Key Takeaways
- Profit hit by inventory write-down, not operations: Standalone PAT fell to ₹4.82 cr from ₹38.74 cr QoQ, almost entirely because crude oil prices dropped from $93.54 to $77.42 per barrel, shrinking the stock adjustment credit. The underlying fields performed.
- B-80 reached first oil sale milestone: The field offloaded 430,652 barrels to IOC at $80.27/barrel, but Q4 sales will drop sharply to ~1,10,000-1,20,000 barrels because inventory built since start-up is now depleted and daily production is ~800 barrels.
- D-1 well is a material, unresolved outage: The well stopped producing after a cyclone, mechanical obstructions were cleared, but a reservoir blockage remains. Baker Hughes has been contracted for chemical treatment, with results expected by end-March. Management declined to put any numbers on recovery.
- Dirok is a stranded asset until pipelines arrive: The field can produce ~50 mmscfd but is capped by demand and dual pricing. Relief comes in stages: DNPL line upgrade by October 2024, IGGL line by March 2026, full grid connectivity by 2026-27.
- What to watch next quarter: Whether Baker Hughes' chemical treatment restarts D-1, the new B-80 gas contract post-March e-auction, and any EC clearance for Kharsang and Western region drilling programs.
B-80 Field: First Oil, Then a Reset
- First sale completed, inventory now lean: The field reached parcel size of 430,652 barrels and sold its first cargo to IOC at $80.27/barrel (Brent less 0.06%). That volume was accumulated since production began, so Q4 sales will be only ~1,10,000-1,20,000 barrels from current stock of ~35,000 barrels plus daily output.
- D-2 well behaving as expected: Gas production is declining and oil production is increasing, a typical phenomenon for a well with a gas cap. Oil rose from 400 to 800 barrels/day. Management expects production to maintain at current levels of ~800 barrels/day plus ~0.35 crore gas.
- D-1 well is the swing factor: The well was producing before a cyclone and stopped abruptly. Mechanical issues in the flowline and tubing have been resolved, but a reservoir blockage (asphaltene and wax deposition) remains. Baker Hughes is mobilizing equipment, chemicals and personnel, with operations expected to complete before end-March. Results will determine if further chemical treatment or a rig intervention is needed, the latter only possible after monsoon.
- Gas contract renewal imminent: The current B-80 gas contract expires 31st March. The e-auction process for a new contract begins by the first or second week of March. Gas is priced at 22.2% of oil price.
- Topside ready for higher output: All topside work is complete and the facility can handle up to 3,000 barrels/day if subsurface output reaches that level.
Management: "This is the well which was producing before the cyclone and after the cyclone it stopped producing. So, it is a surprise to all of us."
Dirok: Production Capability Outruns Market Access
- Demand, not geology, is the bottleneck: The field can produce ~50 mmscfd but is restricted by lack of demand, compounded by dual pricing. PSU customers buy nominated-field gas at $6.5/MMBTU first, leaving private gas at $8.93/MMBTU as a fallback. Dirok acts as a swing supplier, getting differential demand only after cheaper gas is absorbed.
- Pipeline connectivity is the unlock, arriving in three tranches: The DNPL line upgrade is expected by October 2024, which should allow a ramp to ~40 mmscfd. The IGGL new line from NRL to Duliajan is expected by March 2026. Full connectivity to the national grid by 2026-27 would eliminate the demand constraint entirely and allow the field to reach its full potential of ~70 mmscfd.
- Workovers and new drills timed to pipeline readiness: Three legacy wells (Dirok-1, 2, 4) will be worked over, with data used to revise reserve estimates. Two additional producers are planned, with drilling timed so that when lines connect and demand picks up, the wells are ready to market. Each well takes 3-4 months.
- Forest section pipeline progressing: 50% of the forest section pipeline is complete, with the balance expected by December 2025.
R Jeevanandam: "Though, this field can produce about 50 mmscfd, we must restrict the production due to lack of demand. This is further compounded by dual pricing for gas produced from the nominated fields of OIL and private players."
Drilling Catalyst: Kharsang, PY-1 and the Western Blocks
- Kharsang enters a two-year continuous drilling program: The Operating Committee approved 15 development wells and 1 exploration well. Wellheads, Xmas trees and tubulars are already procured. Drilling is expected to begin Q1 FY25 after EC clearance, with a small pause after six wells to review data, then continuing through FY25 and FY26. A second rig is being sourced for deeper formations (lower Girujan, Tipam, Barail) where GCA identified substantial upside.
- PY-1 moves toward a mid-2025 spud: An in-house G&G study identified three drilling locations. A third-party expert from London is reviewing fracture basement data for ~15 days. If confirmed, the first well is planned for April-June 2025. Management described itself as "abundantly cautious" and has not yet procured a rig.
- Western region blocks await EC: Asjol and North Balol are planning two development wells each, with EC expected before March 2024. Palej is planning artificial lifts on all three wells, awaiting partner approval; work duration is short (not more than 10 days per well), so ramp-up should be fast. Cambay has a proposal submitted to partners for three wells on artificial lift to reach 500 barrels of oil equivalent per day.
- Umarthra rig mobilizing: IOCL, the operator, is ready to mobilize a rig by April. HOEC holds only a 10% participating interest.
R Jeevanandam: "Our team has done a good work, and they are very confident about it and drilling three wells have been identified, but we wanted to be abundantly cautious."
Production Ramp-Up Plan
- Three-year net production target: Management laid out a plan to move net production from at least 0.1 crore barrels of oil equivalent to 0.15 crore by next year, and to 0.3 crore by 2026. This was described as "the best case and the minimum."
- Longer-term ambition: The target is to reach 10,000 barrels of oil equivalent net daily production, with at least 3,000 barrels of oil equivalent expected from B-80 alone.
- Capital program backs the plan: ₹1,000 crores over three years: ₹160 cr in FY25, ₹540 cr in FY26, ₹300 cr in FY27. Funding will come from internal accruals and cash flow. Management stated it will not do any project with an IRR below 21% post-tax.
- Talent pool to expand: Management plans to increase the talent pool to meet growth targets.
Management: "We have a plan for three years. We have lined up the program. Our net production should move from at least 0.1 crore barrel of oil equivalent to 0.15 crore by next year and it should go to 0.3 crore by 2026. That is what we are planning for it."
Financials: The Inventory Effect
- Standalone revenue rose, profit fell: Revenue increased to ₹109.04 cr from ₹72.56 cr QoQ, driven by B-80 (₹48.43 cr vs ₹19.03 cr) and Dirok (₹56.7 cr vs ₹48.68 cr). But standalone PAT collapsed to ₹4.82 cr from ₹38.74 cr because the stock adjustment credit shrank to ₹3.4 cr from ₹43.52 cr as crude prices fell.
- Consolidated PAT held stable: At ₹46.57 cr vs ₹43.73 cr QoQ, supported by increased operational days of FSO and MOPU (₹35.55 cr) and B-80 production, despite higher field operating expenses (₹76.23 cr vs ₹50.46 cr) from more B-80 operating days.
- Windfall tax not applicable: The company has not reached the threshold limit for windfall tax on petroleum.
- Management declined to provide forward financials: When asked for revenue and operating cash flow forecasts for FY25 and FY26, management said "I can't give you the exact number" and instead reiterated comfort with the expenditure level. An internal revenue target linked to the ₹1,000 cr capex program was also not disclosed.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| D-1 well chemical treatment | Baker Hughes to complete operations; results will determine next steps (further chemical treatment or rig intervention post-monsoon) | End-March 2024 |
| B-80 gas contract renewal | E-auction process to begin | First or second week of March 2024 |
| DNPL pipeline upgrade | Enables Dirok ramp to ~40 mmscfd | October 2024 (±1 month) |
| Kharsang development drilling | 15 development wells + 1 exploration well, continuous program over two years | Q1 FY25 start, after EC clearance |
| Asjol & North Balol development wells | Two wells each | After EC, expected before March 2024 |
| PY-1 exploration drilling | First well spud, subject to third-party confirmation of locations | April-June 2025 |
| IGGL pipeline (NRL to Duliajan) | Further Dirok demand relief | March 2026 |
| Full grid connectivity for Dirok | Eliminates demand constraint, enables ~70 mmscfd | 2026-27 |
| Three-year capex program | ₹1,000 cr total (₹160 cr FY25, ₹540 cr FY26, ₹300 cr FY27), funded by internal accruals | FY25-FY27 |
| Net production ramp | 0.1 → 0.15 crore BOE (next year) → 0.3 crore BOE (2026) | FY25, FY26 |
| Dirok forest section pipeline | Balance 50% completion | December 2025 |
Key Metrics
| Metric | Q3 FY24 |
|---|---|
| Standalone revenue | ₹109.04 cr, up from ₹72.56 cr in Q2 FY24 |
| Consolidated revenue | ₹192.75 cr, up from ₹119.74 cr in Q2 FY24 |
| Standalone EBITDA | ₹16.74 cr, down from ₹49.05 cr in Q2 FY24 |
| Consolidated EBITDA | ₹80.14 cr, up from ₹72.58 cr in Q2 FY24 |
| Standalone profit after tax | ₹4.82 cr, down from ₹38.74 cr in Q2 FY24 |
| Consolidated profit after tax | ₹46.57 cr, up from ₹43.73 cr in Q2 FY24 |
| Standalone field operating expenses | ₹76.23 cr, up from ₹50.46 cr in Q2 FY24 |
| MTM loss impact on crude inventory | ₹26 cr, due to crude price decline from $93.54 to $77.42 per barrel |
| Net debt (consolidated) | ₹150 cr as on date |
| Outstanding loans (standalone) | ₹87.55 cr; subsidiary: ₹69 cr |
| B-80 crude price realised | $80.27 per barrel, Brent less 0.06%; first offloading of 430,652 barrels to IOC completed 30 Jan 2024 |
| B-80 D2 well oil production | 800+ barrels per day, gas at 3.5 MMSCF per day; one well operated entire 91 days of Q3 |
| Dirok gas offtake | 2.38 crore standard cubic feet per day average, up from 2.29 crore in Q2 FY24 |
| Dirok gas sale volume | 0.59 BCF, condensate 10,841 barrels; field can produce 50 mmscfd but restricted by demand |
| Dirok gas price (private producers) | $8.93 per MMBTU for Oct–Dec 2023, vs $6.5 ceiling for nominated fields |
| Capital outlay planned (next 3 years) | ₹1,000 cr: ₹160 cr in FY25, ₹540 cr in FY26, ₹300 cr in FY27 |
| Net production target | 0.3 crore barrels of oil equivalent by 2026, up from 0.1 crore currently; aspirational target 10,000 boe per day net |