Key Takeaways
- H1 revenue depressed, H2 ramp promised: Standalone H1 FY27 revenue was just ~INR800 crore after slow awarding and appointed-date delays, but management targets INR3,000–4,500 crore in Q4 alone, citing completed mobilization across all major projects.
- Margins crushed by loss-making projects: Standalone EBITDA margin fell to ~11% in H1 because a few projects incurred huge losses; management expects recovery to 13–14% in Q3/Q4 but is not confident of returning to 15%+ in the next 1–2 years.
- Order book healthy, inflow target ambitious: Order book stands at INR13,685 crore, and the company targets INR10,000–11,000 crore of inflows for FY27, with ~INR5,500 crore secured by Q2 and a pipeline spanning NHAI, MSRDC, railways, metro, and transmission.
- HAM monetization unlocking cash: OD5 equity transfer completed with partial consideration of INR103 crore received; AP-1 monetization expected in Q2 FY27; cumulative holdback receipts reached INR857 crore, with balance expected in H2.
- What to watch next quarter: Whether Q3 revenue actually inflects toward the INR4,200 crore H2 target, the pace of contract asset reduction from INR2,100 crore toward INR1,200–1,500 crore, and closure of the Karnal Ring Road monetization deal.
Revenue Trajectory & Project Execution
- H1 was a trough: Standalone H1 FY27 revenue of ~INR800 crore reflects the cumulative effect of slow awarding and appointed-date delays over the last year and this year; consolidated H1 revenue was INR2,074 crore.
- Q4 as the pivot: Management expects Q4 FY27 standalone revenue of INR3,000–4,500 crore, driven by mobilization already completed across all major projects; the wide range reflects uncertainty around exact billing timelines rather than project readiness.
- H2 segment build-up: BESS INR350 crore, transmission ~INR300 crore, rail metro ~INR1,400 crore, HAM Jharkhand packages ~INR700 crore, other HAM ~INR600 crore, Pune-Shirur ~INR600 crore, balance EPC ~INR200 crore, totaling ~INR4,200 crore for H2.
- FY28 ambition: Management is "quite hopeful" of reaching ~INR7,000 crore in FY28, contingent on order inflow of INR8,000–10,000 crore plus and timely appointed dates.
- Completion certificates unlocking cash: UER-2 completion certificate received September 23, 2026 (effective February 28, 2025); Adani Ganga Expressway certificate received very recently; both trigger holdback releases and close out legacy projects.
- Pune-Shirur early contribution: ~INR130 crore in H1 came from utility shifting and pre-operative expenses, booked via contract modification to enable cash flows; appointed date expected by November end or early December, with FY27 target of ~INR700 crore.
- Solar nearing finish line: 96% complete as of September 30, 2026; heavy monsoon, transmission line, land acquisition, and local disruption caused delays; INR250 crore-plus annual turnover targeted once all plants commissioned.
- Railway delays structural, not terminal: Kanpur Railway Station at 58.85% with extension approved in principle up to December 2027 due to block unavailability; Dhule-Nardana at 57.6% with ~11 km land unavailable; Gaya-Sonnagar and Karanjgaon at 56.2% and 67.2% respectively with non-availability of work fronts.
- Thane Metro challenges: Appointed date declared January 11, 2026; project facing land availability and local socio-economic issues; authority working aggressively to resolve, but timeline remains uncertain.
Harendra Singh: "Basically, all these projects where they are appointed is immediately being expected. So we, in any of the scenario, would be doing some INR3,000 or INR4,500 crore... in Q4. So this is giving that... we are confident enough that we would be able to do that part because the mobilization has been done in all such projects."
Margins: Pressure Today, Cautious Tomorrow
- H1 margin collapse: Standalone EBITDA margin was 10.2% in H1 FY27 (INR182 crore on INR1,790 crore revenue) because a few projects incurred huge losses; consolidated EBITDA margin was 26.7% for H1, reflecting HAM project contributions.
- Near-term recovery expected: Management guides 13–14% EBITDA margin for Q3 and Q4 FY27 and subsequent periods, as loss-making projects roll off and higher-revenue quarters absorb fixed costs.
- Medium-term pessimism: Management is "not very much confident that the coming one to two years is going to be better," citing geopolitical commodity prices and competition across the entire infrastructure sector; a return to 15%+ margins seen in previous fiscals is not in sight.
- Commodity impact mixed: Highways are protected by real-time price escalation for bitumen and crude POL; railways took a hit on OHE and S&T changes but civil work is less commodity-sensitive; BESS margins compressed from 20%+ to ~12% due to dollar, currency, and battery prices, but earlier high margins provided cover; transmission faces 30–40%+ aluminum and copper price increases versus bid levels, though price escalation was factored into bid budgets.
- Standalone PAT under pressure: Q2 FY27 PAT of INR32 crore (3.6% margin) versus INR67 crore (5.8%) in Q2 FY26; H1 FY27 PAT of INR60 crore (3.4%) versus INR193 crore (6.7%) in H1 FY26.
- Consolidated PAT distorted: H1 FY27 consolidated PAT of INR35 crore (1.7% margin) versus INR151 crore (6.3%) in H1 FY26, reflecting the interplay of project losses at the standalone level and HAM project economics at the consolidated level.
Harendra Singh: "Probably at the current scenario, it does not look like because of the geopolitical commodity prices as well as the competition all across entire infrastructure. We are not very much confident that the coming one to two years is going to be better."
Order Book & Inflow Pipeline
- Order book composition: INR13,685 crore as of September 26, with roads and highways at 64%, railways at 21%, and renewables and transmission at 15%.
- FY27 inflow target: INR10,000–11,000 crore, with ~INR5,500 crore secured up to Q2; remaining INR5,000–6,000 crore targeted in the last five months of FY27.
- Pipeline breadth: NHAI targeting ~600 km of awards this year; MSRDC re-inviting previously canceled projects with same qualification criteria; Rajasthan RSRDC expressways; railway projects of INR1,000–5,000 crore already bidded; metro projects including Jaipur (INR1,300 crore), Delhi, and Ahmedabad (~INR7,000 crore); plus transmission opportunities.
- FY28 inflow visibility: Management sees INR8,000–10,000 crore-plus inflow as possible, even if delayed by a month or two, supported by the same pipeline drivers.
- UPEIDA disqualification: Technically disqualified from all packages of UPEIDA Link Expressway along with 5–7 other contractors for a small technical reason that all missed; a setback but not pipeline-defining given MSRDC and other state opportunities.
- MSRDC re-bid: Projects re-invited with same qualification criteria from three years back; bid is only RFP, not RFQ, which may streamline the process.
HAM Monetization & Cash Flow Unlocking
- OD5 transfer completed: 51% shareholding transferred in Q2 FY27, receiving partial consideration of INR103 crore; remaining holdback expected in Q3 and Q4 FY27 subject to COD and punch list items.
- AP-1 next in line: NOC received from NHAI and lenders; equity transfer expected to complete in Q2 FY27.
- Cumulative holdback receipts: INR857.46 crore received till September 26 across all monetized assets; INR92.3 crore received in Q2 FY27 alone; balance consideration expected in Q3 and Q4 subject to final COD and conditions.
- Karnal Ring Road monetization: Quotations/offers received from two investors; deal likely to close within two months, but cash receipt expected only in Q2 next year (8–10 months from now) due to PCC, cooling period, and NHAI/bank permission requirements.
- Total monetization receivables: ~INR550 crore yet to be received from monetized HAM projects including AP-1, expected in Q3 and Q4.
- HAM project COD timeline: Karnal Ring Road at 99% completion, COD targeted in Q4 FY27; Raipur-Visakhapatnam OD-6 and AP-1 provisional completion certificates received, COD expected in Q3 and Q4 FY27; Khammam-Devarapalli packages 1 and 2 certificates received last year, COD expected in Q3 and Q4 FY27.
- Equity infusion status: Total equity requirement ~INR3,050 crore; INR1,846 crore infused as of September 26; remaining to be infused in later half of this year and FY28.
Balance Sheet & Working Capital
- Standalone debt elevated: Gross debt of INR1,595 crore (INR714 crore working capital, INR400 crore NCD, INR482 crore term loans); targeting reduction to INR900 crore by year-end via receivable monetization proceeds.
- Net debt trajectory: Expected to drop from ~INR1,600 crore to ~INR900 crore by March, driven by contract asset reduction and HAM monetization inflows.
- Contract assets at peak: Plateau reached last quarter at ~INR2,100 crore; expected to reduce to INR1,200–1,500 crore by March end, with ~INR800 crore of collection likely.
- Railways a major lock-up: Significant amount (~INR580 crore-plus) stuck in railways because milestone and commissioning terms require ~10% of total amount to be paid only upon full project commissioning and handover.
- HAM variation items: Significant amounts due from COS variation items and pending approvals, including ~INR180 crore from UPEIDA/Adani.
- Trade payables reduction: Dropped significantly from INR1,633 crore to INR1,188 crore, reflecting working capital management.
- Finance cost outlook: ~INR80 crore in Q3 and Q4 combined; next year stabilized at INR110–120 crore.
- Capex modest: ~INR50 crore for balance of FY27; ~INR100–120 crore next year.
- Other income items: ~INR18 crore from Maharashtra projects booked in Q2 from contract modification; certain conciliation claims may yield some income in coming quarters, but not very significant amounts.
Harendra Singh: "So, the plateau has been reached in last quarter only. Now significant drop is likely to be there..."
Renewables & Transmission: Early-Stage Build
- BESS execution progressing slowly: Only 6% completion due to land-related constraints; progress expected to improve in coming months.
- BESS procurement on track: Long lead items (BESS and PCS) procurement in place with delivery expected by January 2027; civil works at Banaskantha ~80% and Dholera ~60% completed; Charanka land formalities and design progressing.
- BESS commissioning timeline: Banaskantha and Dholera expected by March 2027; Charanka by June 2027; expected to generate annual revenue of ~INR225 crore upon commissioning.
- BESS margin compression: Margins compressed from 20%+ to ~12% due to dollar, currency, and battery price movements, but earlier high margins provided cover and the impact has been factored into current estimates.
- BESS financial closure: In-principle bank sanction received; binding agreements executed with GUVNL and NVVN for three projects totaling ~1,470 MWh.
- Solar financials: 89% of required project debt sanctioned; remaining INR215 crore plus balance slated for release in Q3 and Q4 FY27 following plant commissioning; invoiced DISCOMs ~INR80 crore in this financial year from 141 active plants.
- Transmission progress: TSAs executed for all three Angul, Odisha projects; part of RITOL received; foundation work progressing and tower erection going smoothly; Jamshedpur route alignment completed with land acquisition underway; Mirzapur land identified and lease agreement under execution.
- Transmission financial closure: Received for Angul; other two projects targeted in coming quarter.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Q4 FY27 standalone revenue | INR3,000–4,500 crore | Q4 FY27 |
| H2 FY27 segment revenue | ~INR4,200 crore (detailed breakdown provided) | H2 FY27 |
| FY27 full-year revenue | Roughly ~INR6,000 crore | FY27 |
| FY28 revenue | ~INR7,000 crore | FY28 |
| FY27 order inflow | INR10,000–11,000 crore total; INR5,000–6,000 crore in remaining five months | FY27 |
| EBITDA margin recovery | 13–14% range | Q3 and Q4 FY27 and subsequent periods |
| Standalone debt reduction | INR900 crore (from INR1,595 crore) | By FY27 year-end |
| Contract assets reduction | INR1,200–1,500 crore (from ~INR2,100 crore) | By March 2027 |
| Net debt reduction | ~INR900 crore (from ~INR1,600 crore) | By March 2027 |
| HAM monetization receivables | ~INR550 crore collection (including AP-1) | Q3 and Q4 FY27 |
| Karnal Ring Road monetization close | Deal closure within two months; cash receipt in Q2 FY28 | Deal: ~2 months; Cash: 8–10 months |
| BESS commissioning | Banaskantha and Dholera by March 2027; Charanka by June 2027 | March–June 2027 |
| Solar project completion | In next few months | Q3/Q4 FY27 |
| Pune-Shirur appointed date | November end or first week of December 2026 | Within a month |
| Pune-Shirur FY27 revenue | ~INR700 crore | FY27 |
| Capital Region Ring Road Pkg 3 appointed date | November end or first week of December 2026 | Within a month |
| Kanpur Railway Station completion | Extension approved up to December 2027 | December 2027 |
| Nelamangala-Tumkur completion | By March 2027 | March 2027 |
| Chennai-Tirupati HEM completion | By March 31, 2027 | March 31, 2027 |
| Bilaspur Railway completion | Q3 FY27 | Q3 FY27 |
| Transmission financial closure (2 projects) | In coming quarter | Q3 FY27 |
| Remaining equity infusion | In later half of this year and FY28 | H2 FY27–FY28 |
| Finance cost | ~INR80 crore combined in Q3/Q4; INR110–120 crore next year | Q3/Q4 FY27; FY28 |
| Capex | ~INR50 crore balance of FY27; ~INR100–120 crore next year | FY27–FY28 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Consolidated revenue | ₹974 cr, compared to ₹883 cr standalone |
| Consolidated EBITDA | ₹250 cr, margin of 25.6% |
| Consolidated PAT | ₹80 cr, margin of 8.2%, compared to ₹52 cr (5.7% margin) in Q2 FY26 |
| Standalone revenue | ₹883 cr |
| Standalone EBITDA | ₹105 cr, margin of 9.9% |
| Standalone PAT | ₹32 cr, margin of 3.6%, compared to ₹67 cr (5.8% margin) in Q2 FY26 |
| Standalone gross debt | ₹1,595 cr, comprising ₹714 cr working capital debt, ₹400 cr NCD, ₹482 cr term loans; targeting ₹900 cr by year-end |
| Order book | ₹13,685 cr as of Sep 26: roads 64%, railways 21%, renewables and transmission 15% |
| FY27 order inflow target | ₹10,000–11,000 cr, with ~₹5,500 cr secured up to Q2 |
| FY27 revenue guidance | ~₹6,000 cr by year-end, with Q4 expected at ₹3,000–4,500 cr |
| H2 FY27 EBITDA margin guidance | 13–14%, up from ~11% in H1 due to loss-making projects |
| FY28 revenue target | ~₹7,000 cr |
| HAM asset monetization: cumulative proceeds | ₹857.46 cr received till Sep 26; ~₹550 cr balance expected in Q3 and Q4 |
| Contract assets (unbilled revenue) | ₹2,165 cr as of Sep 30, expected to reduce by ₹700–800 cr by March-end |
| Solar portfolio: annual turnover target | ₹250 cr plus once all plants commissioned; invoiced DISCOMs ~₹80 cr in FY27 to date |
| BESS projects: expected annual revenue | ~₹225 cr upon commissioning of three projects (1,470 MWh) |