Hi-Green Carbon Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- Main board migration with more frequent quarterly calls
Pending - At the Q2 FY27 call, management stated the company is migrating to the main board, saying "see you soon, every quarterly from almost next quarter... more frequent phone calls very soon". No subsequent disclosure in our record confirms the migration is completed or gives a timeline.
- Pyrolysis volume - 60,000+ MT across three plants
On track - At the Q2 FY27 call, management said at \~80% ideal utilization across three plants (25,000 MT installed, stated as 75,000 MT including crumb rubber) it is "hopeful that 60,000 plus something volume we will do across these three plants". H1 FY27 volume was 24,000 MT - Rajasthan 9,300 MT, Maharashtra 1,650 MT, MP 5,100 MT - vs \~18,000 MT last half year, annualizing to \~48,000 MT against the FY28 horizon.
- rCB volume - \~40% growth in FY27 vs FY26
On track - At the Q2 FY27 call, management guided "we see almost 40% growth in volume this year compared to last year rCB", with 15,000-18,000 MT possible at 80% utilization. H1 FY27 rCB volume was \~3,700 MT vs \~2,800 MT last half year, \~32% growth, with Rajasthan and Maharashtra utilization at 29% and 30% and MP rCB yet to start.
- MP sodium silicate plant (60 TPD) - commercial production by January 2027
On track - At the August 2026 announcement, management guided a 60 TPD Sodium Silicate Plant at Dhar, MP using excess Syn Gas, with tentative commercial production from January 2027, ₹7-8 crore investment and peak net revenue of ₹30-35 crore per annum at a 25% margin. As of Q2 FY27, erection had started and majority civil work was to end by November 2026; no commercial production yet.
- Radhe Renewables consolidation - no additional capex, 1% commission
Pending - At the November 2025 call, management guided consolidating Radhe Renewables into Hi-Green: IP transferred for a token ₹1, factory rented at ₹1 lakh per month, Hi-Green executing all gasification orders with 1% commission and no additional capex. The machinery business was acquired at a nominal ₹1; no cited source discloses Radhe's contribution to FY27 revenue, so the commission outcome is not yet verifiable.
- Samsara Recycling restart after fire - insurance clearance by end-December 2025
Partial - At the November 2025 call, management guided Samsara Recycling (Kutch) would get insurance clearance to restart production by approx. end-December 2025 after the Diwali fire. Samsara reopened and achieved 50% capacity utilization in H1 FY27, but the ₹5.82 crore exceptional loss from the 20 October 2025 fire had its claim still pending as of Q2 FY27, release expected in 3-4 weeks.
- FY26 turnover of ₹130-140 crores with all three plants running
Delivered - At the November 2025 call, management guided that once all three plants run, turnover of ₹130-140 crores is expected for FY26, with H2 at almost ₹80 crore and 38,000-40,000 MT of tyre processing. FY26 revenue was ₹139 cr, within the guided range; processing rose to 36,010 MT vs 24,055 MT in FY24-25, below the guided range.
- Direct tyre company approvals with two tyre companies
Pending - At the Q4 FY25 call, management confirmed it was in the approval process directly with two tyre companies, names withheld under NDA, ongoing for more than one year. No subsequent disclosure confirms approval from either; Q2 FY27 noted rCB exports to Sri Lanka, Thailand and South America, and Indian four-wheeler tyre companies had not yet started using rCB.
- J&K plant (GreenVelly Hydrocarbon) - on hold pending subsidy renewal
Missed - At the Q4 FY25 call, management stated the J&K plant was on hold pending renewal of the central government subsidy of 300% of investment, with land found but no major investment until clearance. The FY26 annual report states the Jammu & Kashmir project has been withdrawn, with expansion focus moved to existing and adjoining geographies; no major progress had occurred due to subsidy uncertainty.
- Dhar plant syngas bottling - LPG/CNG alternative, ₹1-2 Cr additional investment
Missed - At the Q4 FY25 call, management guided syngas bottling at the Dhar plant with approvals started and additional equipment cost "hardly one or 2 crore plus minus"; the FY25 annual report planned bottling as an LPG/CNG alternative for industrial customers. The plan was withdrawn/reset in the FY26 annual report due to government approvals and regulation, replaced by a 60 TPD Sodium Silicate Plant using excess syngas.
- 10x capacity versus pre-IPO capacity in 7-10 years
On track - At the Q4 FY25 call, management guided 10x capacity versus pre-IPO in 7-10 years, calling it "conservative", at roughly one plant per year; this was reiterated in the FY25 and FY26 annual reports and the November 2025 call. Capacity has grown from 100 TPD pre-IPO to 300 TPD (3x), with a fourth plant declaration promised "soon".
- Ideal capital structure - 50% debt / 50% equity for all expansions
On track - At the Q4 FY25 call, management guided an ideal capital structure of 50% debt / 50% equity for all expansions. As of 02 Nov 2026, D/E is 0.70, implying debt of ₹63.23 cr is \~41% of capital; FY26 D/E was 0.30 and consolidated long-term borrowings rose to ₹4,301.27 lakh at 30-09-2025 from ₹3,126.07 lakh at 31-03-2025.
- Long-term sustainable EBITDA margins - stable around 20% to 25%
Partial - At the Q4 FY25 call, management guided long-term sustainable EBITDA margins "stable around 20% to 25% in between"; the November 2025 call targeted a 20% OPM for the full year, returning to 20% by H2 FY26. FY26 OPM was 16.68%, standalone 12.61%; Q2 FY27 OPM was 19.60% and H1 FY27 consolidated EBITDA was ₹20.60 crore on ₹99.78 crore revenue (\~20.6%).
- Dhule syngas-fired power plant - \~1 MW, ₹2 Cr capex, zero power bill
Pending - At the Q4 FY25 call, management guided Dhule would install a syngas-fired power plant, already ordered, generating \~1 MW for around ₹2 Cr capex, cutting the ₹15-20 lakh monthly power bill to zero, with syngas utilization starting "in the next one or two months". As of November 2025, syngas utilization was 0% with a DG set due the next month; no subsequent disclosure confirms installation or generation.
- Dhar (MP) 100 TPD plant - commissioning by Oct-Nov 2025
Partial - At the Q4 FY25 call, management guided the Dhar (MP) plant "expected" in operation by October-November 2025, later November-December; by November 2025, completion was targeted by end-December with trial run by 15th January. The plant received Consent to Operate on May 18, 2026 and commenced commercial operations in May 2026, taking capacity to 300 TPD; H1 FY27 MP utilization was \~40%, now running at 60-70%.