Hindustan Oil Exploration Company Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/n7x39b69yweqav159pnsv118.pdf

Key Takeaways


B-80 Field: Shutdown, Restart and the D1 Problem

R Jeevanandam: "If you look at, the total production from the field is less than 12-months. So, the problems are coming one-by-one. We are trying to address it and normally it will take about two years for any field to get a stable production."

Dirok: Demand Constraint and the Path to 70 mmscfd

R Jeevanandam: "This is further compounded by dual pricing for gas produced from the nominated fields of OIL and private players... the customers who are mostly public sector undertakings would like to avail the low-price gas of $6.5 per MMBTU before availing the gas from private players at a higher price."

Kharsang and the Diversification Push


Other Assets: PY-1, Palej, North Balol, Asjol, Block-19


Financial Position and Capital Program

R Jeevanandam: "We are not going to borrow anymore for investments. It will be mostly from internal accruals and if required we will raise equity from our shareholders."

Guidance & Commitments

CommitmentSpecificsTimeline
B-80 crude first offtakeAuction via M-Junction after third-party assayAssay results end-Nov 2023; first offtake possibly Jan 2024
B-80 top-side issues resolvedTop-side problems to be fixedBy March 2024
Dirok workoversWorkover of three legacy wells (Dirok-1, 2, 4) to enhance productionStart Q4 FY24
Dirok pipeline tie-inRequest to Oil India for tie-in at Kathalgudi to sell gas via existing 15 km lineBalance 15 km pipeline completion by end of 2024
DNPL line connection to IGGLEasing local demand constraint for Dirok gasQ1/Q2 FY24-25
IGGL 180 km line to NumaligarhFull connectivity to national gas grid, removing Dirok demand ceilingFY25-26
Kharsang 6-well development drillingTargeting upper Girujan at ~1,500m; EC clearance expected end-Dec 2023Production increase to ~1,000 bbls/day
PY-1 first development well spudSubject to third-party review of locationsEnd of Q1 FY24-25
Three-year discretionary capex of ₹835 cr11 dev wells, 2 exploration wells, 5 workovers in FY24-25; 5 dev wells in FY25-26; 3 B-80 dev wells in FY26-27FY24-25 through FY26-27, funded by internal accruals
Reserve re-estimationIn-house G&G study followed by third-party validation; B-80 re-estimation after two years of production dataAfter workover data and production history

Key Metrics

MetricQ2 FY24
Standalone revenue₹72.56 cr, vs ₹108.69 cr in Q1 FY24
Consolidated revenue₹119.74 cr, vs ₹187.14 cr in Q1 FY24
Standalone EBITDA₹49.05 cr, vs ₹37.82 cr in Q1 FY24
Consolidated EBITDA₹70.64 cr, vs ₹96.86 cr in Q1 FY24
Standalone profit after tax₹38.74 cr, vs ₹21.34 cr in Q1 FY24
Consolidated profit after tax₹43.17 cr, vs ₹66.07 cr in Q1 FY24
Standalone field operating expenses₹50.46 cr, vs ₹73.07 cr in Q1 FY24
Consolidated operating expenses incl. facilities₹63.63 cr, vs ₹84.38 cr in Q1 FY24
Standalone DDA₹4.77 cr, vs ₹8.85 cr in Q1 FY24
Consolidated DDA₹18.37 cr, vs ₹20.06 cr in Q1 FY24
Stock adjustment credit₹43.52 cr, vs ₹27.70 cr in Q1 FY24; crude valued at US$93.54/bbl on Sep 30, 2023 vs US$74.93/bbl on Jun 30, 2023
B-80 block revenue₹19.03 cr, vs ₹83.44 cr in Q1 FY24; shutdown of ~1.5 months for export line cleaning
Dirok revenue₹49.68 cr, vs ₹21.17 cr in Q1 FY24
Dirok gas offtake2.3 crore scf/day average, up from 1 crore scf/day in Q1 FY24
Dirok gas sales volume0.56 BCF gas and 10,350 barrels condensate, vs 0.24 BCF and 4,573 barrels in Q1 FY24
Kharsang production~432 bbl/day, vs ~350 bbl/day average in prior 6 months
B-80 D2 well production~1,000 bbl/day oil and ~5 MMSCF/day gas
Total oil in stock in FSO~372,000 barrels; 60% HOEC share
Consolidated book value of equity₹1,090 cr, post GeoEnpro consolidation
Outstanding loans (standalone + subsidiary)₹112.34 cr standalone + ₹77.50 cr subsidiary as of Oct 2023
Discretionary capex plan (FY25–FY27)₹835 cr for 20 wells and 5 workovers over three years
Dirok ceiling gas price (non-nominated)US$9.20/MMBTU as of Oct 2023; nominated fields at US$6.50/MMBTU
PY-1 development drilling cost estimateUS$50 million for three wells and facilities
Loss of FSO and MOPU day rates₹33.77 cr due to B-80 shutdown