Hindustan Zinc Ltd management interview: Hindustan Zinc Q2 Results: Hind Zinc के दूसरी तिमाही के नतीजे रहे अच्छे, Amarendu Prakash से चर्चा
ET Now Swadesh, 2026-10-21. Video: https://www.youtube.com/watch?v=maGQoRU3YTY
- Production growth: Q2 mined metal production rose 5% year on year and silver production rose 20%. Management credited debottlenecking, AI and employees’ efforts, and said it would keep advancing toward 1,100 kilotonnes of capacity in Q3 and Q4.
- Zinc costs: Cost of production fell 29% year on year to $703 per tonne in Q2. Higher sulphuric acid prices, increased production and cheaper renewable power helped offset higher hydrocarbon and coal prices.
- Silver outlook: Management said it remained confident of meeting FY27 guidance of 680 tonnes; new plants and improving operational reliability are expected to support output. It expects next year’s production to be higher than this year’s, but said it would provide the exact number in a few months.
- Capex and expansion: Management said sustenance expenditure guidance was ₹4,000 crore, roughly in line with this year, and growth capex guidance was ₹5,000 crore, with roughly 1/3 spent. It is planning to expand capacity from 1.1 million tonnes to 2 million tonnes; Phase 2 design is almost ready and will be brought to the board for approval.
- Critical minerals: Exploration has started in 2 of 4 mineral blocks, with work on the remaining 2 planned to begin in H2 FY27. Management expects to complete exploration by September-October 2028, then prepare a business plan and move toward mining.