Hindustan Oil Exploration Company Ltd Q1 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/g6zk1y1lhep09ld6j7gtaw74.pdf

Key Takeaways


B-80 Operational Status & Constraints

P. Elango: "In the overall, at least it will take about another 6 to 9 months to get the plant to be operated in a stabilized mode and that too during the monsoon there will be a small shutdown, small changes will take place and we cannot exactly quote the timeline, as whichever the way I say I will be incorrect."

Dirok: Demand Collapse & Recovery Path

Management: "You have to understand there is a price, one guy, Oil India is selling at $6.5 and our price is more than $7.5, the first priority goes for the Oil India production, so unless the overall demand is picked up, we will not be able to offtake our gas."

Financial Performance


Portfolio Updates & Drilling Plans


Leadership Transition & Organizational Changes

Mr. Elango: "Now when I began my career, one of the important principles that I at least follow is while every employee is valuable, no one is indispensable. That's the principle under which you need to operate a company."

Disclosure & Communication Approach

Management: "If you are going for a value degradation, suppose the wells are not flowing, the wells are not possible to open, there is a permanent damage of value to the company, then we will come back to the market and inform immediately."

Guidance & Commitments

CommitmentSpecificsTimeline
B-80 stabilized operationsPlant operating in stabilized mode6–9 months (no firm date)
B-80 first oil parcelReach 400,000-barrel parcel size~45–50 days; November
B-80 export line remediationFlush line to return to 250 barrels per hourAfter monsoon (October/November)
B-80 marine system strengtheningReplace under-buoy hose, study mooring, procure sparesOctober–December
B-80 future drillingDrill 3rd, 4th and 5th wells togetherAfter 2 years uninterrupted production (~FY26–27)
Dirok National Grid connectionNortheast gas grid Phase 1 and UrjaGanga project completionNext financial year (FY25)
Dirok pipeline construction18-inch independent pipeline to Duliajan70% of critical forest segment complete; no final date
Kharsang drillingDrill new wells to 3,000 meters after JV consent~18 months (6 months reevaluation + 1 year drilling)
PY-1 drillingDrill exploration well after seismic reprocessing and third-party reviewQ2 FY25
Cambay drillingDrill two wells each in Asjol and North BalolAfter environmental clearance (no date)

Key Metrics

MetricQ1 FY24
Standalone revenue₹108.69 cr, down from ₹158.78 cr in Q4 FY23
Consolidated revenue₹187.14 cr, down from ₹193.39 cr in Q4 FY23
Standalone profit after tax₹21.34 cr, down from ₹107.03 cr in Q4 FY23
Consolidated profit after tax₹66 cr, down from ₹106 cr in Q4 FY23
Consolidated EBITDA₹96.86 cr, down from ₹139.84 cr in Q4 FY23
Standalone operating expenses₹79.12 cr (incl. stock adjustment), up from ₹43.72 cr in Q4 FY23
Consolidated operating expenses₹106.68 cr, up from ₹69.35 cr in Q4 FY23
B-80 block revenue₹83.44 cr, down from ₹86.57 cr in Q4 FY23
Dirok block revenue₹21.17 cr, down from ₹67.74 cr in Q4 FY23
Dirok average gas production10.24 MMSCFD and 187 barrels of condensate per day, vs 29.9 MMSCFD and 577 barrels of oil in Q4 FY23
B-80 oil in stock (FSO)2,92,000 barrels as of 30 Jun 2023, up from 1,87,000 barrels as of 31 Mar 2023
Outstanding loans (standalone)₹137 cr; subsidiary books: ₹86 cr
Bank loan rating obtained₹500 cr from India Ratings
Kharsang block acquisition cost₹50 cr for balance 50% of Geoenpro, making it a subsidiary
Kharsang current production~350 barrels per day
B-80 normalized daily operating cost$140,000 per day (standalone)
Dirok offtake July–August18–20 MMSCFD per day
B-80 production after restart~1,000 barrels per day from one well (D2)