Key Takeaways
- Volume engine is firing, margins are normalizing: Q2 output hit a record, and the company expects to cross 100,000 tons in a single quarter (Q3) for the first time. However, EBITDA margins moderated from an exceptional Q1 as prices eased and startup costs persisted.
- Kalinganagar is the margin story: The new site will improve EBITDA by ₹1,500–₹2,000 per ton due to superior logistics, but the full benefit is delayed until startup and scaling inefficiencies are resolved by December 2026.
- A clear path to half a million tons: FY28 volume guidance is set at ~475,000 tons, backed by a seventh furnace, increased ore raising, and confidence in selling the output into both export and a rapidly growing domestic market.
- Cost pressures are real but framed as temporary: Met coke prices are rising, ore mix shifted to higher-cost underground, and one-off startup costs hit Q2. Management expects a "much cleaner slate" from the new year.
- What to watch next quarter: Whether Q3 output actually crosses the 100,000-ton milestone, the trajectory of met coke costs, and the first contribution from renewable energy, expected from late November.
Volume Ramp-Up: The Kalinganagar Build-Out
- KNR-2 nearing full capacity: The acquired site reached its rated capacity of ~84,000 tons per annum in October and is on track for the full 100,000 tons per annum by December, once transformer replacements in two furnaces are complete.
- KNR-1 is coming online: The first furnace achieved hot metal tapping on August 25th, and the second furnace is expected to follow around November 15th, setting the stage for a full quarter at optimal load in Q4.
- A seventh furnace is on the horizon: A partially built furnace at KNR-2 is expected to be operational around July 2027, pending final permissions, adding further volume to the FY28 target.
- Ore raising must keep pace: The company is "fairly confident" of exceeding the 0.12 crore tons mark in ore raising, a prerequisite for adding more smelting capacity, with a board-approved expansion at the Mahagiri mine adding 50,000-ton increments starting in 2029.
Panda: "Until let's say December of 2026, all these up and down will happen, but we expect to start the new year on a much cleaner slate in terms of these inefficiencies relating to startup being, starting up and scaling up a new location being ironed out."
Margin Mechanics: A Quarter of Normalization
- From peak to plateau: Q1 FY27 saw an exceptional ~30% EBITDA margin, which moderated in Q2 as prices eased and costs moved up, though per-ton EBITDA of ~₹28,000 remains significantly above the long-term average.
- Costs climbed on multiple fronts: Met coke prices moved up, more ore was consumed from higher-cost underground mining, royalty outgoes increased with elevated chrome ore prices, and one-off startup costs from the greenfield site and acquisition hit the P&L.
- Power costs carried a triple burden: Coal prices rose due to an extended monsoon disrupting dispatches, consumption increased in quantum, and startup inefficiencies meant the company paid high grid rates without yet crossing the 60% consumption threshold that triggers lower tariffs.
- A renewable energy tailwind is imminent: The first 70-megawatt tranche from JSW Energy is expected by late November 2026, which should provide a cost advantage from Q3 onwards, though the company is currently paying for the hybrid energy corridor without utilizing it.
- Kalinganagar's structural advantage: Once stabilized, the new site will deliver an EBITDA uplift of ₹1,500–₹2,000 per ton over the existing operations, driven by more efficient logistics compared to Therubali, which is ₹6,000–₹6,500 per ton more expensive than the Choudwar plant.
The Demand Picture: Placing Half a Million Tons
- Export/domestic mix is shifting: By 2028, the company targets a 60:40 export-to-domestic split, with about 300,000 tons exported and 200,000 tons sold domestically, though both components can be adjusted based on market conditions.
- China remains the anchor: Exports to China are expected to grow from ~120,000 tons to 180,000–200,000 tons per annum, with no demand concerns as older, smaller furnaces are replaced by newer, more efficient stainless-steel capacity.
- A long-term contract locks in low-phos output: The company recently concluded a contract to place about 70% of its low-phosphorus ferrochrome output with a Japanese customer for 2027, providing revenue visibility for a premium product.
- Domestic market is a strategic priority: The company has expanded its domestic customer base to include practically all medium and large stainless-steel producers, and management feels a responsibility as the largest producer to properly cater to the home market.
- The India thesis is a long-term bet: Per capita stainless steel consumption in India is just 3.5 kg, versus China's peak of over 8 kg, and management expects adoption to accelerate as the economy matures and buyers shift from initial acquisition cost to life cycle costing.
Panda: "As the largest producer we feel that it is our responsibility as well to make sure that the domestic market is properly catered to."
Industry Dynamics: A Fragile Equilibrium
- South Africa's collapse reshaped supply: Ferrochrome production in South Africa collapsed in 2025 due to high power and inland logistics costs, but a preferential tariff for two producers is now enabling them to scale up output, which could rebalance the market.
- The chrome-unit parity thesis: Management believes South African producers will maintain parity in chrome units, meaning any increase in ferrochrome production will be offset by reduced chrome ore exports, which would constrain China's ability to produce ferrochrome.
- Turbulence is possible during the handoff: There could be market turbulence while South Africa scales up and before a corresponding reduction happens in China or elsewhere, but it is "not in the interest of South African producers to flood the market with excess tonnage."
- IMFA's cost position provides a buffer: Management claims the company is in the "lower decile" of global cost curves, while China is a relatively high-cost producer due to full dependence on imported ore, offering a margin of safety if prices soften.
Panda: "It is not in the interest of South African producers to flood the market with excess tonnage, which will bring down prices, which will affect us for sure, but it will affect every single ferrochrome producer, including the South Africans themselves."
Capital Allocation: Growth with Discipline
- Board-approved capex of ~₹375 crores covers two initiatives: increasing chrome ore raising from the Mahagiri underground mines from 6 lakh tons to 7.5 lakh tons, and establishing low-carbon ferrochrome production.
- Low-carbon ferrochrome is a margin play: The company hopes to be in production by early 2028, sacrificing some high-carbon output as feed material to produce 20,000 tons of a product that commands a significantly higher price and margin.
- An ethanol project adds diversification: A 120 KLD ethanol project is expected to be commissioned in January 2027, following geopolitical and monsoon-related delays, with projected revenue of ₹320 crores and an EBITDA margin of around 10%.
- Critical minerals remain an ambition: The company participated in a couple of auctions but was not successful and remains "alive to the opportunity," hoping to break through "sooner rather than later."
- Capital discipline is explicit: Management will only allocate capital when confident in its ability to add value and create value for stakeholders, and would only proceed on any opportunity that meets certain criteria.
Panda: "We will only allocate capital when we see, when we are confident about our ability to add value and create value for stakeholders."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| KNR-2 full rated capacity | 100,000 tons per annum from existing four furnaces | December 2026 |
| Quarterly output milestone | Cross 100,000 tons of output in a single quarter | Q3 FY27 |
| FY27 production volume | 380,000 tons (slight reduction from earlier on lower KNR-1 output and KNR-2 delay) | FY27 |
| FY28 production volume | Around 475,000 tons | FY28 |
| Seventh furnace commissioning | Partially built furnace at KNR-2 operational | Around July 2027 |
| Renewable energy flow | First 70 MW tranche from JSW Energy | Late November 2026 |
| Startup inefficiencies resolved | Cleaner slate with scaling inefficiencies ironed out | By end of December 2026 |
| Low-carbon ferrochrome production | 20,000 tons per annum | Early 2028 |
| Ethanol project commissioning | 120 KLD capacity, ₹320 crores revenue, ~10% EBITDA margin | January 2027 |
| Export/domestic sales mix | 60:40 in favor of exports (flexible based on market) | By 2028 |
| Mahagiri mine expansion | Incremental 50,000 tons per annum ore raising capacity in stages | Starting 2029 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue | Not stated |
| EBITDA per ton | ₹28,000, significantly above long-term average |
| EBITDA margin | Close to 30% in Q1 FY27, moderated in Q2; Q2 figure not stated |
| Ferrochrome production volume | 380,000 tons guided for FY27, slight reduction from earlier on account of lower KNR-1 output and slight KNR-2 delay |
| Ferrochrome production volume FY28 | ~475,000 tons guided |
| Ferrochrome sales volume H1 FY27 | 161,255 tons |
| Q3 FY27 quarterly output | Expected to cross 100,000 tons for the first time |
| Q2 realization | ~₹1.165 lakh per ton |
| Met coke pricing | 375–380 levels, with slight upward momentum |
| Ore raising target FY27 | 0.1 crore tons |
| Ore raising short-term target | 0.12 crore tons overall, 0.06 crore tons from Sukinda and 0.06 crore tons per annum from Mahagiri |
| Mahagiri ore raising expansion | From 0.06 crore tons to 0.08 crore tons per annum, increments of 50,000 tons starting 2029 |
| Board-approved capex | ₹375 crores for Mahagiri ore raising expansion and low-carbon ferro chrome production |
| KNR-2 rated capacity | ~84,000 tons per annum achieved in October, full 100,000 tons per annum by December 2026 |
| KNR-1 second furnace hot metal tapping | Expected around 15th November 2026 |
| Seventh furnace commissioning | Expected around July 2027 |
| Low carbon ferrochrome target | 20,000 tons, expected by early 2028 |
| Low-phos material production | 10,000 to 12,000 tons per annum, 0.015 phosphorus max, 15% to 20% premium |
| Exports to China | Currently ~120,000 tons per annum, expected to reach 180,000 to 200,000 tons |
| Export vs domestic mix target by 2028 | 60:40 in favor of exports, ~300,000 tons exports and ~200,000 tons domestic out of half a million tons |
| Renewable energy from JSW Energy | First branch of 70 megawatts expected by end of this month |
| Notional MTM forex loss | ₹8 crores in P&L, embedded in other expenses, due to USD moving from 94.6 to 95.98 |
| Cost per ton | ₹88,368 in Q2 FY27 vs ₹85,884 in Q1 FY27, per investor presentation |
| Ethanol project expected revenue | ₹320 crores annually |
| Ethanol project expected EBITDA margin | ~10% |
| Ethanol project internal IRR | 15%, ROCE in range of 13% to 15% |
| India stainless steel per capita consumption | ~3.5 kg, China at peak in excess of 8 kg |
| Global ferrochrome industry size | ~1.7–1.8 crore tons |