Key Takeaways
- A shutdown quarter, but standalone profit rose: B-80 field was shut for ~1.5 months for pipeline cleaning, slashing its revenue to ₹19 cr from ₹83 cr QoQ. Yet standalone PAT improved to ₹38.7 cr from ₹21.3 cr, driven by a Dirok rebound and lower opex.
- Dirok is the swing factor, and it is demand-constrained: The field can produce ~50 mmscfd but offtake is throttled by customer shutdowns and a dual-pricing regime that pushes PSU buyers to cheaper nominated-field gas first.
- B-80 is in a normal, messy ramp-up phase: The D1 well is shut with a suspected mechanical blockage, and management frames the one-by-one problems as typical for a field with less than 12 months of production; it expects two years to reach stability.
- A discretionary ₹835 cr three-year capex plan is laid out, but not committed: The program spans 11 development wells, 2 exploration wells and 5 workovers, funded from internal accruals with equity only if results justify acceleration.
- What to watch next quarter: Whether the B-80 crude auction via M-Junction delivers a first offtake in Jan 2024, the Baker Hughes diagnosis on the D1 well, and any Dirok offtake normalisation as customers return.
B-80 Field: Shutdown, Restart and the D1 Problem
- Shutdown cause and impact: The field was shut for ~1.5 months to clean wax deposition from the oil export line, reducing B-80 standalone revenue to ₹19.03 cr from ₹83.44 cr QoQ and wiping out ₹33.77 cr in consolidated FSO and MOPU day-rate income.
- D2 well performance: The well continues producing at ~1,000 barrels per day and 5 mmscfd, with oil output slightly above the 800-900 bbls seen in testing. Management wants at least one year of continuous data before re-evaluating the reservoir.
- D1 well status: The well could not be activated post-cyclone; in-house analysis points to a mechanical obstruction in the tubing, likely wax, not a reservoir issue. Baker Hughes has been engaged to study the problem and recommend a fix, but no timeline is given pending the study outcome.
- Top-side issues: Additional topside problems are expected to be resolved by March.
- Crude auction process: A fresh third-party assay has been ordered for the ~70,000-80,000 barrels of D2 crude; results are expected by end-November, after which M-Junction will auction the crude among potential buyers, with first offtake possible in January 2024.
- FSO/MOPU economics: Full day-rate charges apply regardless of how many wells are producing; during the shutdown, no day rates were charged, and only 44 operating days were completed in the quarter with 46 more needed.
R Jeevanandam: "If you look at, the total production from the field is less than 12-months. So, the problems are coming one-by-one. We are trying to address it and normally it will take about two years for any field to get a stable production."
Dirok: Demand Constraint and the Path to 70 mmscfd
- Demand, not supply, is the bottleneck: Dirok can produce ~50 mmscfd but output is restricted by customer breakdowns, maintenance shutdowns and a dual-pricing regime. PSU customers prioritise nominated-field gas at US$6.5/MMBTU over private-player gas at US$9.20/MMBTU, leaving Dirok offtake volatile and demand-driven.
- Q2 performance: Revenue improved to ₹49.68 cr from ₹21.17 cr QoQ as offtake recovered from a prior-quarter customer shutdown, though production was still only about one-third of normal. A return to 28-30 mmscfd is expected in Q3 once customers are back online.
- Pipeline progress: 15 km of the forest section has been laid; management is requesting Oil India for a tie-in at Kathalgudi to sell gas via the existing 15 km line while the balance 15 km is completed, a process expected to take two seasons and finish by end of 2024.
- National Grid connectivity: The DNPL line is expected to connect to the IGGL grid in Q1/Q2 of FY24-25, easing the local demand constraint. The new IGGL 180 km line from Duliajan to Numaligarh, expected in FY25-26, will connect Dirok to the central India gas grid, removing the demand ceiling entirely.
- Ramp-up plan: With workovers on three legacy wells (Dirok-1, 2 and 4) starting in Q4 FY24, plus existing producers, output can reach 50 mmscfd. Two additional producers and reserve re-estimation support a further ramp to 70 mmscfd, effectively from FY25-26.
R Jeevanandam: "This is further compounded by dual pricing for gas produced from the nominated fields of OIL and private players... the customers who are mostly public sector undertakings would like to avail the low-price gas of $6.5 per MMBTU before availing the gas from private players at a higher price."
Kharsang and the Diversification Push
- Production improvement: Output rose to ~432 barrels per day from ~350 bbls on average over the prior six months, following acid jobs and workovers.
- GeoEnpro consolidation: The balance 50% stake in GeoEnpro was acquired, making it a wholly owned subsidiary and removing the ₹18 cr investment in associates from the books. GeoEnpro is the operator of Kharsang, where HOEC now holds 35% participating interest directly and indirectly.
- Six-well development program: Six development wells targeting ~1,500 meters in the upper Girujan formation are planned, with environmental clearance expected by end-December 2023. The program aims to lift production to ~1,000 barrels per day.
- Deeper appraisal: While drilling the six development wells, one well will be taken to 3,000 meters to appraise deeper formations (lower Girujan, Tipam, Barail), which are expected to be gas-bearing, subject to JV partner consent.
- Strategic intent: Management explicitly wants to reverse revenue concentration on B-80 and Dirok by developing Kharsang and PY-1, moving from dependence on two blocks to five blocks by 2026-27.
Other Assets: PY-1, Palej, North Balol, Asjol, Block-19
- PY-1 drilling: Three development wells are planned, with the first well targeted to spud at the end of Q1 FY24-25, subject to a third-party review of proposed locations by a London-based expert in fractured basement reservoirs. Incremental volumes will be sold at market price or PPAC price, whichever is higher.
- Palej: Artificial lifts using SRPs are being sourced for all three wells. After results and PSC signing for the R-2 contract area, 3D seismic acquisition and additional drilling are planned.
- North Balol: Two additional producers are planned immediately after environmental clearance is received.
- Asjol: Two producers are planned, with the well count to increase based on drilling results.
- Block-19 (Greater Dirok): Seismic reprocessing is complete and a Geo Technical Order is to be released before month-end. One exploration well is planned in the 2024-25 work program. The block is 100% owned by HOEC and sits between Dirok and Kharsang.
Financial Position and Capital Program
- Standalone vs consolidated divergence: Standalone revenue and profit improved QoQ on the Dirok rebound and lower B-80 opex. Consolidated revenue and PAT fell because of lost D1 production and the reduction of MOPU/FSO charges to 50% during the shutdown.
- Inventory mark-to-market: Stock adjustment rose to ₹43.52 cr from ₹27.70 cr QoQ as crude oil prices moved from US$74.93/bbl (June 30) to US$93.54/bbl (Sep 30).
- Debt position: Total debt is ~₹190 cr (standalone ₹112 cr + subsidiary ₹78 cr), not the ₹400 cr estimated by an analyst. Management stated no further borrowing is planned; investments will be funded from internal accruals or equity.
- Discretionary capex of ₹835 cr over three years: The program covers 11 development wells, 2 exploration wells and 5 workovers in FY24-25; 5 development wells in FY25-26; and 3 B-80 development wells in FY26-27. Management describes this as discretionary, not committed, and expects internal accruals to cover it, with equity raised only if drilling results justify acceleration.
- Insurance gap: Loss-of-profit insurance is not available for production loss; only accident-caused loss can be covered.
R Jeevanandam: "We are not going to borrow anymore for investments. It will be mostly from internal accruals and if required we will raise equity from our shareholders."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| B-80 crude first offtake | Auction via M-Junction after third-party assay | Assay results end-Nov 2023; first offtake possibly Jan 2024 |
| B-80 top-side issues resolved | Top-side problems to be fixed | By March 2024 |
| Dirok workovers | Workover of three legacy wells (Dirok-1, 2, 4) to enhance production | Start Q4 FY24 |
| Dirok pipeline tie-in | Request to Oil India for tie-in at Kathalgudi to sell gas via existing 15 km line | Balance 15 km pipeline completion by end of 2024 |
| DNPL line connection to IGGL | Easing local demand constraint for Dirok gas | Q1/Q2 FY24-25 |
| IGGL 180 km line to Numaligarh | Full connectivity to national gas grid, removing Dirok demand ceiling | FY25-26 |
| Kharsang 6-well development drilling | Targeting upper Girujan at ~1,500m; EC clearance expected end-Dec 2023 | Production increase to ~1,000 bbls/day |
| PY-1 first development well spud | Subject to third-party review of locations | End of Q1 FY24-25 |
| Three-year discretionary capex of ₹835 cr | 11 dev wells, 2 exploration wells, 5 workovers in FY24-25; 5 dev wells in FY25-26; 3 B-80 dev wells in FY26-27 | FY24-25 through FY26-27, funded by internal accruals |
| Reserve re-estimation | In-house G&G study followed by third-party validation; B-80 re-estimation after two years of production data | After workover data and production history |
Key Metrics
| Metric | Q2 FY24 |
|---|---|
| Standalone revenue | ₹72.56 cr, vs ₹108.69 cr in Q1 FY24 |
| Consolidated revenue | ₹119.74 cr, vs ₹187.14 cr in Q1 FY24 |
| Standalone EBITDA | ₹49.05 cr, vs ₹37.82 cr in Q1 FY24 |
| Consolidated EBITDA | ₹70.64 cr, vs ₹96.86 cr in Q1 FY24 |
| Standalone profit after tax | ₹38.74 cr, vs ₹21.34 cr in Q1 FY24 |
| Consolidated profit after tax | ₹43.17 cr, vs ₹66.07 cr in Q1 FY24 |
| Standalone field operating expenses | ₹50.46 cr, vs ₹73.07 cr in Q1 FY24 |
| Consolidated operating expenses incl. facilities | ₹63.63 cr, vs ₹84.38 cr in Q1 FY24 |
| Standalone DDA | ₹4.77 cr, vs ₹8.85 cr in Q1 FY24 |
| Consolidated DDA | ₹18.37 cr, vs ₹20.06 cr in Q1 FY24 |
| Stock adjustment credit | ₹43.52 cr, vs ₹27.70 cr in Q1 FY24; crude valued at US$93.54/bbl on Sep 30, 2023 vs US$74.93/bbl on Jun 30, 2023 |
| B-80 block revenue | ₹19.03 cr, vs ₹83.44 cr in Q1 FY24; shutdown of ~1.5 months for export line cleaning |
| Dirok revenue | ₹49.68 cr, vs ₹21.17 cr in Q1 FY24 |
| Dirok gas offtake | 2.3 crore scf/day average, up from 1 crore scf/day in Q1 FY24 |
| Dirok gas sales volume | 0.56 BCF gas and 10,350 barrels condensate, vs 0.24 BCF and 4,573 barrels in Q1 FY24 |
| Kharsang production | ~432 bbl/day, vs ~350 bbl/day average in prior 6 months |
| B-80 D2 well production | ~1,000 bbl/day oil and ~5 MMSCF/day gas |
| Total oil in stock in FSO | ~372,000 barrels; 60% HOEC share |
| Consolidated book value of equity | ₹1,090 cr, post GeoEnpro consolidation |
| Outstanding loans (standalone + subsidiary) | ₹112.34 cr standalone + ₹77.50 cr subsidiary as of Oct 2023 |
| Discretionary capex plan (FY25–FY27) | ₹835 cr for 20 wells and 5 workovers over three years |
| Dirok ceiling gas price (non-nominated) | US$9.20/MMBTU as of Oct 2023; nominated fields at US$6.50/MMBTU |
| PY-1 development drilling cost estimate | US$50 million for three wells and facilities |
| Loss of FSO and MOPU day rates | ₹33.77 cr due to B-80 shutdown |