Key Takeaways
- Production constrained, not capacity: Dirok can produce over 5 crore cubic feet of gas but is restricted by weak demand, while B-80 ran at full tilt for 92 days and lifted revenue. The quarter’s story is about offtake, not the reservoir.
- A ₹1,000 crore revenue ambition, self-funded: Management projects reaching ~₹1,000 crores in revenue by next financial year, funded entirely by EBITDA with no new debt, as CAPEX momentum shifts to FY26.
- The drilling catalyst is now tangible: A rig is secured for Kharsang, the first well spuds around 15 March, and nine shallow wells are planned; Dirok’s demand constraint is expected to ease by March-end as pipelines near completion.
- PY-1 and B-15 are the long-dated options: Petro Vietnam’s 90-day review of PY-1 and the sole bid for B-15 could redefine the reserve base, but neither contributes near-term cash flow and B-15’s award timing is unknown.
- What to watch next quarter: Whether the DNPL pipeline connection and Dirok demand constraint actually resolve by March-end, the pace of Kharsang’s nine-well program, and any B-15 award announcement.
Production & Operational Performance
- Dirok: potential trapped by demand. The field can produce more than 5 crore cubic feet of gas but output is curtailed because ONGC and OIL, with a ~$1 per mmbtu price advantage on nominated blocks, get first call on offtake. Full potential is achievable only when the demand constraint eases.
- B-80: a clean quarter of steady flow. Both wells produced for all 92 days with zero shutdowns; oil output rose to 88,073 barrels and gas to 0.6292 bcf, up from 58,000 barrels and 0.38 bcf in the prior quarter. A new hawser was installed, and the existing infrastructure can handle up to 10,000 barrels of oil and 2 crore cubic feet of gas per day.
- Oil stock credit swells with production. The credit adjustment rose from ₹13.6 crores to ₹29.47 crores, driven by 52,844 barrels of oil held vs 35,344 barrels last quarter, a direct consequence of continuous B-80 production.
- Volatility is structural, not episodic. Management flagged that quarterly results will swing with weather, price and demand, factors largely beyond the company’s control.
Jeevanandam: "Though this field can produce more than 5 crore cubic feet of gas, we have to restrict the production due to lack of demand."
Growth Catalysts & Drilling Timelines
- Kharsang: rig secured, spud imminent. A 1,000 HP rig is finalized and civil works are in progress; the first development well is expected to start around 15 March. The initial program targets nine shallow wells in the Upper Girujan sand at depths under 1,000–1,200 meters, with each well put on production within 10–15 days of drilling.
- Kharsang production target: a step-change in scale. If each well delivers ~100 barrels per day, the nine-well program could push field output past 1,000–1,200 barrels per day in the next financial year, a material uplift from current levels.
- Dirok demand relief: a pipeline story. The GAIL line to Guwahati is complete and the Guwahati-to-Numaligarh section is under commissioning; the DNPL line is under repair with connection expected by end-March. Management expects the demand constraint to resolve by the end of this financial year, though the timeline is set by authorities, not HOEC.
- Dirok ramp-up: fast once unblocked. Once the pipeline connection is live, production can ramp up quickly; management expects Dirok to contribute from Q1 FY26, initially at 3–3.5 crore cubic feet, with the full 5.5 crore dependent on further infrastructure.
- B-80 scale-up: drilling under internal review. The next production step-change requires new wells; the field development plan targets at least six wells over a 20-year contract. Drilling was planned for FY26–27 but management is internally discussing whether to advance it, with in-house basic engineering and external experts for detailed engineering.
- Cambay: clearance unlocks activity. After a four-year wait, environmental clearance was secured for North Balol and Asjol; a rig is secured for workover of two wells and drilling of two more, pending JV partner approval.
Jeevanandam: "Our first well will start, we expect it to start by 15th of March, plus minus one week."
PY-1 & B-15: The Long-Dated Options
- PY-1: a specialist review, not a commitment. Petro Vietnam has been contracted to evaluate the block’s full potential and review geological models, not just the three previously identified locations. Data uploading has started and the 90-day review clock begins next week. Any drilling would commence in FY25–26 only if the review supports it.
- B-15: sole bidder, no timeline. HOEC is the sole bidder for Block B-15 in the Mumbai offshore DSF Special Bid Round 2024 and believes substantial potential exists. However, the company has been waiting three months for an award announcement and will know only when the government declares it. Once awarded, the field must be put on production within 24 months, implying a P&L contribution no earlier than FY27–28.
Jeevanandam: "It is like a specialist doctor you know, instead of going for a general physician you go for a specialist doctor to get the full review done."
Financial Position & Capital Allocation
- ₹1,000 crore revenue target, wishful but grounded. Consolidated nine-month revenue stands at ~₹500 crores, with the full year expected around ₹800 crores. Management projects reaching ₹1,000 crores next financial year, driven by full Dirok potential, continuous B-80 production, and new Kharsang wells.
- CAPEX: delayed now, accelerating soon. Planned CAPEX for the current year went unspent because regulatory and environmental clearances for Kharsang and North Balol wells were delayed. All clearances are now in place, and spending will gain momentum from FY26, with ~₹250 crores earmarked for the North-East and ~₹50–60 crores for the Western region over the next two years.
- Self-funded growth, no debt. Management was explicit: the ₹1,000 crore CAPEX plan will be funded entirely from EBITDA, with net debt or net cash status maintained over the next two to three years. No debt will be taken.
- Currency depreciation: non-cash, balance-sheet flow. Currency depreciation is treated as a non-cash item that moves through the balance sheet and into the income statement, not a cash outflow.
- Service assets: captive-first, opportunistic second. The company will explore acquiring smaller assets like a coil tubing unit or slickline unit next year, primarily for captive use, with third-party servicing only if idle time permits. Management explicitly ruled out building a service company.
Jeevanandam: "We will be reaching the revenue of 1000 crores... we will be able to reach to this revenue level by the next financial year that's our wishful projection."
Pricing, Offtake & Market Dynamics
- Gas pricing: a two-tier market. Private companies have marketing freedom and price based on demand and supply, with the PPAC price (10% of crude) as a benchmark. Nominated blocks for ONGC and OIL face a ceiling of $6.5 with a floor price, creating the ~$1 per mmbtu differential that disadvantages HOEC’s Dirok offtake.
- B-80 pricing: a floor, not a ceiling. Management will not sell below the PPAC price in the Eastern region; in the Western region, where demand is stronger and gas prices track imported LNG, it expects to sell above PPAC. For oil, the company targets $80 per barrel and uses storage capacity to wait if the spot price is unfavorable at the point of offload.
- Natural hedge in place. The company hedges both dollar and price exposure naturally, though no details on the specific instruments or structure were provided.
Jeevanandam: "We endeavor to sell it only at $80 not lesser than this."
Strategy & Corporate Positioning
- Acquisition appetite: opportunistic, not urgent. Management is always open to buying assets, with a simple philosophy: “buy it at a cost and sell it at a price.” The company is equally open to selling if expectations are met, and sees no shortage of opportunities in India or abroad.
- Reducing two-asset dependence. The stated focus is to complete drilling across onshore and offshore assets to increase both production and the reserve base, explicitly to reduce reliance on the two major assets, B-80 and Dirok.
- No revenue guidance, by design. When pressed for FY26 projections, management declined, calling guidance improper and unfair in this industry because “either way, I will be incorrect.” The only reference point offered: doing a little better than the current year.
Jeevanandam: "Always it is our strategy, we will buy it at a cost and sell it at a price."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Dirok demand constraint resolution | Demand constraint for HOEC’s gas volume to be resolved; timeline given by authorities | By end of current financial year (March 2025) |
| Kharsang first development well spud | First well to start drilling | Around 15 March 2025 |
| Kharsang nine-well program completion | Most of the nine wells drilling to be completed | Next financial year (FY26) |
| Kharsang production target | Surpass 1,000–1,200 barrels per day from the nine-well program | Next financial year (FY26) |
| Dirok production contribution | Ramp up to at least 3–3.5 crore cubic feet, demand permitting | From Q1 FY26 |
| PY-1 evaluation report | Petro Vietnam to deliver full field potential review | Within 90 days (from ~mid-February 2025) |
| B-15 field development | Field to be put on production within 24 months of award | Within 24 months of approval receipt |
| Revenue ambition | Reach ~₹1,000 crores consolidated revenue | Next financial year (FY26) |
| CAPEX funding | ₹1,000 crore CAPEX funded entirely by EBITDA; no debt taken; net debt/cash maintained | Over next two to three years |
| B-80 additional wells drilling | Drilling of additional wells; internally discussing advancing from original plan | Planned FY26–27, may be advanced |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Consolidated revenue | ₹156 cr, vs ₹100 cr in Q2 FY25 |
| Standalone revenue | ₹72.46 cr, vs ₹51.85 cr in Q2 FY25 |
| Consolidated EBITDA | ₹77.69 cr, vs ₹36.47 cr in Q2 FY25 |
| Standalone EBITDA | ₹15.59 cr, vs ₹9.73 cr in Q2 FY25 |
| Consolidated profit before tax | ₹52.47 cr, vs ₹13.41 cr in Q2 FY25 |
| Consolidated profit after tax | ₹43.32 cr, vs ₹10.81 cr in Q2 FY25 |
| Standalone profit after tax | ₹4.93 cr, vs ₹1.11 cr in Q2 FY25 |
| Net debt | Zero; term loan outstanding ₹91.25 cr as of 4 Feb 2025 |
| B-80 oil production | 88,073 barrels, vs 58,000 barrels in Q2 FY25 |
| B-80 gas production | 0.6292 bcf, vs about 0.38 bcf in Q2 FY25 |
| B-80 average gas price realized | US $10.78 per mmbtu, vs US $9.89 per mmbtu in Q2 FY25 |
| B-80 oil stock (closing) | 3,17,000 barrels, valued at US $73.32 per barrel |
| Dirok gas sales volume | 0.44 bcf (HOEC share), vs 0.37 bcf in Q2 FY25 |
| Dirok condensate sold | 7,499 barrels, vs 5,858 barrels in Q2 FY25 |
| Dirok average gas price realized | US $8.25 per mmbtu, vs US $9.08 per mmbtu in Q2 FY25 |
| Dirok gas offtake rate | 1.76 crore scf per day, vs 1.5 crore scf per day in Q2 FY25 |
| Kharsang current production | About 360 barrels per day |
| Credit rating | 'A' with positive outlook from India Ratings, for ₹500 cr loan |
| Capital outlay, North-East region (next 2 FYs) | ₹250 cr |
| FY26 revenue aspiration | Approaching ₹1,000 cr (per management's wishful projection) |