Key Takeaways
- First production achieved, then interrupted: B-80 delivered first gas and oil in June 2022, but a snapped hose and a separate D1 actuator issue forced both wells to shut in by mid-July. The quarter's ₹13.45 crores of B-80 gas revenue came from roughly three weeks of operations.
- Dirok carries the P&L: Higher oil and gas realizations added ~₹12 crores in Assam revenue, more than offsetting lower offtake volumes. Management says Dirok cash flow alone can cover liabilities even if B-80 stays offline for 5–6 months.
- Startup challenges caught management off guard: The CEO admitted the company lacked adequate in-house marine expertise and resources for monsoon operations, calling the B-80 difficulties unanticipated.
- No penalty risk on B-80 gas contract in year one: The GSPC agreement carries zero take-or-pay or supply-or-pay obligation until June 2023, giving HOEC a full-year cushion to stabilize operations.
- What to watch next quarter: Whether the D2 gas well reconnects during a monsoon weather window (management targets end of this month or early next), and whether the post-monsoon underwater survey yields a permanent fix for both wells.
B-80: First Production, Then Shutdown
- D2 gas well: Produced for ~3 weeks in June at rates building toward the committed 1 crore cubic feet per day, invoices were raised and revenue realized, and operations continued smoothly into early July.
- What broke: A hose connecting the CALM buoy to the FSO snapped during monsoon rough weather. Because oil co-produced with gas must be continuously exported through that hose, the gas well had to be shut in on 14th July even though the well and process systems are intact.
- D1 oil well: A separate technical issue in the actuator line recurred after a few days of production; the well is kept shut-in and a permanent solution is expected only post-monsoon after a comprehensive underwater survey.
- MOPU topside issue: The Expro-supplied separator system needs rectification; Expro will repair or replace at its own cost under the contract, so HOEC bears no expenditure.
- Revenue mode during shutdown: The MOPU continues earning $48,000/day; the FSO earns zero until production resumes. Management does not expect the whole quarter to be lost.
- Both wells are fine: Management stressed repeatedly that the wells themselves have no problems and delivered to expectation; the issues are entirely in the connecting systems and topside equipment.
P. Elango: "Frankly, we had not anticipated the startup challenges that we are facing in B-80, especially after the onset of monsoon. We do not have adequate resources and appropriate in-house marine expertise. Mobilizing marine assets and resources also takes a lot of costs and time."
B-80: The Path Back to Production
- D2 gas resumption: Reconnecting the snapped hose requires 2–3 days of work; management is watching for a weather window during the monsoon itself, possibly by end of this month or early next month. September onwards, conditions improve.
- D1 oil well fix: Most likely post-monsoon, in the October/November timeframe; multiple options are being evaluated.
- Full-stream target: By the end of this calendar year, both wells are expected to be fully on stream.
- Permanent solution: Post-monsoon, HOEC plans to engage internationally reputed offshore construction contractors for a comprehensive survey of all below-water connecting systems; repairs and replacements will follow from that survey.
- Safety constraint: Management emphasized that all work will proceed only within acceptable safety norms, which has governed the pace of response.
- Separator capacity: Both separators together can handle the targeted volumes with some modification by Expro; not expected to be a constraint when both wells are ready.
- Targeted volumes: Management expects both wells together to deliver roughly 4,500 barrels of oil per day and the committed 1 crore cubic feet of gas per day after internal consumption; wells have not yet been tested to full capacity.
Management: "We have made the first year free of any take or pay or supply or pay obligations just to ensure that both their side and we side have time to stabilize the operation."
Dirok: The Steady Anchor
- Production constrained by offtake, not wells: An unplanned BCPL plant shutdown in April–May 2022 limited Q1 production to an average ~2.5 crore cubic feet per day; after BCPL came back online, offtake improved.
- Revenue up despite lower volumes: Gas sales fell from 76 crore cubic feet to 65 crore cubic feet QoQ, and condensate from 15,932 barrels to 12,900 barrels, but higher dollar realizations (from 73–74 to 79) more than compensated, yielding an additional ~₹12 crores.
- Well productivity remains healthy: All three new wells from the last drilling campaign are performing well; the existing six wells are sufficient to meet current peak market demand.
- Phase 2 development advancing: Environmental clearance secured; working permission received to lay the 18-inch pipeline in the forest segment.
- Long-term demand visibility: The Northeast gas grid is being implemented in phases, connecting multiple demand centers.
- Gas price impact from October: Management does not expect a major impact from government-notified price changes because all major consumers source from both Oil India and HOEC, and Oil India will also sell at notified prices.
Other Assets & Development Pipeline
- PY-1: In-house designed low-cost gas dehydration unit commissioned; gas sales to GAIL recommenced in May at ~0.1 crore cubic feet per day. Internal geological studies for the next drilling campaign in the fractured basement reservoir are complete; a final investment decision awaits an independent technical review and risk mitigation.
- Cambay: Two development wells planned at Asjol and North Balol under the approved field development plan.
- Palej: Further development drilling to follow execution of the ring-fenced PSC, which has now been signed.
- Greater Dirok: Potential drilling locations identified; land acquisition and preliminary EIA studies to be initiated in the near future.
- Kherem and Umatara: Regulatory process for forest and environmental clearances is progressing.
- Sequencing discipline: Management was explicit: no new drilling campaigns (Cambay, PY-1) will proceed until B-80 is fully on stream and in a stable, hassle-free operating mode.
Management: "We wanted to put it in such a manner that one job at a time, now unless I have a revenue stream, which meets my all obligations in time that I cannot embark on another one."
Financial Position & Capital
- B-80 economics: The block is just breakeven on gas sales alone; the oil well must be on production to generate meaningful profit.
- Cash flow sufficiency: Even if B-80 stays offline for the next 5–6 months, Dirok cash flow at higher prices is enough to meet liabilities; management characterized the liability burden as manageable (₹30–40 crores is "not a big deal").
- Debt repayments: Quarterly repayments to Axis Bank and monthly to HDFC Bank are on track; funds are lined up.
- Capital infusion for growth: The company has borrowed ~₹300+ crores and will look at strategic ways to infuse additional capital. A capital plan will follow reserve re-evaluation and geologists' assessments; debt or equity infusion will be decided thereafter, subject to Board approval.
- Capital work in progress: Consequent to B-80 production commencement, ₹517 crores of capital work in progress moved to oil and gas assets; the MOPU moved to operating assets.
- Windfall tax: No impact expected; previous year production was below the 0.2 crore barrel threshold.
- Oil pricing model: Management plans to replicate the e-auction model used for gas price discovery, sharing settled crude samples with domestic refineries and conducting e-auctions benchmarked to Brent with premium/discount quotes.
Disclosure & Communication
- Analyst pushback on timely disclosure: An analyst requested more timely disclosure of material events (the B-80 disruption) to exchanges, citing SEBI requirements. Management acknowledged the point but did not commit to changing practices, stating they will "look at other ways of ensuring that there's a common communication and update happens."
- No revenue projections: Management declined to provide approximate cash generation estimates for FY24 even under assumptions of full production and current prices, calling it "incorrect" to predict before the field reaches sustainable, comfortable revenue mode.
- Government gas price uncertainty: When asked about the possibility of a government-imposed cap or ceiling on gas prices, management answered: "The honest answer is we really don't know."
Management: "We kind of agree but, I agree it would have been good to have shared such information. But please understand our effort whenever a problem of this nature occurs is to go and rectify the problem."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| B-80 D2 gas well reconnection | Reconnect snapped hose and resume gas production and sales | During a monsoon weather window; possibly end of this month or early next month |
| B-80 D1 oil well permanent fix | Comprehensive underwater survey followed by repairs | Post-monsoon; October/November period |
| B-80 both wells fully on stream | Both wells delivering ~4,500 bbl/day oil and 1 crore cf/day gas | By end of calendar year |
| B-80 permanent solution | Engage international contractors for survey of below-water connecting systems; repair/replace as needed | Post-monsoon |
| New drilling campaigns (Cambay, PY-1) | Proceed only after B-80 is fully on stream and in stable, hassle-free mode | No date; conditional on B-80 stabilization |
| Capital plan for new development | Re-evaluate reserves, assess geologists' numbers, then present capital plan to Board | After reserve re-evaluation; no specific date |
Key Metrics
| Metric | Q1 FY23 |
|---|---|
| Revenue (standalone) | ₹65.66 cr, vs ₹38.84 cr in Q4 FY22 |
| Revenue (consolidated) | ₹93.42 cr, vs ₹44.42 cr in Q4 FY22 |
| Standalone profit after tax | ₹34.21 cr, vs ₹23.47 cr in Q4 FY22 (excluding exceptional items) |
| Consolidated profit after tax | ₹32.7 cr, vs ₹7.6 cr in Q4 FY22 |
| Consolidated EBITDA | ₹52.23 cr, vs ₹22.3 cr in Q4 FY22 |
| Total standalone expenses (incl. DDA) | ₹35.99 cr, vs ₹20.85 cr in Q4 FY22 |
| Statutory levies (royalty and cess) | ₹9.74 cr, vs ₹6.59 cr in Q4 FY22; increase due to B-80 operations from 4 June 2022 |
| Operating cost | ₹22 cr, vs ₹5.46 cr in Q4 FY22; includes B-80 and other blocks |
| B-80 gas sales revenue | ₹13.45 cr, from commencement on 4 June 2022 |
| B-80 average gas sales rate (June) | ~0.7 crore standard cubic feet per day |
| B-80 gas price realized | $20 per MMBTU |
| Dirok average production | ~2.5 crore standard cubic feet per day, reduced by unplanned BCPL plant shutdown in April–May 2022 |
| Dirok share of premium sales | 40%, maintained at healthy level |
| Dirok gas sales volume | 65 crore cubic feet, vs 76 crore cubic feet in Q4 FY22 |
| Dirok condensate sales volume | 12,900 barrels, vs 15,932 barrels in Q4 FY22 |
| PY-1 current production | ~0.1 crore cubic feet per day |
| PY-1 gas sales price | $3.68 per MMBTU, as per contract |
| Total debt (as of 30 June 2022) | ₹330 cr, comprising HDFC Bank ₹119 cr, Axis Bank ₹125 cr, other short-term borrowings, and Hindage ₹62 cr |
| Accumulated crude inventory | ~15,000 barrels |
| Windfall tax impact | Zero; previous year production below 0.2 crore barrels threshold |
| MOPU leasing revenue (from 14 July) | $48,000 per day; FSO revenue reduced to zero until production resumes |
| Estimated B-80 rectification cost (worst case) | ₹4–4.5 cr, or up to ₹5 cr; includes D1 hydraulic leak fix (~$350k) and FSO hose reconnection ($150–200k) |