HG Infra Engineering Ltd Q4 FY2022 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/pm5lhbui4k4bd42tqcfeatcc.pdf

Key Takeaways


FY22 Performance: The Margin Story

Harendra Singh: "We faced several headwinds during the year, especially in the last quarter, with rising prices of key raw materials and various input cost pressures on account of disruption due to COVID, higher crude prices and geopolitical tension, etc., However, our strategy on selective bidding and constant efforts on operational efficiencies, coupled with multiple digital initiatives helped us mitigate this pressure and continue maintaining our margin profile."

Order Book & Project Pipeline


FY23 Guidance: Revenue Bridge & Margin Path

Harendra Singh: "We have seen the margin pressure in Q4, that was visible, wherein Q1 again we cannot rule it out, because the project is in main stream of execution, all projects are being awarded to us in two, two and a half years earlier. So there I think you can just see completely hit where this margin pressure is there. But later on, I think significant execution would be coming from those projects, which we got during March '21 or so. Almost the prices which we have considered in our rate. There is not a big gap into a recent price of commodity to that. So we will not see much of a hit in Q2 onwards and Q3 and Q4."

Input Costs & Margin Mechanics

Harendra Singh: "There is no rising competitive intensity which has impacted our margins, because these all are the projects, which were all being awarded to us some two and a half years back. So it's only price hit which has impacted the margin."

Balance Sheet & Capital Allocation


Competitive Landscape & Sector Dynamics

Harendra Singh: "I cannot say much about most of the companies doing wrong and just losing..."

Guidance & Commitments

CommitmentSpecificsTimeline
FY23 revenue₹5,000 croresFY23 full year
FY23 EBITDA margin15.5% to 16%FY23 full year
FY23 order inflow₹9,000 crores to ₹10,000 croresFY23 full year
FY24 revenue~₹6,000 crores (~20% YoY growth)FY24 full year
FY24 EBITDA margin16%–16.5%, conditional on stable commodity prices and ₹9,000–10,000 cr order addition in FY23FY24 full year
Margin recoveryQ1 pressured; Q2 onwards less hit; Q3 and Q4 in ~16% rangeQ2 FY23 onwards
Ganga Expressway order inflowLOA expected very soon; appointed date likely by AugustBy month-end / August 2022
Ganga Expressway FY23 revenueAt least ₹50–100 cr in Q2; ₹800 cr full yearQ2 and FY23
Ganga Expressway FY24 revenue₹2,000–2,500 cr plusFY24
Raipur-Visakhapatnam OD-5 & OD-6 appointed datesWithin a weekMay/June 2022
Khammam-Devarapalle appointed datesSeptember and October 2022Q2 FY23
Neelmangala-Tumkur appointed dateAugust or September 2022By Q2 end
HAM monetizationTransaction expected by year-endFY23 end
HAM equity investment₹459 cr in FY23; ₹208 cr in FY24; ₹113 cr in FY25FY23–FY25
Net CAPEX₹110–120 cr in FY23; ~₹90–100 cr subsequent yearsFY23 and beyond
Debt levelMaintained at ₹300–350 crAt least two years
Mobilization advanceRise back to ₹350–400 crAfter Q2 appointed dates
Non-road order inflow₹1,000–1,500 cr from water (JJM) and railwaysFY23

Key Metrics

MetricQ4 FY22
Standalone revenue₹1,026 cr
Standalone EBITDA₹157 cr
Standalone PAT₹91 cr, margin of 8.9%
FY22 standalone revenue₹3,615 cr, growth of 43% YoY, surpassing target of ₹3,400 cr
FY22 standalone EBITDA₹585 cr, margin of 16.2%
FY22 standalone PAT₹330 cr, margin of 9.3%
FY23 revenue guidance₹5,000 cr
FY23 EBITDA margin guidance15.5% to 16%
FY23 order inflow target₹9,000 cr to ₹10,000 cr
FY24 revenue guidance~₹6,000 cr, ~20% YoY growth
Total order inflow in EPC value for FY22₹4,328 cr
Order balance as of March 2022₹7,972 cr
Total standalone gross debt as of March 2022₹315 cr, includes working capital debt of ₹44 cr, term loans plus current maturities of ₹271 cr, NCD of ₹97 cr
Consolidated debt as of March 2022₹1,183 cr, includes project loans of ₹869 cr
Cash and bank balance, standalone₹159 cr
Cash and bank balance, consolidated₹165 cr
Debt-to-equity ratio0.23x as of March 2022, improved from 0.28x at end March 2021
Net working capital days31 days, improved from 33 days at start of year
Debtors days49 days
Inventory days36 days
Creditors days54 days
ICRA ratingUpgraded to AA-minus (long term) and A1-plus (short term)
HAM projects total liquidity requirement till FY25₹1,137 cr
HAM projects amount already invested as of March 2022₹354 cr
HAM projects projected investment for FY23₹459 cr
HAM projects balance equity requirement for FY24~₹208 cr
HAM projects balance equity requirement for FY25~₹113 cr
Net CAPEX addition expected in FY23₹110 cr to ₹120 cr
Mobilization advance as of March 2022₹195 cr
Retention money as of March 2022~₹180 cr
Unbilled revenue as of March 2022₹361 cr
Bonus expected in FY23 from HAM projects~₹24 cr, likely in first half
Ganga Expressway EPC valueNot less than ₹4,000 cr, single package
Ganga Expressway completion bonus if done in 24 months₹50 cr
NCD interest rate8% flat, 18-month moratorium, repayment starts June 2023 in 6 quarterly installments
Finance cost on HAM annuity projects7.1% to 7.3%
Adani receivables including timeshare~₹52 cr
IRB receivables excluding retention not yet due₹167 cr
Rajasthan project execution in FY22~₹60 cr
Maharashtra project execution in FY22Not more than ₹22 cr
National highway construction in FY2210,400 km, decline of nearly 24% YoY
Government target for national highway construction in FY2325,000 km
Government plan for national highway network by 20252 lakh km
Delhi-Vadodara Pkg-8 completion75% till date
Delhi-Vadodara Pkg-9 completion59% till March 2022
Hapur-Morradabad EPC project completion~78%
Mancherial project (Adani) completion56%
Karala-Kanjhawala (UER-2) EPC project completion4%
Rewari Bypass HAM project completion60%
OD-5 and OD-6 land acquisition88%, joint memorandum signed with NHAI
Bids underway, yet to open₹1,400 cr, two EPC projects
Non-road order target for FY23 (water, railways)₹1,000 cr to ₹1,500 cr
Rental income reclassified from other income to main revenue~₹7 cr
Change of scope recognized in Q4Over ₹95 cr
Utility shifting order balance~₹120 cr
Q4 utility shifting revenue₹14 cr
Investment in Safety First Engineering and Safety First Partnership26% stake for ~₹9 cr
NHAI relief measures extended tillOctober 31, 2022, performance guarantee at 3% till March 2023