Indian Metals & Ferro Alloys Ltd Q4 FY2022 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/109lf1yactxa40ns7n1fq593.pdf

Key Takeaways


Cost Structure & Margin Pressure

Prem Khandelwal: "No Shubham I think we'll see some more cost pressure in Q1 on account of coke and coal because the prices have gone up, particularly the coal price has gone up very high so which is going to be consumed in Q1 and Q2."

Realization & Pricing Outlook

Deepak Mohanty: "Q4 vs Q1 as you know because of the Russia-Ukraine was and other nickel prices went up and there was cyclone in Australia which affected the coking coal and all, so coke and all other prices went up. In order to take care of the cost push as well as the availability bottlenecks the benchmarks increased by 36 cents in Q1 of this year."

Production & Volume Dynamics


Growth CAPEX & Expansion

Prem Khandelwal: "In fact, this entire CAPEX of 1,500 crores whatever is there 1,500-1,600 crores to be spent over a period of 7 years. We are planning from internal accruals as of now."

Balance Sheet & Capital Allocation


Utkal C & Regulatory Overhang

Prem Khandelwal: "Those things you know in India how court functions so, even if yes even if we request them they are not going to listen. They will give date as per their convenience only."

Guidance & Commitments

CommitmentSpecificsTimeline
Q1 FY23 realizationAround Rs 1,20,000 per ton (average, spot and contract)Q1 FY23
Q2 FY23 realizationMore or less similar to Q1 (~Rs 1,20,000)Q2 FY23
Cost pressureMore cost pressure in Q1, possibly Q2, around Rs 8,000/ton levelQ1 and Q2 FY23
Ferrochrome production~250,000 tons (optimum capacity)FY23
Chrome ore production~6 lakh tonsFY23
Finance costRs 10–15 croresFY23
Kalinganagar construction startConstruction to beginBy March 2023
Kalinganagar commissioningProject completion and commissioningMarch 2025
Incremental furnace capacity1 lakh tons operationalEnd of FY25, full production FY26
Chrome ore mining capacity~8 lakh tonsFY25/26
Total CAPEX fundingRs 1,500–1,600 crores from internal accruals, no new debtOver 7 years
Utkal C compensationDetermination and payment within 80 days of agreement signingPost-agreement signing (date uncertain)

Key Metrics

MetricQ4 FY22
RevenueNot stated
Average realization₹1,06,000 per ton, Q1 FY23 expected around ₹1,20,000
Average cost of production₹82,700 per ton, QoQ cost increase of around ₹8,000 per ton (Q1 FY23 expected)
Operating marginNot stated
Net profitNot stated
Ferrochrome production61,462 tons, vs 67,000 tons in Q4 FY21
Ferrochrome sales volume70,395 tons
FY22 total ferrochrome sales2,48,000 tons
Ferrochrome grade produced61%, up from 59% in previous year
Chrome ore production (Q4)206,000 tons, higher than budgeted
Chrome ore production (FY22)559,000 tons, up almost 7% YoY
Blended cost of chrome ore at Choudwar₹6,500 per ton
Expected Q1 FY23 cost pressureAround ₹8,000 per ton increase vs Q4 FY22
Expected Q1 FY23 average realizationAround ₹1,20,000 per ton
Expected Q2 FY23 average realizationAround ₹1,20,000 per ton, similar to Q1
Benchmark ferrochrome price increase (Q1 FY23)36 cents
China May tender priceIncreased by 650 RMB, from 9,000 to 9,650
UG2 chrome ore price$295 to $300, up from around $175
Latest major coke booking price$480 to $490 per ton
Coke inventory coverageTill October
Current spot coke priceMore than $700 per ton
Tax rate going forwardAround 25% (new tax regime)
Tax provision (P&L, FY22)₹177 crores
FY23 expected finance costAround ₹10 to 15 crores
Depreciation increase (Q4)₹10 crores, due to change in mining asset life
Employee cost increase (Q4)Almost ₹20 crores, due to managerial remuneration provision
Total CAPEX plan (next 7 years)₹1,550 to 1,600 crores (₹1,000 cr mines + ₹550 cr furnace)
Kalinganagar furnace capacity addition1 lakh ton, commissioning targeted March 2025
Total ferrochrome production post-expansionAround 3.5 lakh tons
Chrome ore mining capacity targetAround 8 lakh tons by FY25 or FY26; 12 lakh tons by FY27
FY23 planned chrome ore miningAround 6 lakh tons
FY23 planned ferrochrome productionAround 2,50,000 tons (optimum capacity)
MCL coal linkage capacity4,58,000 metric tons per annum
Total thermal coal requirement~12 LMT per annum (5 LMT MCL coal + 7 LMT washery rejects)
Export share~90% of product to Far East Asia
Contracted sales quantityMore than 90% of total sales
Selling expenses per ton~₹6,000 to 7,000 per ton
Working capital requirement~₹400 crores
Mine lease expiry2049 and 2055
MCL coal linkage expiryMarch 2023