Key Takeaways
- Seasonal Q1, stable margins: Revenue of ₹460 crores was down sequentially on normal monsoon and site-clearance seasonality, while EBITDA margin held at 8.6% and EBITDA grew 24.6% on better pricing.
- PAT flat on treasury, not operations: PAT stayed at ₹28 crores because IPO cash has been spent on capex, so interest income is gone; management frames this as a healthy trade-off now that capacity is built.
- Capacity build-out accelerated: A ₹250 crore QIP, a new heavy structure plant in Andhra, a second Gujarat PEB plant, and a Canadian open web joist export JV all point to one goal: top 2 in India, "come what may."
- Heavy structures are the next leg: First order already secured for the new plant, ~₹100–150 crores of heavy structure revenue is in FY27 projections, and management is deliberately ramping slowly to avoid execution missteps.
- What to watch next quarter: Whether the heavy structure plant commissions on schedule, whether QIP approvals convert into a timely raise, and whether the promised ₹550–600 crore quarterly revenue trajectory actually materializes.
Q1 Performance & Working Capital
- Seasonality, not weakness: Q1 revenue of ₹460 crores was lower than Q3, Q4, and even Q2 of FY26 because rains and flooded sites prevented dispatch of customized materials; management says this is the normal pattern every year, with Q1 lowest and Q3–Q4 picking up.
- Margin stability: EBITDA margin held at 8.6% while EBITDA grew 24.6% against revenue growth of 20.7%, which management attributed to better pricing rather than cost cuts.
- PAT flat on treasury mechanics: PAT stayed at ₹28 crores because IPO funds of ₹180 crores have been spent on capex (₹230–240 crores already spent), so treasury interest income is gone; depreciation is also rising. Management frames this as a good thing since capacity is now built and should yield operational profit going forward.
- Working capital normalized: Last quarter's negative working capital effects have reversed. The three prior drags were large projects billed but not collected, extra steel stocking due to rising prices, and advance payments to suppliers to secure steel; the company is "back to positive now."
- Cash flow turned positive: Q1 operating cash flow was ₹26.83 crores, almost equal to profit before tax. Last year's negative operating cash flow was specifically because very large orders were executed on a work-contract basis and are now getting completed with billing and payment collection underway.
- Finance cost optics: Finance costs appeared to jump 20–30% faster than revenue, but the upward trajectory is a function of interest income no longer being there, plus one-time bank processing fees paid this quarter for fresh enhancements of non-fund-based limits to meet growing business needs.
- Buildings segment breakout: Buildings (institutions, flight kitchens, commercial buildings, office buildings, multistory buildings, process buildings) grew to 10% of Q1 revenue from 2% or 0% earlier, driven by conversion from RCC-framed to steel-framed buildings; Q1 included a data center built in Noida for RailTel Corporation.
Nanda: "Revenue growth without profitability growth doesn't make much sense to us."
Capacity Expansion & Capex
- QIP raised to ₹250 crores: The Board cancelled the earlier ₹100 crore QIP and approved a ₹250 crore raise instead, citing changes in the Indian industrial landscape. Approvals are being sought now; timing is not decided but could be within the next quarter or next 4 months, with the idea to get approvals and keep them ready to move at market speed.
- Heavy structure plant, Andhra Pradesh: Phase 2 and Phase 3 will cost ~₹150 crores; all 3 phases are now being completed in 1.5 years instead of the earlier slower pace. The plant is expected to start by next month.
- Gujarat Plant 2: Land is already purchased for a second Gujarat plant for PEB requirements; capex of ₹50–60 crores is planned.
- Canadian JV / MOU: An MOU is signed with a Canadian company (ER Steel, per an analyst) to set up a 100% export unit for open web joist steel structures. Interarch handles manufacturing; the partner handles sales, engineering, installation, and collections in North America.
- Kheda Phase 1 inaugurated: Capacity moved from 200,000 tonnes to 221,000 tonnes.
- Two-year capex total: Approximately ₹129 crores this year and ₹133 crores next year, totaling about ₹250 crores over two years.
- QIP rationale: Management is raising funds for the next 2 years together to have speed in control rather than going back to market repeatedly; funds are needed for capex and working capital. All QIP money will go into capex because the company is zero-debt.
- Capacity utilization discipline: Existing plants are meeting 80–90% utilization; a new PEB plant is only set up once existing plants are sure to be at 80–90%. Last year utilization was 80% of installed capacity but ~88% of utilizable capacity because utilizable capacity is only 85–90% of installed in this business.
- Large project strain: Large projects (EV, semiconductor, renewable, lithium battery, data centers) are straining industry capacity; most large orders are divided between 2–3 companies because no single company can execute them alone.
Nanda: "We have made up our mind that we have to be in the top 2 companies in India, come what may. And actually, we cannot be in the top 2 companies if we don't have the capacity. There's no question. So that is our decision."
Heavy Structures & Hybrid Opportunity
- First order secured: The new heavy structure plant already has its first order, a data center to be manufactured in the new plant, to be used for trial production and commercial production.
- FY27 heavy structure revenue: Projections include about ₹100–150 crores of heavy structures.
- Next year projection: Management is adding about ₹200 crores of heavy structure business to projections for next year, increasing the projection to ₹2,700 crores; they will revise after another quarter or two and prefer to be cautious.
- Deliberate slow ramp: Management is taking the heavy structure ramp slowly to avoid missteps. For next year, they are adding about ₹200 crores of heavy structure business to projections, increasing the projection to ₹2,700 crores; they will revise after another quarter or two.
- Bidding before plant readiness: The company is already bidding for projects involving heavy structures before the plant is fully operational; the general strategy is to enter the market before plant setup.
- Hybrid positioning: Management sees more hybrid structures going forward; few heavy structure companies can do hybrid and few PEB companies can do hybrid, so Interarch will be in a good position to bid hybrid and make it commercially and technically viable for customers.
- Team built over 3 years: An in-house team specialized in heavy structures was built over the last 3 years, including outside consultants for engineering skill; business development and marketing were done, and the company found very good response.
- Heavy structure execution history: Some orders taken were part of PEB with heavy structure components (Tata Electronics plant, semiconductor plant, lithium battery plant), where 80–85% was standard PEB and 15% was heavy structure manufactured from outside.
- Utilization visibility: Management expects a better idea of heavy structure utilization by March this year; they want to be more definite after a few months and are being conservative for 5–6 months to learn the ropes practically.
Nanda: "Business is there. There's plenty of business in the market that is available... but we are taking it slowly because we want to not make -- have a misstep going forward."
Exports & Open Web Joist JV
- JV economics: The open web joist plant will have capacity of ~15,000 tonnes; Phase 1 of 4,000–5,000 tonnes with sales of ~$7.5 million (~₹70–75 crores) at ~20% EBITDA margin. Production is expected by 1st July or end July next year; 2–3 years to build to full capacity; full capacity sales of ~$20–23 million. The company is ready to expand further if demand picks up.
- Capex for JV: ₹50–60 crores capex for the 100% export unit under the Canadian MOU.
- Exports as strategic vertical: Management sees exports as an important vertical going forward; exports are more profitable due to higher prices, zero sales/marketing expense, and zero project management expense.
- Export mix target: Short to medium term (1–2 years), about 10% of total turnover through exports.
Nanda: "Exports will be more profitable. Prices there are higher. We will make more profit. The expense on sales marketing is 0. Expense on project management is 0. So therefore, we feel that exports are very important, and this is a part of that overall strategy."
Order Book & Demand Environment
- Order book discipline: The company remains disciplined in order selection, focusing on projects aligned with execution capability, strategic priorities, and profitability objectives.
- New age industry positioning: Management has positioned the company to cater to new age industries (renewables, EVs, lithium battery, data centers, semiconductors, chips, phone assembly); margin accretion depends on competition, but larger projects mean fewer bidders and better productivity.
- Order book mix: 35% of the order book comes from newer segments (renewables, EVs, lithium battery, data centers, semiconductors), though management did not have the Q1 revenue split for these segments and said they would send it later.
- Execution timelines lengthening: Recent orders have 15–16 month execution periods vs normal 8–12 months because they are energy-sector orders (HVDC valve halls, heavy transformer manufacturing) where engineering approvals and site clearances take ~6 months vs normal 2–3 months; these orders are typically on variable price concept.
- External challenges: The Iran war caused prices to go up, shortages, steel shortage, steel prices going up and remaining higher; site manpower with certified builders has been a challenge, while factory manpower is more under control.
- Cost pressures: Fluctuations in freight, labor prices going up, and erection prices going up are ongoing challenges.
- Competitive environment: Management is not worried; the pie is increasing dramatically, steel usage is going up dramatically, and every year will be a dramatic change.
Nanda: "It's a business which can kill you very fast if you're not careful. Nobody has ever in this business closed down because of lack of orders. They have closed down because they couldn't deliver properly."
Margins & Profitability
- Margin trajectory: Management is working to increase margins through more complex jobs/clients, better purchasing, less wastage, better recoveries, cost reductions, exports, and heavy structures; margins are expected to "gradually go up" with addition of exports and heavy structures.
- Not immediate: Management is not sure of immediate results this year due to advance expenses on new plants (Gujarat, heavy structure); they are hopeful of substantial margin increase in FY27–28.
- Profitability focus: Management is concentrating on improving profitability, sometimes sacrificing revenue growth to increase profitability; they are trying to get better payment terms and better pricing from customers.
- Profitability ambition: Management does not think the company is making very good profits and believes it should do much, much better, but acknowledges not everything is in their hands.
Nanda: "I think margins will gradually go up with addition of exports, with the addition of heavy structures. We are also trying to leverage our present expenses to increase our turnover in these lines. So I think it will show results, but I'm not very sure that it will show immediate results this year because we have to also, whenever we open new plants and new areas like we have done, Gujarat and heavy structure, a lot of expense goes into that in advance of actually the sale happening."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue target | ₹2,150 crores; requires ~₹1,700 crores in the next 9 months | FY27 |
| Quarterly revenue trajectory | Could move up to ~₹550 crores, then ₹600 crores, then ₹620 crores in subsequent quarters | Next 3 quarters |
| FY27 volume | Approximately 190,000 tonnes, around 18% volume growth | FY27 |
| Heavy structure revenue in FY27 | About ₹100–150 crores included in projections | FY27 |
| Next year projection | Adding about ₹200 crores of heavy structure business, increasing projection to ₹2,700 crores; will revise after another quarter or two | FY28 |
| Open web joist JV production | Plant to come up around end of quarter 2 next year; Phase 1 of 4,000–5,000 tonnes with sales of ~$7.5 million at ~20% EBITDA margin | End Q2 next year |
| Heavy structure plant commissioning | Expected to start by next month | Next month |
| Export mix target | About 10% of total turnover through exports | 1–2 years |
| Two-year capex | Approximately ₹129 crores this year and ₹133 crores next year, totaling about ₹250 crores | FY27–FY28 |
| QIP raise | ₹250 crores approved; approvals being sought; timing not decided, could be within next quarter or next 4 months | Next 1–4 months |
| Heavy structure utilization visibility | Better idea by March this year; being conservative for 5–6 months to learn the ropes practically | March |
| Cash flow outlook | Management expects much more positive cash flows during remainder of the year | FY27 remainder |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Revenue | ₹460 crores, +20.7% YoY vs ₹381 crores in Q1 FY26 |
| EBITDA | ₹39 crores, +24.6% YoY vs ₹32 crores in Q1 FY26 |
| EBITDA margin | 8.6%, stable YoY |
| Profit after tax | ₹28 crores, flat YoY, impacted by lower other income |
| Order book | ₹1,864 crores as of 31st July 2026, significantly better than 3 months ago |
| Major order in order book | ₹165 crores from a major energy company in Vadodara |
| Sales volume | 38,499 tonnes in Q1, ~80% of quarterly capacity of 50,000 tonnes |
| Capacity utilization | 80% of installed capacity in FY26; ~88% of utilizable capacity |
| Installed capacity | 221,000 tonnes after Kheda plant Phase 1 inauguration |
| Operating cash flow | ₹26.83 crores positive from operating activities in Q1 |
| Export contribution | ₹10–12 crores out of ~₹460 crores Q1 revenue |
| New age industries share of order book | ~35% of remaining order book, including multistory buildings, data centers, hotels |
| Buildings segment share of Q1 revenue | 10%, up from 2% or 0% earlier |
| FY27 revenue target | ₹2,150 crores, with ~₹1,700 crores required over next 9 months |
| FY27 volume guidance | ~190,000 tonnes, ~18% volume growth |
| Heavy structure contribution to FY27 revenue | ₹100–150 crores included in FY27 guidance |
| QIP size approved | ₹250 crores, up from earlier ₹100 crores approval |
| Capex planned this year | ₹129 crores in FY27 |
| Capex planned next year | ₹133 crores in FY28 |
| Open web joist JV capacity | 15,000 tonnes full capacity; Phase 1 of 4,000–5,000 tonnes |
| Open web joist JV full-capacity sales estimate | $20–23 million at ~$1.50 average price |
| Open web joist JV Phase 1 sales estimate | $7.5 million, ~₹70–75 crores, with ~20% EBITDA margin targeted |
| Export mix target | ~10% of total turnover in short to medium term, 1–2 years |
| Heavy structure projection for next year | ~₹200 crores added to projections, increasing projection to ₹2,700 crores |
| Heavy structure plant capability | Up to 20 tonnes per column or beam, vs 4–5 tonnes previously |