Key Takeaways
- Production build underway, but still promise not proof: Kharsang output rose to 450 bpd from 351 bpd QoQ on new wells, yet the bulk of the 10,000 bpd target rests on a 2-year, INR 1,250 crores drilling program that has barely begun.
- B-80 remains the quarter's drag: Revenue fell on lower gas production and a monsoon-driven shutdown; a workover is planned for November 2025, but new well drilling may slip a full year if a rig is not secured soon.
- The Northeast Gas Grid is the single biggest catalyst: Management expects commissioning by end of Q4 FY26, which would unlock Dirok's constrained 5 crore scf/day capacity and eliminate the seasonality that makes quarterly comparisons misleading.
- Inventory sale is a pragmatic cash call, not a windfall: Liquidating 410,000 barrels at $65–$70 funds the capex program while service costs are falling, but management declined to give a revenue range.
- What to watch next quarter: Whether the gas grid stays on its Q3/Q4 timeline, whether a rig is secured for B-80's 3 new wells, and the pace of Kharsang drilling toward the December 2025 deadline.
Production & Operations
- Kharsang ramp-up: 4 of 9 phase-1 wells drilled, 3 hooked up and producing 350 bopd, equivalent to all 28 existing wells combined; a fourth well is testing gas in Upper Girujan sands and a fifth is underway. Management expects ~1,000 bpd by end-2025 and has issued EOIs for deeper 2,000 HP rigs to target the Barail formation.
- Dirok demand handcuff: The field can produce 5 crore scf/day but gas sales were just 0.41 Bcf this quarter because local offtake is insufficient. A revised FDP has been submitted to enable block extension, and 4 new wells are planned once the grid opens demand.
- B-80 disruption and recovery: Production stopped mid-June when the FSO de-moored from the SPM for monsoon safety; it was re-moored in August and production has recommenced. The D1 well also suffered mechanical and wax issues that a post-monsoon workover aims to fix.
- Monsoon impact unchanged: Management said the disruption so far is similar to last monsoon, not better, and declined to compare until the season ends.
Jeevanandam: "All have been producing. There are no dry holes at all."
The Northeast Gas Grid Catalyst
- The constraint: Dirok's gas sales volume is capped not by geology but by local demand; the grid would connect it to a wider market and allow production to rise toward field capacity.
- The timeline: Management expects completion by Q3 FY26 and full commissioning by end of Q4, based on field observations of lines being connected and discussions on common carrier issues. It acknowledged the timeline is not in HOEC's control but believes it is in the best interest of all regional parties.
- The consequence: Once the grid is functional, the seasonality that makes QoQ comparisons misleading should disappear, and Dirok's sales volume can step up materially.
Jeevanandam: "We expect that from the third quarter it should be completed. By all probability, end of the fourth quarter, it should be fully commissioned. That's what we believe in."
Drilling Program & Capex
- Scale and scope: The 2-year program targets 18 shallow plus 3 deep wells at Kharsang, 4 at Dirok, 2 at Greater Dirok, 2 each at North Balol and Asjol (onshore), and 10 offshore wells split across PY-1 (3), B-80 (3), and B-15 (4). Total capex is INR 1,250 crores, which may slip to 2.5 years.
- Funding: INR 250 crores raised as long-term debt, with the balance from internal accrual; management pledged not to exceed that debt level and to be debt-free within 2 years.
- Offshore sequencing: The campaign starts with the B-80 workover in November 2025, followed by PY-1 drilling in the last quarter of FY26, then continuing except during monsoon. B-80's 3 new wells require a platform and will take about a year once a rig is secured.
- PY-3 progress: PetroVietnam submitted a 4-well plan (2 infill, 1 appraisal, 1 exploration) with capex not exceeding $50 million; HOEC is lining up a rig and long-lead items to drill the first well before end-FY26, though the dispute tribunal has not yet been constituted.
Jeevanandam: "When oil price is going down, your drilling costs and other -- the input cost of the development drilling and other things will also go down, because we are embarking on a capital program. So the prices of all service and other things will come down. And that is the right time for us to go and complete our drilling program. For that, we need this money as such, so we are going ahead and getting it done."
Inventory Liquidation
- The decision: HOEC appointed M-junction to auction 410,000 barrels of inventory, with technical evaluations completed and price bidding to follow. Management expects the auction before 31 August and offtake within 10–15 days of bid acceptance, liquidating the inventory in roughly 1–1.5 months.
- The rationale: With oil price indications at $65–$70, management judged it prudent to sell; simultaneously, lower oil prices reduce drilling service costs, making this the right moment to fund the capital program.
- No revenue guidance: When asked for a revenue range, management declined, telling the analyst to multiply 410,000 barrels by whatever price they wished to consider.
Financials & Ownership Changes
- Standalone costs fell: Field operating expenses dropped to INR 55.8 crores from INR 62.59 crores QoQ, and statutory levies also decreased.
- Consolidated costs rose: Total expenses increased to INR 69.29 crores from INR 64.9 crores QoQ, mainly on stock movement.
- B-80 consolidation effect: HOEC now owns 100% of B-80, so facility revenue and cost are eliminated in consolidated accounts for the current quarter.
- India Ratings upgrade: The agency reaffirmed an 'IND A' rating and revised the outlook from 'stable' to 'positive' for the INR 50 crores bank loan.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Kharsang 9-well program | Complete all 9 phase-1 wells; reach ~1,000 bpd | Before December 2025 |
| Northeast Gas Grid | Completed Q3, fully commissioned Q4 | End of Q4 FY26 |
| Dirok offtake increase | Demand increase to commence | Q3 FY26, likely before 31 March 2026 |
| B-80 D1 workover | Workover to start post-monsoon | November 2025 |
| PY-1 first well | Finalize rig, source long-lead items, spud first well | Last quarter FY26 |
| Inventory liquidation | Auction and offtake completed | Auction before 31 Aug; offtake within ~1.5 months |
| Total capex program | INR 1,250 crores across onshore and offshore wells | 2 years (may slip to 2.5) |
| Production target | P90 expectation of at least 10,000 bpd (HOEC share) | After full capex program |
| Debt ceiling | Not to exceed INR 250 crores; debt-free thereafter | Within 2 years |
| PY-3 first well | Drill first of 4 wells; capex not to exceed $50 mn | Before end of FY26 |
Key Metrics
| Metric | Q1 FY26 |
|---|---|
| Standalone revenue | ₹83.48 cr, vs ₹83.37 cr in Q4 FY25 (Q4 FY25 with year-end adjustments: ₹142.61 cr) |
| Consolidated revenue | ₹85.5 cr, vs ₹85.54 cr in Q4 FY25 (adjusted for PI assignment and day rate revision) |
| Standalone EBITDA | ₹27.24 cr, vs ₹24.38 cr in Q4 FY25 (Q4 FY25 with year-end adjustment: ₹148.32 cr) |
| Consolidated EBITDA | ₹35.02 cr, vs ₹38.74 cr in Q4 FY25 (excluding adjustment for 40% PI acquisition and rate revision; Q4 FY25 with adjustment: ₹61.85 cr) |
| Standalone PAT | ₹48.21 cr, vs ₹130 cr in Q4 FY25 (with year-end adjustment) |
| Consolidated PAT | ₹43.87 cr, vs ₹51.16 cr in Q4 FY25 (including year-end adjustments) |
| Standalone field operating expenses | ₹55.8 cr, vs ₹62.59 cr in Q4 FY25 |
| Statutory levies | ₹12.13 cr, vs ₹13.5 cr in Q4 FY25 |
| Total standalone costs | ₹66.28 cr, vs ₹48.01 cr in Q4 FY25 |
| Consolidated total expenses | ₹69.29 cr, vs ₹64.9 cr in Q4 FY25 |
| Kharsang average production | 450 barrels per day, up from 351 barrels per day in Q4 FY25 (total field production; HOEC share 35%) |
| Dirok gas sales volume | 0.41 Bcf (HOEC share), vs 0.37 Bcf in Q4 FY25 |
| Dirok condensate production | 8,893 barrels, vs 6,603 barrels in Q4 FY25 |
| Dirok gas price realized | US$7.54 per MMBtu, vs US$8.45 per MMBtu in Q4 FY25 |
| B-80 oil production | 48,406 barrels, vs 60,000 barrels in Q4 FY25 |
| B-80 gas production | 0.37 Bcf, vs 0.4 Bcf in Q4 FY25 |
| B-80 gas price realized | US$11.4 per MMBtu, vs US$12.09 per MMBtu in Q4 FY25 |
| B-80 unsold oil inventory | ~410,000 barrels, auction expected to complete before 31st August 2025; estimated value ~US$25–26 million (over ₹220 cr) |
| Debt raised for capex | ₹250 cr long-term loan; India Ratings reaffirmed 'IND A', outlook revised to 'positive' for ₹50 cr bank loan |
| Total capex target | ₹1,250 cr over 2–2.5 years (previously ₹1,000 cr, increased by ₹250 cr) |
| Post-capex production target | At least 10,000 barrels per day (P90, HOEC share) |