenue | ₹871.02 cr, vs ₹800.72 cr in Q4 FY25 and ₹1,158.24 cr in Q1 FY25 |
| EBITDA | ₹42.93 cr, vs ₹-22.33 cr in Q4 FY25 and ₹185.37 cr in Q1 FY25 |
| EBITDA margin | 4.93%, vs -2.79% in Q4 FY25 and 16.00% in Q1 FY25 |
| Profit After Tax (PAT) | ₹-29.30 cr, vs ₹-83.30 cr in Q4 FY25 and ₹110.65 cr in Q1 FY25 |
| PAT margin | -3.36%, vs -10.40% in Q4 FY25 and 9.55% in Q1 FY25 |
| Telecom product segment revenue share | 66.35% of total revenue, vs 76.33% in Q4 FY25 and 61.42% in Q1 FY25 |
| Order book | ₹10,480 cr, vs ₹9,967 cr in Q4 FY25 and ₹6,776 cr in Q1 FY25 |
| FY26 revenue growth guidance | ~25% higher than FY25 (₹4,064 cr), implying ~₹5,080 cr |
| Optical fibre cable (OFC) revenue guidance | ₹2,400 cr in FY26, doubling from ₹1,200 cr in FY25; more than 50% expected from exports |
| OFC margin expectation | ~15% from July 2025 onwards, after demand recovery and improved capacity utilisation |
| EPC (turnkey) margin expectation | 6% to 8%, sometimes slightly higher in BharatNet |
| Defence segment revenue target | ₹200-plus cr in FY26, management's best estimate |
| OFC capacity utilisation | ~100% for optical fibre; OFC cable utilisation improving, reaching almost 100% in July 2025 |
| Total OFC manufacturing capacity (post-expansion) | ~4.24 cr fibre km per annum, up from ~2.51 cr fibre km; IBR cable capacity expanding from ~0.17 cr fkm to ~1.9 cr fkm per annum |
| CAPEX guidance for FY26 | ~₹250 cr, of which ~₹130 cr for IBR cable expansion |