Indian Metals & Ferro Alloys Ltd Q1 FY2026 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/bbv34zqm2w2x9ey7wz698gua.pdf

Key Takeaways


Performance & Cost Structure

Gupta: "When the overall price actually drops in the market, we will see that our margins have been better off compared to our peers. So, that is the advantage we are having."

Ore Production & Mining Transition

Narade: "Right now, our raising cost is about Rs. 3,000 together of both the mines. And definitely it will increase when we go fully underground. As of now I cannot give the exact number of what the cost will be, but it will increase."

Competitive Position & Market Dynamics

Chigurupalli: "We are better compared to the China and many countries. Only a few countries which are faring better than us are like Kazakhstan, that is producing at a lower price than us."

Expansion Projects

Gupta: "But we can't comment much on something which will happen after 1.5 years in the current geopolitical situation."

Balance Sheet, Mix Shift & Other Updates

Venkatesh: "Overall, when we look at the ratio of 90-10, that is going to change drastically."

Guidance & Commitments

CommitmentSpecificsTimeline
Kalinganagar first furnaceFirst furnace operationalJune 2026
Kalinganagar second furnaceSecond furnace operationalSeptember 2026
Ethanol plant commissioning120 KLD plant in Therubali commissionedQ4 FY26
Ore production ramp-upRamp up ore production as per requirementQ3 FY26
Mahagiri underground mineReach 6 lakh tons productionNext 1-2 years
Mines expansion programmeFull expansion plan to continue4-5 years
EBITDA cost rangeRemain at current ~₹77,500 levelOngoing, subject to geopolitical volatility
Cost efficiency gains1-2% improvement potentialComing years

Key Metrics

MetricQ1 FY26
RevenueSequential improvement driven by ferrochrome price pick-up
EBITDA cost per ton₹77,500, marginally increased by ~₹500 QoQ; range-bound at 77,000–77,900 over last year
Ferrochrome production65,929 metric tons
Chrome ore production1,03,780 metric tons
Chrome ore raised~1,04,000 tons, down ~50% YoY from 2,02,000 tons in Q1 FY25 and down from 2,20,000 tons in Q4 FY25
Chrome ore cost per ton₹8,400, up from ₹7,500 in Q4 FY25; normal range ₹8,000–9,000
Power cost per unit₹5.27 total, variable cost ₹4.03; Q1 FY25 was ₹4.97
Coal cost per unit₹2.68
Coke cost per ton (within EBITDA cost)~₹14,500
Ore raising cost per ton~₹3,000 (both mines combined)
Niche/value-added product share~5%–6% of total capacity, ~15,000 tons produced
Premium on niche products₹4,000 to ₹20,000 per ton
Renewable power share~25% renewable, ~75% thermal; REC obligation for FY26 is 33.01%
Other income₹21 crores, excluding ₹7 crores from Utkal C; total surplus ~₹915 crores
Domestic stainless-steel growth~6% CAGR