Key Takeaways
- A quarter of blocked potential: Revenue halved YoY to Rs. 81 crores, not because the assets are dry but because Dirok gas offtake is constrained and B-80 needs a workover that is delayed by resource constraints, including cash stuck with HPCL.
- The Northeast gas grid is the unlock: Dirok can produce 4.5 crore scfd but sells far less; the DNPL-IGGL pipeline connection, expected by end-March 2026, is the single event that can triple production.
- B-80 is the problem child: The field is underperforming and the D1 workover, originally planned before mid-May, now looks likely to slip past the monsoon to October, keeping production in the current range for at least two more quarters.
- An 18-well onshore, 10-well offshore drilling plan is on the books across Kharsang, Dirok, Cambay, PY-1, B-80 and B-15, but timing is contingent on partner approvals, rig availability, and resolving the HPCL cash blockage.
- What to watch next quarter: Whether the DNPL-IGGL hook-up actually happens by end-March, whether the HPCL dispute is settled amicably or goes to arbitration, and whether a new CEO is named.
The Production Bottleneck: Dirok Can Flow, But Cannot Sell
- Dirok is evacuation-ready: Management states the field can hit its full 4.5 crore scfd capacity the moment offtake demand appears; the hook-up to the grid is "a day's job" once the downstream connection is complete.
- The missing link is a single pipeline connection: DNPL's line is mechanically complete but not yet connected to the IGGL trunk line that links Guwahati to Numaligarh; that connection is expected by end-March 2026, with offtake rising before Q4 FY26 ends or early Q1 FY27.
- Revenue impact is already visible: Dirok revenue fell this quarter on lower offtake and margin compression on selling prices; the field has been producing below capacity for multiple quarters.
- The grid connection triples Dirok's contribution: Management targets around 40,000 MMBTU daily production for FY27, roughly triple the current run-rate, and sees overall company production rising at least threefold once the Northeast grid is operational.
R. Jeevanandam: "Even if it is tomorrow, it's ready."
B-80: The Field That Is Not Pulling Its Weight
- Production is stuck in a low range: B-80 is not performing as expected; the D1 well needs a workover and the D2 well needs a zone transition from depleted gas zones to upper oil-and-gas zones, but both interventions are delayed.
- The workover timeline has slipped: Management initially aimed to complete the D1 workover before 15 May, but now says it is likely to happen only after the monsoon, meaning the next available window opens in October.
- The delay is partly financial: Resource constraints, including the need to recover money from HPCL, are cited as a reason the workover rig could not be sourced while onshore drilling in the Eastern region is in full swing.
- New wells are planned but distant: Three additional wells are planned at B-80, with drilling to start after the forthcoming monsoon, but until all three are drilled, production will stay on a similar trajectory.
The HPCL Overhang: Cash, Contamination, and an Unwanted Arbitration
- A crude-quality dispute is blocking cash: HPCL raised a contamination concern roughly three weeks after taking custody of crude; the Crude Oil Sales Agreement carries no warranty on quality, yet HOEC's outstanding dues remain unpaid.
- Management wants an amicable settlement: The company is pursuing avenues to realize dues but explicitly does not want litigation, calling HPCL "our big brother" and preferring to preserve the relationship for future dealings.
- The financial knock-on is material: If the HPCL issue is not resolved, the whole operational process gets delayed by 4 to 6 months; if the money remains substantially blocked, HOEC will need to look at alternative funding, with both debt and equity options open.
- Arbitration is the fallback: If the dispute goes legal, the COSA arbitration should be resolved within 3 to 4 months, but management currently has no intention of triggering that route.
R. Jeevanandam: "We have no intention of doing anything on this thing. We want an amicable settlement. They are after all our big brother. We have to deal with them in the subsequent period also. We don't want to be in a litigation mode in life."
The Drilling Inventory: A Large Plan Waiting on Approvals and Cash
- Onshore, 18 shallow and 3 deep wells are planned at Kharsang: 9 wells proposed immediately (6 plus 3 later) and 1 deeper well; the budget is proposed but awaits partner Oil India's 65% approval, and location finalization is in progress.
- Dirok and Greater Dirok add 6 more wells: The revised Field Development Plan is approved, environmental clearance for Greater Dirok is in hand, and the North Dirok well targeting the Barail formation awaits the formal extension letter from the government.
- Offshore, 10 wells are on the drawing board: 3 at PY-1, 3 at B-80, and 4 at B-15, but the offshore campaign is delayed due to the revenue impact on rig contracting; PY-1 can wait until October, and B-15 development awaits a mining lease expected shortly.
- The Northeast onshore program has a 2-year completion target: Management's endeavour is to commercialize discovered resources within that window, and it does not intend to borrow for onshore developments.
- Kharsang is already delivering incremental barrels: 8 wells drilled, 5 are oil producers, a sixth is a gas well after a well-control issue was resolved, and 2 more await perforation alongside the ninth well with hook-up expected by mid-March.
R. Jeevanandam: "We earnestly hope that with the support of Oil India Limited, we can unlock substantial value for all stakeholders in the block."
Leadership Transition and Strategic Gaps
- A new CEO is being sought: The Nomination and Remuneration Committee and Board are looking for a successor; an announcement is expected shortly, and the incoming CEO will replace R. Jeevanandam, who will not hold any executive position thereafter.
- Management is openly dissatisfied with recent performance: The last couple of quarters have been frustrating: the company can produce but cannot sell, capital commitments continue while B-80 underperforms, and some surface issues are not fully within its control.
- Gaps are being filled, but slowly: Management says gaps are getting filled now and performance will improve once grid connectivity comes into play, but the timeline for resolution has already stretched.
R. Jeevanandam: "So I'm not happy about it. That's for sure. So one is even because you are able to produce, you are not able to sell. Second thing, you are continuing with the capital commitments and the B-80 is not performing as expected."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| DNPL-IGGL pipeline connection | Mechanical completion done; connection with IGGL line pending; offtake increase to follow | End of March 2026 |
| Dirok production ramp-up | Triple current production to ~40,000 MMBTU/day | FY27 |
| Kharsang well hook-up | 2 completed wells perforated alongside ninth well | By 15 March 2026 |
| B-80 workover | D1 well workover; if missed this season, next window opens October | Before 15 May 2026, or post-monsoon (October) |
| B-15 field on production | Development plan submission, then ~2 years to first production | Within ~2 years of plan submission |
| HPCL dispute resolution (legal route) | COSA arbitration to be dealt within 4 months if triggered | Within 4 months of arbitration start |
| HPCL dispute impact on operations | If unresolved, delays whole process by 4-6 months | 4-6 months from now if not settled |
| New CEO appointment | NRC and Board search underway; announcement expected shortly | Much earlier than 3-6 months |
| Northeast drilling program completion | 18 shallow + 3 deep wells at Kharsang, 4 at Dirok, 2 at Greater Dirok | Within 2 years |
| Offshore drilling campaign | 10 wells across PY-1, B-80, B-15; commence once temporary operational issues resolved | After operational issues resolved |
| EBITDA margins | Expected around 60% | FY27-28 |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Standalone revenue | ₹77.32 cr, vs ₹321.51 cr in Q2 (which included ₹258.78 cr crude oil sale from B-80) |
| Consolidated revenue | ₹81.04 cr, vs ₹64.53 cr in Q2 (excluding crude oil sales); declined from ₹156 cr YoY |
| Standalone EBITDA | ₹23.89 cr, vs ₹28.81 cr in Q2 |
| Consolidated EBITDA | ₹30.99 cr, vs ₹25.15 cr in Q2 |
| Standalone PAT | ₹11.96 cr, vs ₹19.04 cr in Q2 |
| Consolidated PAT | ₹8.28 cr, vs ₹2.83 cr in Q2 |
| Standalone field operating expenses | ₹60.34 cr, vs ₹46.51 cr in Q2; increase due to higher B-80 production |
| Statutory levies | ₹12.44 cr, vs ₹10.6 cr in Q2 |
| Net debt | ₹55 cr; cash about ₹30 cr |
| Dirok gas sales volume | 1.3 crore scf/day, vs 1.4 crore scf/day in Q2; field capacity up to 4.5 crore scf/day |
| Dirok gas sold (HOEC share) | 0.31 bcf, vs 0.34 bcf in Q2 |
| Dirok condensate production | 5,614 barrels, vs 5,858 barrels in Q2 |
| Dirok gas price realized | $7.32/mmbtu, vs $7.8/mmbtu in Q2 |
| B-80 oil production | 45,742 barrels, vs 31,468 barrels in Q2 |
| B-80 gas production | 0.4 bcf, vs 0.23 bcf in Q2 |
| B-80 gas price realized | $10.5/mmbtu, vs $10.62/mmbtu in Q2 |
| B-80 gas sales revenue | ₹40.22 cr, vs ₹22.94 cr in Q2 |
| B-80 operational days | ~89 days out of 90 in the quarter |
| Cambay gas production | 0.32 mmscfd, vs 0.33 mmscfd in Q2 |
| Kharsang current production | ~800 barrels/day; targeting 1,000-plus barrels with existing wells |
| HPCL outstanding dues | ₹259 cr plus interest; 417,000 barrels of crude sold, payment blocked over contamination claim |
| India Ratings credit rating | IND-A reaffirmed for ₹500 cr bank facilities |
| HOEC reserves and resource potential | ~10 crore barrels of oil equivalent (HOEC share) |
| FY27-28 EBITDA margin expectation | ~60% (management guidance) |
| Dirok FY27 production expectation | ~3x current production; ~40,000 MMBTU/day |