Key Takeaways
- Record volumes, margin hit from one-offs: Sales volume grew 33% YoY to a record 85,500 tons, but EBITDA per ton fell 26% to INR 2,760, driven by a one-time credit loss provision and declining steel prices.
- Value-added product ramp is the next catalyst: Trial runs began on the color coating line, and the Sanand large-diameter pipe plant is nearing commissioning, setting up a shift toward higher-margin products from H2 FY24.
- Balance sheet strengthened despite price headwinds: Net working capital days improved sharply from 67 to 50, and net debt fell by INR 33 crores, even as HR coil prices corrected through the quarter.
- Steel price bottom is near, but not yet confirmed: Management expected a floor at INR 55,000/ton, but prices slipped a further INR 4,000–5,000; the primary-secondary gap has narrowed, and restocking is likely once the bottom is in.
- What to watch next quarter: Whether the color coating line hits its 80% utilization target by March, the pace of EBITDA per ton recovery toward the INR 3,500–4,000 range, and any movement on the deferred promoter equity infusion.
Volume & Operational Performance
- Record quarterly volumes: Sales volume reached 85,500 tons, a 33% increase, driven by better capacity utilization and improved sales utilization across the existing asset base.
- Capacity utilization improving: The company reached 60% utilization during the quarter, with peak utilization of 70% seen as achievable from current facilities. Phase II land at Sanand is available for brownfield expansion when needed.
- Volume growth ambition: Management is targeting 25% volume growth every year, supported by the ongoing ramp-up of new capacities and a narrowing price gap between primary and secondary steel.
Anish Bansal: "We are targeting a 25% growth every year."
Margin Walk & One-Time Impacts
- EBITDA per ton compressed: EBITDA per ton fell 26% to INR 2,760, with two main drivers: a one-time provision of INR 6.51 crores for expected credit loss on an OEM customer, and a declining trend in HR coil prices that pressured realizations.
- Credit loss provision explained: The full INR 6.51 crores claim relates to an OEM customer that entered NCLT during COVID. Hi-Tech is an operational creditor in the fourth category, meaning financial creditors and unsecured lenders recover first. Management described recovery chances as minimal but is still trying to recover whatever they can from this loss.
- Recovery path to INR 3,500–4,000 EBITDA/ton: Management expects a return to this range in two to three quarters, contingent on steel price stabilization and a growing contribution from value-added products like color-coated coils and large-diameter pipes.
Anish Bansal: "The recovery process, like I am, honestly, I'm doubtful because we are right now in the fourth category. So once the financial creditors get their things and then the unsecured lenders will get, and then they will come to operational creditors. So the chances are minimal, but we are still trying our best to recover whatever we can from this loss."
Steel Price Environment
- HR coil prices declined further than expected: Management had felt a bottom at INR 55,000 per ton, but prices corrected by an additional INR 4,000–5,000 per ton. The expectation now is for a bottom by December.
- Primary-secondary gap narrowing: The spread between primary and secondary steel prices compressed from INR 16,000 to INR 5,000–6,000 per ton, which improves the competitive position of organized players like Hi-Tech. The gap is expected to become negligible by Q4.
- Channel inventories are lean: Not much inventory is sitting in the pipeline currently. Restocking by dealers and distributors is expected once prices bottom out, likely by end of December.
Anish Bansal: "Hopefully, yes. I think by December, it should be bottomed out."
Value-Added Product Ramp
- Color coating line: trial runs commenced: Trial production started at the UP facility in November, making Hi-Tech the third player in North India with fully integrated manufacturing from HR coil to color-coated coils.
- Ramp-up plan: Utilization is expected to start at 50% in December, reaching 80% by end of March. Production volumes are planned at 2,000 tons in December, scaling to 3,500–4,000 tons per month.
- Downstream capacity unlock: As color coating stabilizes, the galvanizing line will run on a full-stream basis, and cold roll capacity utilization will increase by 4,000–5,000 tons, improving overall asset turns.
- Sanand greenfield project: The API and large-diameter pipe plant in Sanand, Gujarat, is in an advanced stage of commissioning. Trial production of water pipes and structural pipes is expected by end of Q4 FY23, with API certification expected six months from that point.
- Sanand contribution timeline: The plant will start contributing from the second half of FY24, with some earlier contribution from water and structural pipes.
- Export duty overhang on coated products: An export duty currently suppresses EBITDA on coated products. Management expects its removal in the next budget session, after which EBITDA per ton on coated products should return to the INR 6,000–7,000 range.
Anish Bansal: "Very large, and it is growing by the pace of 15%-20% per annum. This, the roofing segment."
Balance Sheet & Working Capital
- Working capital days reduced sharply: Net working capital days improved from 67 to 50 days, driven by better management of receivables and inventory despite steel price volatility. The target is to reach 40–45 days net by end of FY23.
- Net debt reduction: Net debt fell by INR 33 crores during the period, reflecting the working capital release and disciplined cash management.
- Debt-to-equity trajectory: Management expects the ratio to reach 1:1 soon, once the negative impact of steel price movements is fully absorbed.
- Working capital breakup not quantified: When asked for specific day targets for receivables, inventory, and payables individually, management cited price volatility as a reason for not providing component-level guidance.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY23 volume | 375,000 tons | FY23 (full year) |
| Steel price bottom | Prices to stabilize | By December |
| EBITDA per ton recovery | Return to INR 3,500–4,000 range | Two to three quarters |
| Working capital days | 40–45 days net | By end of FY23 |
| Color coating utilization | 80% | By end of March |
| Sanand trial production | Water and structural pipes | End of Q4 FY23 |
| Sanand API certification | Certification received | Six months after trial production |
| Sanand revenue contribution | Meaningful contribution begins | H2 FY24 |
| Export duty removal on coated products | EBITDA/ton returns to INR 6,000–7,000 | Next budget session (post-removal) |
| New CFO appointment | Hire completed | One to two months |
Key Metrics
| Metric | Q2 FY23 |
|---|---|
| Revenue | ₹599 cr, +30% YoY vs ₹462 cr in Q2 FY22 |
| Sales volume | 85,500 tons, +33% YoY, record highest |
| EBITDA per ton | ₹2,760, -26% YoY vs ₹3,742 in Q2 FY22 |
| Value addition | 5% to 6% of revenue |
| Net debt reduction | ₹33 cr reduced |
| Net working capital days | 50 days, improved from 67 days in FY22 |
| Capacity utilization | 60% |
| FY23 volume guidance | 375,000 tons, unchanged |
| Debt-to-equity ratio | 1.2x, expected to reach 1:1 soon |
| One-time credit loss provision | ₹6.51 cr claim filed in NCLT against an OEM customer, fully provisioned |
| Cold roll production (September) | 11,000 tons |
| Galvanizing line production | ~4,000 tons per month |
| Color coating capacity | 50,000 tons per annum |
| Color coating ramp-up target | 2,000 tons in Dec, ramping to 3,500–4,000 tons per month |
| API pipe capacity | ~15,000 tons per year |
| API project capex incurred | ₹25 cr incurred, ~₹4–5 cr additional needed |
| Total capacity post API addition | 630,000 tons (implied) |
| HR coil price level | ₹55,000/ton, further correction of ₹4–5 expected in coming months |
| Primary vs secondary steel price gap | ₹5,000–6,000/ton, narrowed from ₹16,000/ton; expected to close further by Q4 |
| Color-coated roofing segment growth | 15%–20% per annum |
| Color-coated product EBITDA/ton (historical) | ₹6,000–7,000/ton, currently ~₹4,000/ton post export duty |
| EBITDA/ton recovery target | ₹3,500–4,000/ton expected in 2–3 quarters |
| Working capital days target (FY23 exit) | 40–45 days net |
| Annual volume growth target | 25% every year |