Indian Metals & Ferro Alloys Ltd Q4 FY2025 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/9lbxmdd58sp31l8xcmhlhtsu.pdf

Key Takeaways


Realization & Pricing Environment

Venkatesh: "The challenges continue to remain. There has been an improvement in prices, but challenges continue to remain. The challenges like all of us know in terms of tariffs and ongoing conflicts. But there are small signs of the market improving."

Cost Structure & Efficiency


Kalinganagar Expansion

Gupta: "It has increased because last year, initially, we had said it will be around INR700 crores from there. It has increased on the base level, to INR840 crores. As well as there is an escalation of the various costs, which has happened because this INR700 crores we had mentioned somewhere around 2.5 to 3 years back."

Production & Inventory


Strategic Projects & Energy Transition


Guidance & Commitments

CommitmentSpecificsTimeline
Kalinganagar first furnace commissioningFirst furnace onlineJune '26
Kalinganagar second furnace commissioningSecond furnace onlineSeptember '26
Kalinganagar FY27 production50,000–60,000 metric tonsFY27
Renewable energy supply startBoth JSW (70 MW) and Ampin (40 MW) PPAs supplying powerJune '26
FY26 chrome ore raising8.25 lakh tonsFY26
FY26 capex spendApproximately INR800 crores, managed through internal accruals; major spend in H2FY26
FY27 total production3.1–3.2 lakh tonsFY27
FY28 total production3.6 lakh tonsFY28
H1 FY26 productionAround 130,000 tonsH1 FY26
Met coke cost benefitFurther benefit expectedQ1 and Q2 FY26

Key Metrics

MetricQ4 FY25
RevenueNot stated
Net realization (ferrochrome)₹87,021 per ton, down from ₹96,943 in Q3 FY25 and ₹101,771 in Q4 FY24
EBITDA cost per metric ton₹76,980, down from ₹77,800 in Q3 FY25 and ₹82,836 in Q4 FY24
PAT (full year FY25)₹378 cr
Free cash flow (full year FY25)₹430 cr, before dividend payout
Net cash balance₹535 cr (₹906 cr cash less ₹372 cr working capital borrowings)
Capex guidance for FY26~₹800 cr, across three projects; ~₹100 cr spent in first 45 days, major spend in H2
Kalinganagar project capex₹840 cr (base level), plus ~₹60 cr for commissioning and trial run capitalization
Ferrochrome production guidance (H1 FY26)~130,000 tons for two quarters
Chrome ore raised (full year FY25)702,000 tons; plan for FY26: 825,000 tons
Chrome ore cost per ton (ex-mine)₹7,500, without royalty
Met coke cost per ton₹31,000; specific consumption: 560 kg per ton of ferrochrome
Power variable cost₹4.09 per unit, down ₹0.28 from Q4 FY24
Export share of sales90–95%; domestic: 5–10%
Long-term contract share of sales~80%