Key Takeaways
- A quarter of operational repair, not growth: Production fell at B-80 and PY-1, while Kharsang and Cambay improved. Standalone PBT before exceptional items dropped to ₹12.54 crores from ₹30.4 crores, largely on crude inventory movements.
- The B-80 story is now a recovery story: Only ~15% of stored crude has been sold at a ₹4–6 crore loss, workovers are slated for October, and management expects two wells producing by November–December 2026.
- Dirok is the nearest material catalyst: PNGRB made the DNPL line a common carrier, degraded sections have been replaced, and hot tapping removes the NRL shutdown dependency. Pipeline completion is targeted for December.
- PY-1 drilling is now conditional, not scheduled: Two new wells will only be spudded after a take-or-pay agreement with GAIL or IOCL, a direct lesson from the field's 15-year history of shut-in wells.
- What to watch next quarter: Whether B-80 workovers actually start in October, whether Dirok hits its December pipeline target, and whether any take-or-pay agreement for PY-1 gas materializes.
B-80: The Core Asset in Repair
- Production status: Never fully shut, but one well had severe splash-zone corrosion requiring asset-integrity work, and another has very high water cut producing very little. Compression was reconfigured from parallel to series to achieve higher suction at lower suction pressure, now in test mode.
- Workover plan: Two existing wells (D1 and D2) are on track for workover, with rig award expected this month and mobilization by October. Workovers will shut off water zones and open new oil and gas zones.
- Drilling sequence: Three wells to be brought on production by June of next year, with the campaign running through end of March or early April, followed by jacket and production deck installation. Management cautioned offshore wells can have delays.
- Reserves confidence: Management believes 2P reserves of 2.6 crore barrels are still in ground with only 0.15–0.2 crore produced, and rig intervention allows complete shut-off of water zones and re-perforation of new strata.
- Crude inventory overhang: Approximately 15% of stored crude has been sold at losses of ₹4–6 crores so far, with total loss expected around 7–10% of value depending on Brent. Entire inventory expected cleared from HPCL refinery by end of October or early November.
- The HPCL delay: A "Black Swan event" where ₹260 crore plus interest (~₹300 crore) got stuck prevented workovers in November of last year and three wells from being drilled.
Mishra: "We believe our 2P reserves are still there, 2.6 crore, of which 0.15-0.2 crore has been produced so far. So there are reserves to be produced."
Dirok: The Nearest Catalyst
- Evacuation constraint: Producing only 50%–70% of capability from existing well stock because of lack of evacuation route. The DNPL line is degraded and operating at 40–50 bars instead of its 90-bar design pressure, reducing capacity from 2.5 MMSCM/day to 1–1.2.
- Common carrier status: PNGRB has made the DNPL line a common carrier, previously captive of NRL/Oil India and operated by AGCL. NRL has also been made a re-seller, so NRL can take HOEC gas and sell it on the exchange.
- Pipeline repair progress: Sections of the DNPL line that needed replacement have been laid; only tying back to the original line remains. Hot tapping solution adopted, with Assam Gas Company in the process of awarding the contract.
- Timeline: Pipeline completion expected by December, with hot tap lead time roughly 16–20 weeks. NRL shutdown no longer needed because hot tap option is available.
- Sales route: Once pipeline is completed, gas can be sold on the exchange in three days; no firm buyer needed if going to the exchange, though intermediate buyers can charge a marketing margin.
- Locked-in volumes: HOEC locked-in volumes are 0.6 to 0.7, sometimes 0.05 crore standard cubic meters on a gross basis; should be able to sell all well stock gas once pipeline capacity is brought online.
Mishra: "There isn't a reservoir in India, and in large parts of the world, where your production header pressure from six wells is 3,000 PSI. That speaks to the prospectivity of this reservoir."
PY-1: Drilling Now Conditional on Gas Buyers
- Production loss: Serious production loss suffered at PY-1 East Coast platform with three wells. Rig-less intervention contract already awarded to increase production in the short term before drilling two new wells.
- Historical failure: Wells came on 15 years ago with 5 crore standard cubic feet per day from three wells, but lack of buyers forced shut-in; water overwhelmed the gas zones in the basement reservoir, requiring re-processing and PetroVietnam analysis.
- Drilling deferral: Drilling of two new wells, previously planned for Q4 of next year, has become contingent upon ability of gas buyers IOCL/GAIL to lift gas. Concern that newly drilled wells kept shut for months would water out again.
- Take-or-pay condition: Intent to secure take-or-pay agreement with GAIL or IOCL before spudding two new wells; only then will wells be spudded. In the meantime, rig-less intervention funded from own books to increase production from existing wells.
Mishra: "So this time, we are trying to get it right. As far as possible, we'll have a take-or-pay agreement either with GAIL or with IOCL and only then we will spud the wells."
Kharsang & Cambay: The Working Assets
- Kharsang production: Successfully completed nine wells program and doubled production from last year. Five or six workovers completed on previously shut wells, incrementally increasing production.
- Kharsang second phase: Second phase of nine wells being prepared; rig identified, award imminent; tubulars ordered, expected in one to two months.
- Kharsang gas monetization: Virgin gas found in two wells in Kharsang, but no buyer and no pipeline, delaying monetization of reserves.
- Kharsang pipeline: Tender for route survey for the 24-km pipeline closes tomorrow (August 14, 2026). Oil India has already laid a pipeline from Kumchai fields to Bordumsa; HOEC will tie into that pipeline at Bordumsa, connecting to NRL and the national gas grid.
- Cambay production: New belt technology implemented at Balol, in trial phase. Palej facility debottlenecked using thermionic heaters; 5%–6% production increase already seen in last quarter. Sucker rod pumps ordered.
- Cambay outlook: 20%–30% increase in production expected going forward from Cambay assets. New exploration block in final stages of approval, close to Palej field.
Mishra: "The problem remains that if we find gas, then we don't have a buyer and in fact, we have found virgin gas in two of the wells in Kharsang. That's a good problem to have, but the only thing is it delays the monetization of reserves because we don't have a pipeline."
Financials & Funding
- Profitability decline: Standalone PBT before exceptional items fell to ₹12.54 crores from ₹30.4 crores mainly due to offset to higher inventory of crude in previous quarter; previous quarter's reversal of HPCL sale resulted in lower cost offset to overall operating cost.
- Inventory impact: Movement of profitability needs to be viewed in context of cost structure, mainly impact of changes in inventory of crude stored in tankers and not sold till appropriate time.
- EBITDA adjustment: Management declined to immediately quantify what Q1 EBITDA would have been excluding inventory adjustments, citing technical complexity involving inventory adjustment, profit petroleum adjustment, and sale adjustment.
- Capex budget increase: Increase from Q4 presentation attributed to contingency for rig contract, not necessarily to be fully spent; rigs in short supply as oil prices rise. Facility will be drawn down on need basis.
- B-80 funding: For delivering B-80 program, company will have to rely on debt; in the process of raising debt. By November/December of 2027, cash flows will be sufficient to fund growth for B-15.
- Cash flow outlook: Dirok will "definitely buy up the balance sheet" if all locked-in molecules are produced; better cash flow situation if Dirok is completely on stream.
Mishra: "Now how much? I would put my number to around 7% to 10%, but please don't take it as a guidance."
HPCL Relationship & Crude Sales
- Crude sale reversal: Sale of B-80 crude to HPCL was reversed in March–April of this year; agreed to sell to third parties instead. HPCL has kept the crude; additional gantries were created for offtaking crude.
- Conciliation process: High Court Chief Justice has been appointed for conciliation with HPCL. Management said they will not renege on what has been agreed.
- Liability question: An analyst asked why HOEC isn't passing on the liability to HPCL given the 10–15% loss from Brent price reduction and HPCL's fault; management deflected by saying they want to preserve a collaborative atmosphere.
- FSO crude sale: October sale planned of 120,000–130,000 barrels using smaller tankers to avoid demurrage charges; monsoon must end first.
Mishra: "We would like to preserve it and keep it that way rather than having double barrel guns at each other and fighting."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| B-80 workovers | Two existing wells (D1 and D2) worked over, water zones shut off, new zones opened | Rig award this month; mobilization by October; production by November–December 2026 |
| B-80 drilling | Three wells brought on production | By June of next year |
| B-80 crude inventory clearance | Entire crude inventory cleared from HPCL refinery in Chembur, Mumbai | End of October / early November |
| Dirok pipeline completion | DNPL line tied back, hot taps completed by AGCL | December |
| PY-1 drilling | Two new wells spudded only after take-or-pay agreement with GAIL or IOCL | Contingent on gas sales agreement; no date |
| Kharsang second phase drilling | Nine wells drilled; rig identified, tubulars ordered | Award imminent; tubulars in one to two months |
| Kharsang pipeline | 24-km pipeline laid, tied into Oil India line at Bordumsa | 6–8 months for right of way, 6–8 months to lay; ideal completion December 2027 |
| Cambay production increase | 20%–30% increase from Cambay assets | Going forward; no specific date |
| B-15 drilling | FDP under preparation; drilling planned | FY28 |
| Asset-wise realization disclosure | Offshore and onshore realizations reported separately | Next presentation |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Standalone revenue from operations | ₹117.5 cr, compared with negative ₹194 cr in Q4 FY26 |
| Net standalone revenue | ₹107.6 cr, after profit petroleum and revenue share of ₹9.83 cr |
| Consolidated revenue from operations | ₹124 cr, net consolidated revenue of ₹114.17 cr after profit petroleum and revenue share |
| Standalone profit before tax and exceptional items | ₹12.54 cr, compared with ₹30.4 cr in Q4 FY26 |
| Consolidated profit before tax and exceptional items | ₹6.5 cr, compared with ₹9.01 cr in Q4 FY26 |
| Other income | ₹19.37 cr standalone, ₹20 cr consolidated |
| Standalone total expenses | ₹114 cr, including depletion of ₹51 cr, royalty and statutory dues of ₹13 cr, stock adjustments of ₹41 cr |
| Consolidated total expenses | ₹128 cr, including depletion of ₹58 cr, royalty/cess/statutory dues of ₹15 cr, stock adjustments of ₹41 cr |
| Kharsang production | 17,400 BOE, up from approximately 12,300 barrels of oil in Q4 FY26 |
| Average crude and condensate realization | $95.5 per barrel, compared with approximately $70.8 per barrel in Q4 FY26, standalone |
| Average gas price realization | $12 per MMBTU, compared with $9.8 per MMBTU in Q4 FY26 |
| B-80 gas realization | $16.5 per MMBTU average, approximately $15–16 per MMBTU on the exchange |
| Dirok gas realization | $12.5 per MMBTU average, pegged at $10–12 per MMBTU |
| B-80 crude inventory sold | Roughly 15% sold as of the call, with losses incurred of ₹4–6 cr so far |
| B-80 2P reserves | 2.6 crore barrels, of which 0.15–0.2 crore has been produced so far |
| Gearing | 0.04, with ₹20 cr bank loan as the only debt on the books |
| DNPL pipeline capacity | 0.25 crore standard cubic meters per day target at 90 bar, up from current degraded capacity of 1–1.5 MMSCMD |
| Dirok production capability utilization | 50%–70% of capability from existing well stock due to lack of evacuation route |
| B-80 workover target | 500 to 800 barrels per well, and 3 to 0.5 crore scuffs per day from worked-over wells |
| B-80 new well production range | 1,000 to 1,500 barrels per well, could be 700 or 1,400 based on reservoir models |
| PY-1 new well potential | 1.5 to 2 crore standard cubic feet per day from two new wells, per PetroVietnam analysis |
| Kharsang gas pipeline timeline | 14 to 18 months total, 6 to 8 months for right of way plus 6 to 8 months to lay 24 km pipeline |
| Cambay production increase expected | 20% to 30% going forward, with 5% to 6% increase already seen in Q4 FY26 |