IndiGrid Infrastructure Trust Q4 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/xbs440h2sphzqwqqk1xgt1ic.pdf

Key Takeaways


Distribution & DPU Guidance

Shah: "I think our view is that it's a long-term business. And there are upsides, there are downsides, there are things that can go wrong. And therefore, a quarter, 1.5 quarters of distribution is a sufficient requirement for ensuring that our DPU is not impacted on account of short-term volatility of any kind, right, be it war, be it COVID, be it capital market freeze, refinancing, variety of risks can pan out, right, in a large portfolio."

Portfolio Operations & Availability


EnerGrid & the Development Pipeline

Shah: "So by doing it outside IndiGrid, the limit that under construction projects, let's say it's under IndiGrid is removed. And therefore, it allows us to do much larger size of development projects, not just per size, but total projects, which means that IndiGrid have a better growth profile going forward, which we could not have done it within IndiGrid."

Project Wins & Commissioning

Shah: "The IndiGrid teams delivered this project in record time, superior quality and first-time right approach."

Balance Sheet & Financing


Accounting & Tax Notes


Guidance & Commitments

CommitmentSpecificsTimeline
DPU₹16 per unit, maintainable without additional acquisitionsFY26, with minimum 5-year life
Availability restorationGPTL and JKPTL disruptions resolved, back to original levels"In a quarter or so"
Portfolio availability targetSustain at least 99.5%Ongoing
Ratle Kiru constructionProject constructed and commissioned24 months
Under-construction capRemain below 10% of AUM from projects already wonMarch 2026
All current projects commissionedEvery project currently owned will be commissionedBy June 2027
EnerGrid biddingEnerGrid begins bidding for new projectsStarting this quarter
FY26 refinancing~₹2,570 crore refinanced, including ~₹978 crore ECB at one SPVNext quarter (for the ECB portion)

Key Metrics

MetricQ4 FY25
Revenue (reported)₹874 cr, +11% YoY
Revenue (operational, adjusted)₹799 cr, +1.6% YoY
EBITDA (reported)₹729 cr, +11% YoY
EBITDA (operational, adjusted)₹721 cr, +9.9% YoY
EBITDA margin (adjusted)~90%, in line with historical range
NDCF₹434 cr
DPU₹4.1 per unit, +15.5% YoY and 9.3% above guidance of ₹3.75
DPU guidance (FY26)₹16 per unit, increased from ₹15, +6.7% over prior guidance
AUM₹29,600 cr
Net debt to AUM59.1%
Average cost of debt7.67% on gross borrowing of ~₹19,900 cr
Interest coverage ratio2.01x
Quarterly transmission availability98.4%
Solar plant availability98.2%
Solar generation43.96 cr units, CUF of 23.8%
Collections (transmission)115% for the quarter
Collections (solar)89% for the quarter
DSO (transmission)38 days as of March 31
DSO (solar)48 days as of March 31
NAV per unit₹144.11 as of March 31
Cumulative distribution per unit since listing₹101.32, totaling ₹6,208 cr
Total return since listing (2017)~143%, CAGR of 12%
Gross borrowing fixed-rate portion90% of ~₹19,900 cr
Ratle Kiru project annual transmission charge~₹195 cr post commissioning
Under-construction CAPEX (currently won projects)~₹4,000 cr across 6 projects