Hindustan Oil Exploration Company Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/yut3ps2a7lbmcapql0fl41sp.pdf

Key Takeaways


Production & Operational Recovery

Baroruchi Mishra: "We requested their core competency to assess our field and they did that, and they have come back with the report that we can still make 1.5 crore to 2 crore SCFs of gas in this field. That is phenomenal..."

B-80: Workover, Drilling & Monetization

Baroruchi Mishra: "So how wrong can we go? That's the question that we have to answer. Even if I have half that amount, I'm still doing well."

Assam Gas: Dirok, Evacuation & the Grid Connection

Baroruchi Mishra: "This has 3,000 psi header pressure. That tells you about the potential of this hydrocarbon system."

PY-1 Revival: Intervention, Compressors & the Take-or-Pay Condition

Baroruchi Mishra: "If I don't have a firm gas sales contract, take-or-pay contract and I spend USD2 crore-USD2.5 crore drilling these wells, and then I have to shut them down. I'll be back to square one, what happened 20 or 15 years ago when these wells came on stream."

Kharsang, Cambay & Other Assets


Funding, Capital Discipline & the Balance Sheet

Baroruchi Mishra: "That puts a lot of challenge on us and expectations from the shareholder community to fast monetize these reserves because out of the 10.4 crore barrels of oil equivalent, we have not produced more than 5 or 6. So there is an opportunity for us to run as if there is no tomorrow."

Guidance & Commitments

CommitmentSpecificsTimeline
B-80 workover production1,000–1,500 bbl/day oil + 0.5–0.7 crore SCF/day gasEnd Dec / early Jan
B-80 new wells drilling finish3 wells drilled; rig demobilized for tow insuranceBy 15 May
B-80 new wells on streamProducing from new wellsJune 2028
DNPL grid connectionSpur line tie-in to national gas gridDec-end; best case mid-Dec
Kharsang drilling start9 wellsJan / early Feb
Kharsang gas pipeline24-km pipeline to Assam pipelineWithin 18 months
North Dirok drilling startExploration/appraisal wellJan / Feb next year
PY-1 coil tubing interventionSLB contract signed; increase productionPost-monsoon (underway)
PY-1 new wells2 wells, contingent on take-or-pay contractMid next year (P50 chance of contract)
B-15 development on streamAdding 3,000–3,500 boe/dayJune 2028
B-174 drilling startDevelopment drillingOctober 2028
Production target11,000 boe/day net HOECMid-2027
Production target22,000 boe/day net HOECFY28
Production target30,000–32,000 boe/day net HOECFY29
Palej R2 PSC extensionPSC extensions in placeJanuary
B-80 FSO crude disposal120,000–130,000 barrels soldBetween Jan and Mar next year

Key Metrics

MetricQ2 FY27
Consolidated revenue₹151.78 cr, +25% QoQ from ₹117 cr
EBITDA₹37.51 cr, more than doubled QoQ from ₹21 cr; margin 24.71% (Note: CFO stated EBITDA more than doubled from ₹21 cr to ₹46 cr on page 9)
Profit before tax₹38 cr, tripled QoQ from ₹12.5 cr
Profit after tax₹19.03 cr
H1 FY27 revenue₹275.78 cr, vs ₹405 cr in H1 FY26 which included a one-time ₹258 cr HPCL sale
H1 FY27 EBITDA₹63.18 cr, up 20% YoY from ₹56 cr (Note: CFO stated EBITDA up 20% from ₹56 cr to ₹67 cr on page 10)
H1 FY27 PAT₹25.10 cr, up 46% from adjusted profit of ₹17.18 cr in H1 FY26
H1 operating cash surplus₹39 cr, vs negative ₹18 cr in H1 FY26; swing of ₹57 cr (Note: CFO also stated H1 operating cash was ₹18.23 cr on page 10)
Net debt₹44.90 cr, net debt to EBITDA at 0.71x
Gross debt₹211.11 cr
Cash and cash equivalents₹166 cr at September-end consolidated
B-80 HPCL inventory monetized in H1₹80 cr realized, with approximately 36,103.90 metric tons remaining
B-80 HPCL stock revenue in Q2₹57.79 cr added to revenue
Dirok gas realization$7.8–$8 per MMBTU in Q2; currently $12 per MMBTU, linked to Indian crude basket
Dirok production2.21 cr SCFs per day, up from 14–15 range in prior quarters
Net production target11,000 boe/day by mid-2027; 22,000 by FY28; 30,000–32,000 by FY29
2P reserves10.4 cr boe, crossed 10 cr with award of B-174
B-80 workover target1,000–1,500 bbl/day oil and 0.5–0.7 cr SCFs/day gas post-workover
B-80 capex$60 mn ($45 mn wells + $15 mn workover), unchanged from last quarter
Loan raised for workovers₹125 cr, part of ₹179 cr total raised including credit facilities
Crude awaiting disposal in FSO120,000–130,000 barrels in B-80 field