Key Takeaways
- A quarter lost to a hose: B-80, the company's core asset, was shut for over 110 days after a monsoon-exposed hose failed, collapsing standalone PAT to Rs.6.57 crores from Rs.34.21 crores QoQ.
- Pricing reset to market reality: The $20/MMBTU B-80 gas contract was abandoned after GSPC found no buyers; HOEC will now sell at IGX-discovered prices, starting at ~$13.5/MMBTU for November.
- D1 well repair is the next catalyst: A sealant injection fix for the shut-in D1 oil well is planned for December; success would restore full two-well production and materially improve cash flows.
- Capital raise is now existential, not optional: The company needs equity and debt to fix working capital, fund permanent monsoon-proofing, and drill new wells; shareholders have approved Rs.250 crores but no mode or price is set.
- What to watch next quarter: Whether the D1 sealant fix works in December, whether IGX gas prices hold above $13, and whether the equity raise launches with concrete terms.
B-80: The Core Asset, the Shutdown, and the Fix
- The shutdown: Gas sales halted from 14 July to 31 October because an under-buoy hose connecting the FSO vessel developed a leak, exposing the system's inability to withstand monsoon conditions.
- The restart: Gas sales from the D2 well resumed on 4 November after hose repair; the well is currently producing ~1 crore cubic feet/day of gas and ~300 barrels/day of oil, with oil stored in the FSO.
- The D1 outage: The D1 well, which would double production, is shut in due to a hydraulic pressure loss in one core of the umbilical; a minor leak was identified and a sealant injection solution chosen.
- The D1 repair plan: A specialist UK company will inject sealant into the triple SV line, requiring imported sealant and a mobilized dive support vessel; execution is targeted for December 2022, with management committing to complete the fix before March/April 2023.
- The backup plan: If sealant injection fails, the company will pull the tree cap and tighten the joint or change the flying lead; management states the fix will be permanent regardless of which path is taken.
- The cost structure: At the consolidated level, operating cost net of FSO/MOPU revenue is ~$5/MMBTU; marginal cost is $5.35/MMBTU, so at a $14 gas price the company makes a contribution even with only the D2 well producing.
- The development philosophy: Management consciously chose a cost-effective development model because ONGC had deemed the field uneconomic since its discovery in the mid-80s; some equipment choices led to monsoon issues now being addressed with a different approach.
P. Elango: "What we can learn this, whatever connecting systems that we've set it up, were not able to withstand the roughness of the monsoon. That is the fact."
B-80 Gas Pricing: From $20 to Market
- The contract collapse: GSPC reported inability to find customers at $20/MMBTU, the price realized in June; HOEC agreed to adopt IGX-discovered monthly market prices and will amend the gas sales contract accordingly.
- The new price: November 2022 supplies will price at ~$13.5/MMBTU; the D2 gas sales contract was awarded to GSPC via e-auction on an IGX-linked basis for the next 5–6 months, after which original contract terms resume.
- The contract protection, and its flip side: No penalty was payable for non-supply from mid-July because the first-year contract has no take-or-pay or supplier-pay obligation; this same clause meant GSPC had no obligation to take gas at $20.
- The second-year backstop: From April 2023, the second contract year brings 75% annual take-or-pay at a committed price into force; the company also has the option to raise volume to alternate customers after stabilization.
- The IGX outlook: Management expects ~$4–$5 premium over government-notified prices on the exchange; delivering to Gujarat, the most premium market, and expects better price visibility over the next six months as ONGC volumes trade on the exchange.
P. Elango: "Ultimately, as a company, we cannot expect more than what the market is willing to do."
Monsoon-Proofing: The Permanent Fix
- The root cause: Connecting systems set up for B-80 could not withstand monsoon roughness; a reputed engineering firm is being appointed to evaluate overall systems and processes for the next monsoon, with an expert mobilized from Dubai at day rates.
- The hose replacement: Before the next monsoon (typically May/June), the company will procure new floating and under-buoy hoses engineered by Beinit Energy (Dubai) to withstand monsoon conditions; permanent rectification and replacement work is planned during the fair weather season.
- The spare parts strategy: The company will procure and stock ~30 pieces of 10-meter hose sections onboard the FSO, plus a spare hose of 225 meters at a cost of ~$250,000–$300,000, to enable quick replacement if subsequent leaks occur.
- The timeline: All procurement, engineering, inspections, and certifications will be completed before May/June so facilities can handle full monsoon production; hoses will be changed before May to avoid risk.
Dirok: Steady, with a Pipeline Ambition
- Volume and pricing: Average daily gas sales rose to 3.4 crore scf/day in Q2 from 2.5 crore scf/day in Q1; the share of premium gas sales increased marginally to 45%, realizing a minimum $1 premium over the $6.1/MMBTU government notified price.
- Revenue contribution: Gas and oil price increases at Dirok contributed ~Rs.55 crores to H1 FY23 standalone revenue; Q2 revenue was ~Rs.62 crores and is expected to increase ~30% with the new gas price of $8.57/MMBTU, subject to continued offtake.
- The pipeline initiative: Site grading work has begun for a proposed 18-inch pipeline from Dirok to the Duliajan marketing hub, independent of Oil India's pipeline network, to enable future connection to the Northeast gas grid and significantly enhance market size.
- The strategy: Continued focus on value over volume; additional wells will be drilled only after consistent offtake is established; no new customers were added, with existing customers continuing offtake at similar levels.
Capital Raise: The Enabler for Everything Else
- The dual purpose: Equity and debt are being raised to address working capital issues arising from revenue-cost mismatch, and to fund development of dormant assets including PY-1 drilling and B-80 expansion wells.
- The equity component: Shareholders have approved Rs.250 crores; all options including a rights issue are being evaluated; management emphasized dilution "for a value and not at any cost" and intends to raise the equity within ~3 months.
- The deployment plan: A major portion (~Rs.100 crores) is earmarked for PY-1 development drilling and working capital; the entire equity capital is to be deployed on development within ~6 months.
- The B-80 expansion dependency: The first new well of the expansion program, costing ~$8 million, will be drilled only after equity is raised; the total program is ~$24 million plus ~$26 million.
- The asset-level strategy: Where HOEC has high participating interest, plans exist to bring in farm-in partners to dilute and reduce risk exposure at the asset level, at an appropriate time and right price.
- The debt component: Debt will be raised as required to correct the working capital mismatch.
R. Jeevanandam: "We are running an oil and gas company and have got 11 assets in the company. We are not running B-80 alone."
Other Assets: Small Steps, Long Paths
- PY-1: 100% owned and operated; small-volume gas sales to GAIL continuing since May 2022; an extensive G&G review has been completed and drilling locations identified; block extension is valid until 5th December, with the company planning to secure a further extension.
- Cambay: Production operations continuing; the ringfenced PSC for the R2 area is still awaited from the government.
- Kharsang: Normal production continuing; the government is insisting on cost recovery limits as a condition for PSC extension, with discussions ongoing between the government and the operator.
- Northeast blocks (Kherem, Umatara): The regulatory process for forest and environmental clearances is continuously being pursued.
- PY-3: Operated by another company; a legal dispute is ongoing and the matter is sub judice; the field remains shut down since 2011 with no update available.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| D1 well repair | Sealant injection fix to be executed; backup plan to pull tree cap and tighten joint or change flying lead if sealant fails | December 2022; completed before March/April 2023 |
| Permanent monsoon-proofing | Procure replacement hoses, complete engineering, inspections, certifications; change hoses before monsoon | Before May/June 2023 |
| Spare hose procurement | Procure ~30 pieces of 10-meter hose sections and 225-meter spare hose (~$250,000–$300,000) | Order placed imminently; stocked before May |
| Equity fundraise | Raise ~Rs.250 crores via equity (mode TBD); deploy entire equity capital on development | Raised within ~3 months; deployed within ~6 months |
| B-80 expansion drilling | Drill first new well (~$8 million cost) from expansion program | Only after equity is raised |
| PY-1 block extension | Secure further extension beyond current validity | Before 5th December 2022 |
| B-80 gas contract Year 2 | 75% annual take-or-pay at committed price comes into force; option to raise volume to alternate customers | From April 2023 |
Key Metrics
| Metric | Q2 FY23 |
|---|---|
| Revenue (standalone) | ₹81.69 cr, vs ₹70.19 cr in Q1 FY23 |
| Revenue (consolidated) | ₹125.79 cr, vs ₹91 cr in Q1 FY23 |
| Standalone profit after tax | ₹6.57 cr, vs ₹34.21 cr in Q1 FY23 |
| Consolidated profit after tax | ₹17.71 cr, vs ₹32.35 cr in Q1 FY23 |
| Consolidated EBITDA | ₹46.16 cr, vs ₹52.97 cr in Q1 FY23 |
| Total standalone expenses (incl. DDA) | ₹75.12 cr, vs ₹35.98 cr in Q1 FY23 |
| Total consolidated expenses (incl. DDA) | ₹105.71 cr, vs ₹59.08 cr in Q1 FY23 |
| B-80 gas production rate (D2 well) | ~1.1 crore scf/day, delivering full contract volume of 1 crore scf/day |
| B-80 gas price (November 2022) | ~$13.5 per MMBTU, adopting IGX monthly prices; June realized price was $20 per MMBTU |
| B-80 shutdown duration | Over 110 days, from 14 July to 31 October |
| Dirok average daily gas sales | 3.4 crore scf/day, vs 2.5 crore scf/day in Q1 FY23 |
| Dirok share of premium gas sales | 45%, marginally increased from Q1 FY23 |
| Dirok premium gas price | Minimum $1 premium over government notified price of $6.1 per MMBTU |
| B-80 operating cost at consol level (D2 well only) | $5 per MMBtu, after accounting for FSO and MOPU revenue; marginal cost is $5.35 per MMBtu |
| D1 well repair cost (sealant option) | ~$250,000 (~₹2 cr) |
| Spare hose procurement cost | $250,000 to $300,000 for under-buoy and floating hoses |
| Shareholder-approved equity fundraise quantum | ₹250 cr, intended to be raised within ~3 months |