Key Takeaways
- Revenue beat, margin held: FY22 standalone revenue grew 43% YoY to ₹3,615 crores, surpassing the ₹3,400 crores guided target, while EBITDA margin was maintained at 16.2% despite severe input cost inflation in Q4.
- FY23 guidance is aggressive: Management set a ₹5,000 crores revenue target (38% YoY growth) and ₹9,000–10,000 crores order inflow target, with margin recovery to 16%+ promised from Q2 onwards after a pressured Q1.
- Ganga Expressway is the swing factor: A single package worth not less than ₹4,000 crores EPC value is expected to enter the order book imminently and drive ₹2,000–2,500 crores of FY24 revenue, making its timely appointed date the single biggest variable in the outlook.
- Input cost pain is transitory, per management: The Q4 margin hit came from projects bid 2–2.5 years ago when commodity prices were lower; execution from Q2 onwards shifts to projects bid around March '21, where bid prices are closer to current levels, so the gap narrows.
- What to watch next quarter: Whether the Ganga Expressway LOA and appointed date land on schedule, whether Q1 margin pressure is as bad as Q4, and whether the ₹9,000–10,000 crores order inflow target stays on track after a near-standstill in bidding activity.
FY22 Performance: The Margin Story
- Topline surge: Standalone revenue hit ₹3,615 crores, 43% above FY21, exceeding the in-year guided target of ₹3,400 crores. Rental income (~₹7 cr) previously in other income is now reported in main revenue, a minor reclassification.
- Margin resilience: EBITDA margin of 16.2% was maintained as guided, achieved through selective bidding, operational efficiencies, and digital initiatives that partially offset the input cost surge.
- Q4 margin pressure: The visible margin decline of about a percentage point YoY was driven entirely by the commodity price gap on older projects, not by rising competitive intensity, because all projects in mainstream execution were awarded two and a half years back when bid commodity prices were far lower.
- COVID and weather drag: The second wave of COVID-19 and prolonged monsoon impacted execution of certain projects; unseasonal rains and cyclones combined with steep input price rises limited the ability to ramp up significantly.
- National highway slowdown: Total construction of national highways was 10,400 km, a decline of nearly 24% YoY, though NHAI and agencies outbid the prior year's performance.
- Change of scope boost: Over ₹95 crores was recognized in Q4 from change of scope, with utility shifting order balance of ~₹120 crores, of which ₹95 crores was recently recognized from a change of agreement.
- Working capital and rating: Net working capital improved to 31 days from 33 days; debt-to-equity improved to 0.23x from 0.28x; ICRA upgraded long-term facilities from A+ to AA- and short-term from A1 to A1+.
- Debtor spike explained: Last year NHAI issued a circular by 22nd March insisting bills be passed and paid during that year, causing a one-time reduction in receivables and higher cash. This year, out of ~₹277 crores debtors in government projects, ₹194 crores was received in April alone, so receivables are not stressed.
- Unbilled revenue: Some unbilled revenue sits in SPVs from recently completed projects where final bills and certificates of settlement are on card; ₹61 crores in NTPC/Adani Mancherial potash transportation works; Delhi-Vadodara/UER unbilled ~₹77 crores, none of it stressed.
Harendra Singh: "We faced several headwinds during the year, especially in the last quarter, with rising prices of key raw materials and various input cost pressures on account of disruption due to COVID, higher crude prices and geopolitical tension, etc., However, our strategy on selective bidding and constant efforts on operational efficiencies, coupled with multiple digital initiatives helped us mitigate this pressure and continue maintaining our margin profile."
Order Book & Project Pipeline
- Order inflow: Total EPC order inflow of ₹4,328 crores was slightly lower due to intense bidding competition, with major bidding from private players during the year.
- Private player share spike: Last year ~22–23% of total orders came from private players; for a short period of 6–8 months private contribution may be visible at 40%, then decrease to 35% and further down as management is not looking for further addition of subcontracting projects beyond current levels.
- Ganga Expressway: Notice to proceed has been issued; letter of acceptance expected very soon; lump sum turnkey EPC, 51 km, 27 months duration, star rate-based price variation clause, ₹50 crores bonus for early completion within 24 months. Appointed date expected by month-end (likely August).
- Raipur-Visakhapatnam corridors: Appointed date for one package received on 31st March; two more expected within the month. OD-5 and OD-6 land acquisition corrected to 88%; joint memorandum signed with NHAI; appointed date expected within a week.
- Khammam-Devarapalle: Pkg-1 and Pkg-2 LOA received September; Pkg-2 agreement signed 25th February 2022, Pkg-1 expected June; appointed dates expected September and October.
- Neelmangala-Tumkur EPC: Letter of acceptance received January '22; concession agreement yet to be signed, likely in June; appointed date expected August or September (by Q2 end).
- Project completions: Delhi-Vadodara Pkg-4 almost completed, applied for COD; Hapur-Morradabad EPC completed close to 78%, applied for PCOD likely June '22; Mancherial (Adani) completed around 56%, applying for PCOD in June '22, likely by July.
- HAM project milestones: Received PCOD for three HAM projects (Gurgaon-Sohna, Rewari Ateli Mandi, Narnaul Bypass) and EPC projects (Banar-Bopalgarh, Jodhpur-Marwar, Morshi-Chandur Bazar). Bonus eligibility in Rewari Ateli Mandi and Narnaul Bypass for 178 to 255 days.
- Bidding standstill: Bidding activity is almost at a standstill pending modifications to networth and O&M criteria, though management expects criteria to be finalized very soon and does not see the O&M standardization as a challenge to competitive intensity.
- Bharatmala tailwind: Bharatmala-I to be awarded in next two years; Bharatmala-II to be approved from parliament; 40,000 km to be developed in Bharatmala-I and II, giving a sense of lot of opportunities in the next five years.
FY23 Guidance: Revenue Bridge & Margin Path
- Revenue target: ₹5,000 crores, broken into ₹3,200 crores from projects with appointed dates already received (including Raipur-Visakhapatnam), ₹800 crores from Ganga Expressway, and ₹1,000 crores from projects expecting appointed dates in Q2 (Khammam-Devarapalle Pkg I & II, Tumkur Karnataka EPC).
- Order inflow target: ₹9,000 crores to ₹10,000 crores, with HAM order inflow of about ₹3,500 crores (EPC value ~₹3,000 crores) and ₹1,000–1,500 crores targeted from water (Jal Jeevan Mission) and railways.
- Margin trajectory: Q1 may see margin pressure because projects in mainstream execution were awarded 2–2.5 years earlier and face commodity price gaps; Q2 onwards less hit as execution shifts to projects won around March '21 where bid commodity prices are closer to current levels; Q3 and Q4 in range of about 16%.
- FY24 early view: Revenue of ~₹6,000 crores, ~20% YoY growth, based on likely ₹9,000–10,000 crores order inflow during FY23 and current order book; Ganga Expressway alone expected to contribute ₹2,000–2,500 crores plus. EBITDA margin of 16%–16.5%, conditional on stable commodity prices and the order addition materializing.
- Mobilization advance: Decreased from ~₹323 crores (March '21) to ₹210-odd crores (March '22); expected to rise back to ₹350–400 crores after Q2 appointed dates.
- Equity requirement: ₹490 crores in FY23, to be funded entirely from internal approvals; balance ₹208 crores in FY24, ₹113 crores in FY25.
- CAPEX: FY23 net CAPEX addition expected at ₹110–120 crores, driven by significant expected order inflow and fleet replacement (older fleet 6+ years, new technology for operational efficiency and fuel economy); subsequent years ~₹90–100 crores; normal run rate ~₹70–75 crores.
- Debt: Likely to be maintained at current level of ₹300–350 crores for at least two years.
- HAM monetization: Reinitiating talks with potential investors; appetite in the market is available, with the only gap being debate on O&M cost assumptions; with rate of interest and GST impact on annuity now clear, significant improvement expected in a few months; monetization expected by this year-end.
Harendra Singh: "We have seen the margin pressure in Q4, that was visible, wherein Q1 again we cannot rule it out, because the project is in main stream of execution, all projects are being awarded to us in two, two and a half years earlier. So there I think you can just see completely hit where this margin pressure is there. But later on, I think significant execution would be coming from those projects, which we got during March '21 or so. Almost the prices which we have considered in our rate. There is not a big gap into a recent price of commodity to that. So we will not see much of a hit in Q2 onwards and Q3 and Q4."
Input Costs & Margin Mechanics
- The core problem: Projects in mainstream execution during Q4 and Q1 FY23 were awarded 2–2.5 years earlier, when bid commodity prices were far lower than the recent spike driven by COVID disruptions, higher crude prices, and geopolitical tensions. The resulting gap compressed margins.
- Why HAM fared better: HAM projects did not see a big margin impact because most HAM execution was completed in Q2 or partly Q3, before the worst commodity pressure hit in Q3/Q4.
- EPC formula gap: In EPC, the impact was felt because some formula correction is desired at the contract level; management initiated a request to NHAI and the ministry to correct it so that eventually EPC and HAM will have similar protection. The new formula would apply only to new EPC projects, not older ones.
- Government relief expected: Benefit from government export duty changes on iron ore and steel is expected; the margin impact is likely to subside not in Q1 but in Q2 at least.
- Competitive intensity not the culprit: Management was explicit that there is no rising competitive intensity impacting margins, because all projects under execution were awarded two and a half years back; it is only the input price hit.
- Bidding discipline: Management maintains its own standards and discipline, keeping control on margins, geographical areas, and balancing HAM, EPC, and private EPC.
- Mines and sourcing: For southern corridors (Tumkur, Khammam-Devarapalle, Odisha, Raipur-Visakhapatnam), crushers have been established in allocated mines; for north projects, it does not make sense to establish own mines due to existing established supply.
Harendra Singh: "There is no rising competitive intensity which has impacted our margins, because these all are the projects, which were all being awarded to us some two and a half years back. So it's only price hit which has impacted the margin."
Balance Sheet & Capital Allocation
- Working capital: Debtors at 49 days, inventory at 36 days, creditors at 54 days; net working capital improved to 31 days from 33 days.
- NCD issuance: Raised at 8% flat interest, 18-month moratorium, repayment in 6 quarterly installments starting June '23.
- HAM asset refinancing: Refinancing done at interest rate of 7.1%–7.3%, which is less than annuity receipts from NHAI.
- Stake acquisition: Government acquired 26% in Safety First Engineering and Safety First Partnership for ~₹9 crores; a backward-integration move for crush barriers and miscellaneous items, expected to yield cost savings.
- Contract assets and liabilities: Contract liabilities are mobilization advances received (mostly interest-bearing), recovered during execution. Contract assets are unbilled revenue, typically settling in the final bill, often post-75%-plus execution.
- Finance cost: Finance cost does not have impact in the parent company; it is all in SPVs where the entire financial model is taken into consideration.
- Non-current financial assets increase: In consolidated, it is annuity; also can be GST receivable from government authorities.
- NHAI relief extension: NHAI extended relief measures for contractors/developers till 31st October '22; performance guarantee stays at 3% till March '23.
Competitive Landscape & Sector Dynamics
- Bidding intensity: Intense bidding competition from private players was a feature during the year, contributing to slightly lower order inflow of ₹4,328 crores.
- Financial closure stress: No significant trend yet on financial closure difficulties for smaller players; banks are cautious where equity is insufficient; management expects competitive intensity may improve in 6 months or Q2–Q3.
- HAM criteria modifications: Modifications to networth criteria and O&M criteria (standardized as percentage of BPC/tentative EPC) are expected very soon; the O&M standardization prevents front-loading but does not change competitive intensity.
- Budget impact: Industry representations have been made regarding the excise cut impact on NHAI funding; management does not see the budget impact affecting NHAI payments for FY23 or FY25.
- Gati Shakti: Government is keen on developing the core network for national highways and expressways; the Gati Shakti initiative indicates significant sincerity for infrastructure development across all sectors.
- BOT caution: Management views traffic origination-destination studies as projections only; dynamics are changing year-on-year with many corridors being developed, so estimation at this point is not appropriate.
Harendra Singh: "I cannot say much about most of the companies doing wrong and just losing..."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY23 revenue | ₹5,000 crores | FY23 full year |
| FY23 EBITDA margin | 15.5% to 16% | FY23 full year |
| FY23 order inflow | ₹9,000 crores to ₹10,000 crores | FY23 full year |
| FY24 revenue | ~₹6,000 crores (~20% YoY growth) | FY24 full year |
| FY24 EBITDA margin | 16%–16.5%, conditional on stable commodity prices and ₹9,000–10,000 cr order addition in FY23 | FY24 full year |
| Margin recovery | Q1 pressured; Q2 onwards less hit; Q3 and Q4 in ~16% range | Q2 FY23 onwards |
| Ganga Expressway order inflow | LOA expected very soon; appointed date likely by August | By month-end / August 2022 |
| Ganga Expressway FY23 revenue | At least ₹50–100 cr in Q2; ₹800 cr full year | Q2 and FY23 |
| Ganga Expressway FY24 revenue | ₹2,000–2,500 cr plus | FY24 |
| Raipur-Visakhapatnam OD-5 & OD-6 appointed dates | Within a week | May/June 2022 |
| Khammam-Devarapalle appointed dates | September and October 2022 | Q2 FY23 |
| Neelmangala-Tumkur appointed date | August or September 2022 | By Q2 end |
| HAM monetization | Transaction expected by year-end | FY23 end |
| HAM equity investment | ₹459 cr in FY23; ₹208 cr in FY24; ₹113 cr in FY25 | FY23–FY25 |
| Net CAPEX | ₹110–120 cr in FY23; ~₹90–100 cr subsequent years | FY23 and beyond |
| Debt level | Maintained at ₹300–350 cr | At least two years |
| Mobilization advance | Rise back to ₹350–400 cr | After Q2 appointed dates |
| Non-road order inflow | ₹1,000–1,500 cr from water (JJM) and railways | FY23 |
Key Metrics
| Metric | Q4 FY22 |
|---|---|
| Standalone revenue | ₹1,026 cr |
| Standalone EBITDA | ₹157 cr |
| Standalone PAT | ₹91 cr, margin of 8.9% |
| FY22 standalone revenue | ₹3,615 cr, growth of 43% YoY, surpassing target of ₹3,400 cr |
| FY22 standalone EBITDA | ₹585 cr, margin of 16.2% |
| FY22 standalone PAT | ₹330 cr, margin of 9.3% |
| FY23 revenue guidance | ₹5,000 cr |
| FY23 EBITDA margin guidance | 15.5% to 16% |
| FY23 order inflow target | ₹9,000 cr to ₹10,000 cr |
| FY24 revenue guidance | ~₹6,000 cr, ~20% YoY growth |
| Total order inflow in EPC value for FY22 | ₹4,328 cr |
| Order balance as of March 2022 | ₹7,972 cr |
| Total standalone gross debt as of March 2022 | ₹315 cr, includes working capital debt of ₹44 cr, term loans plus current maturities of ₹271 cr, NCD of ₹97 cr |
| Consolidated debt as of March 2022 | ₹1,183 cr, includes project loans of ₹869 cr |
| Cash and bank balance, standalone | ₹159 cr |
| Cash and bank balance, consolidated | ₹165 cr |
| Debt-to-equity ratio | 0.23x as of March 2022, improved from 0.28x at end March 2021 |
| Net working capital days | 31 days, improved from 33 days at start of year |
| Debtors days | 49 days |
| Inventory days | 36 days |
| Creditors days | 54 days |
| ICRA rating | Upgraded to AA-minus (long term) and A1-plus (short term) |
| HAM projects total liquidity requirement till FY25 | ₹1,137 cr |
| HAM projects amount already invested as of March 2022 | ₹354 cr |
| HAM projects projected investment for FY23 | ₹459 cr |
| HAM projects balance equity requirement for FY24 | ~₹208 cr |
| HAM projects balance equity requirement for FY25 | ~₹113 cr |
| Net CAPEX addition expected in FY23 | ₹110 cr to ₹120 cr |
| Mobilization advance as of March 2022 | ₹195 cr |
| Retention money as of March 2022 | ~₹180 cr |
| Unbilled revenue as of March 2022 | ₹361 cr |
| Bonus expected in FY23 from HAM projects | ~₹24 cr, likely in first half |
| Ganga Expressway EPC value | Not less than ₹4,000 cr, single package |
| Ganga Expressway completion bonus if done in 24 months | ₹50 cr |
| NCD interest rate | 8% flat, 18-month moratorium, repayment starts June 2023 in 6 quarterly installments |
| Finance cost on HAM annuity projects | 7.1% to 7.3% |
| Adani receivables including timeshare | ~₹52 cr |
| IRB receivables excluding retention not yet due | ₹167 cr |
| Rajasthan project execution in FY22 | ~₹60 cr |
| Maharashtra project execution in FY22 | Not more than ₹22 cr |
| National highway construction in FY22 | 10,400 km, decline of nearly 24% YoY |
| Government target for national highway construction in FY23 | 25,000 km |
| Government plan for national highway network by 2025 | 2 lakh km |
| Delhi-Vadodara Pkg-8 completion | 75% till date |
| Delhi-Vadodara Pkg-9 completion | 59% till March 2022 |
| Hapur-Morradabad EPC project completion | ~78% |
| Mancherial project (Adani) completion | 56% |
| Karala-Kanjhawala (UER-2) EPC project completion | 4% |
| Rewari Bypass HAM project completion | 60% |
| OD-5 and OD-6 land acquisition | 88%, joint memorandum signed with NHAI |
| Bids underway, yet to open | ₹1,400 cr, two EPC projects |
| Non-road order target for FY23 (water, railways) | ₹1,000 cr to ₹1,500 cr |
| Rental income reclassified from other income to main revenue | ~₹7 cr |
| Change of scope recognized in Q4 | Over ₹95 cr |
| Utility shifting order balance | ~₹120 cr |
| Q4 utility shifting revenue | ₹14 cr |
| Investment in Safety First Engineering and Safety First Partnership | 26% stake for ~₹9 cr |
| NHAI relief measures extended till | October 31, 2022, performance guarantee at 3% till March 2023 |