Key Takeaways
- Engineering drove the quarter, chemicals felt the pinch: Engineering EBIT surged ~31% YoY on higher scale and mix, while chemical EBIT fell 11% YoY as raw material cost spikes outpaced price hikes.
- Order book provides multi-year visibility: A ₹1,267 cr backlog plus a ₹6,700 cr bid pipeline supports strong engineering revenue growth for the next 2–3 years.
- Consumer products nearing breakeven: Full-year revenue grew 26% and the Q4 loss narrowed to ₹3.6 cr; management expects a clear turnaround and positive EBITDA in FY23.
- Greenfield CAPEX delayed, not derailed: The large ~₹300 cr expansion awaits environmental clearance and will now spill into H1 FY24, pushing major spend out.
- What to watch next quarter: Whether chemical margins recover as input cost pressures ease, the pace of new international order conversions, and any progress on the subsidiary consolidation exercise.
Engineering: The Quarter's Engine
- Q4 revenue and profit surge: Engineering revenue rose ~10% YoY to ₹320.8 cr, while EBIT jumped ~31% to ₹73.2 cr. The margin spike came from higher scale delivering better fixed-cost leverage, a favorable mix shift toward higher-margin work, and progressive pass-through of escalated input costs. This is a multi-year seasonal pattern.
- Full-year resilience: Despite a slight 0.6% revenue dip for the full year, engineering EBIT still grew ~7%. The full-year EBIT margin of ~11–11.5% is considered repeatable on a continuous basis, though quarterly variations will occur.
- UP Jal Nigam project accelerated: Execution pace picked up materially in Q4, with revenue recognized based on work completion. The firmed-up portion is to be executed by FY24, with the remaining portion (still under processing) targeted for completion by H1 FY25.
- Sri Lanka: progress with caution: Progressive handover of completed stages to the Sri Lanka Water Board began in Q4, but economic turmoil slowed execution via fuel, manpower, and subcontractor shortages. The company received a further time extension through Q2 FY23 and expects to complete by then if ground conditions hold.
Management: "We do not expect to have any credit risk because we're not getting paid directly by the Sri Lankan government. And plus, these payments are insured and guaranteed."
Chemicals: Volume Steady, Margins Squeezed
- Revenue up, profit down: Chemical division revenue grew 17% YoY in Q4, but EBIT fell 11% YoY. Domestic sales held steady while export volumes improved with COVID-curb relaxation, though logistics issues hampered dispatches.
- Raw material costs the culprit: Incessant one-way input price increases, especially after the first half, made it difficult to normalize margins. Periodic price hikes were insufficient because of the volatility and rapidity of cost increases.
- Volume picture flat: Q4 capacity utilization was ~75%, similar to Q3, implying volumes were more or less flat sequentially with variations across product lines. Management declined to provide specific volume growth figures for the full year, citing wide variance in product types and units of measurement.
- Pass-through mechanics: Wherever possible, price rises have been passed to customers, and a good portion have been accommodative even when contracts lacked price variation clauses. Still, the overall margin profile shows a slight reduction compared to earlier achievements.
- FY23 margin hope tied to raw materials: Management is hopeful of margin improvement if raw material prices soften; conservatively, full-year margin should be similar to FY22.
Management: "Generally, we are able to pass on the price increases to the customers over a period of time. However, in the overall margin profile there is a slight reduction compared to what we had achieved earlier and we are hoping that the next quarter or so that would come back more in line with what we have achieved earlier."
Order Book & Growth Visibility
- Backlog and pipeline: The engineering order book stands at ₹1,267 cr (excluding Sri Lanka and UP Jal Nigam), with a bid pipeline of ₹6,700 cr. This gives strong revenue visibility for the next 2–3 years from the engineering segment.
- New project wins: Initial work has started on the IOCL and Morocco desalination projects; first revenue typically books two to three months after work begins.
- International order prospects: Management indicated some contracts are close to finalization and hopes to declare them in the very near future. The company is working on some very large opportunities alongside smaller and medium ones, though it remains conservative and careful when evaluating and converting them.
- UP Jal Nigam and beyond: The current contract is the only one converted so far in this segment. Many more opportunities exist, but the company has been cautious about the quantum of work it picks up, carefully analyzing risk profiles before bidding.
- Oil & gas tailwind: Higher crude prices sustaining CAPEX plans are creating opportunities for water and wastewater treatment equipment and chemicals, both in India and internationally, especially in the Middle East.
Management: "We are standing at a very interesting juncture with some of the threats post the pandemic seeming to be behind us. There seems to be an uptick in growth expectations across the board."
Consumer Products: Turnaround in Sight
- Growth trajectory: Consumer segment revenue rose 13% YoY in Q4 and 26% for the full year. The Q4 loss narrowed slightly to ₹3.6 cr from ₹3.7 cr a year ago.
- Drivers of improvement: New product launches and increased market coverage drove sequential improvement in turnover. Quarter-to-quarter growth momentum has picked up, with increased business levels continuing even after Q4.
- FY23 expectation: Management expects to almost certainly see a turnaround in FY23, with positive EBITDA.
CAPEX & Capacity Expansion
- Greenfield CAPEX delayed: The large greenfield project (~₹250 cr on the resin side plus ~₹50–60 cr on the chemical side) is awaiting environmental clearance from a government signatory currently unavailable. It will not complete by end of FY23 and will spill over to H1 FY24. The major expenditure portion will be in the later part of execution.
- FY22 actual spend: ~₹49 cr was spent across membrane plant capacity enhancement, engineering division capacity improvements, and incremental chemical division CAPEX.
- FY23 planned spend: ~₹60–70 cr total, with the major portion going to complete the membrane facility capacity enhancement plus ₹15–20 cr incremental in the chemical segment.
- Membrane plant: Currently running at well over 90% capacity utilization; expansion is on and implementation is expected in Q4 of FY23.
- Ankleshwar plant: Some headroom is available; the company is trying to make incremental adjustments to augment capacities for the time being while the greenfield expansion is delayed.
- Resin capacity outlook: A substantial increase is anticipated in the next couple of years, which will boost resin business revenues.
Capital Allocation & Corporate Structure
- Retained earnings deployment: Internal generation is partly used for capacity augmentations in the chemical business, with additional cash deployed to further expand projects and the engineering side. As contract sizes grow larger, additional capital will be required to support growth.
- Subsidiary consolidation: Progress is being made; in the next few months, the company will initiate a merger exercise involving more than two companies. This is the first step of consolidating some subsidiaries, with more such consolidations to follow.
- R&D as margin defense: Continuous innovation and new product development is described as a core requirement of the business and essential to maintaining margins above commodity-player levels.
Management: "The kind of business that we are in, we need to continuously innovate and bring out new products, that is core requirement of our business and also fulfills our ability to maintain margins at a level which is better than what otherwise is available for commodity players."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Engineering revenue growth | Significant improvement expected over FY22 on strong order book and inquiry bank | FY23 |
| Full-year EBIT margin | Maintain similar to FY22 (~11–11.5%) | FY23 |
| Sri Lanka project completion | Complete contract assuming smooth ground situation | Q2 FY23 |
| Consumer products turnaround | Positive EBITDA expected | FY23 |
| Chemical segment growth | Much stronger growth expected vs. last couple of years | FY23 |
| Membrane plant expansion | Implementation completed | Q4 FY23 |
| UP Jal Nigam (firmed-up portion) | Execution completed | FY24 |
| UP Jal Nigam (remaining portion) | Execution completed | H1 FY25 |
| Greenfield CAPEX completion | Major spend in later part of execution; spills beyond FY23 | H1 FY24 |
| Subsidiary consolidation | Initiate merger exercise involving more than two companies | Next few months |
Key Metrics
| Metric | Q4 FY22 |
|---|---|
| Consolidated operating income | ₹496.4 cr, +11.5% YoY |
| Operating EBITDA | ₹95.1 cr, +11% YoY; EBITDA margin 19.16% |
| Net profit after tax | ₹83.2 cr, +18% YoY; PAT margin 16.76% |
| Engineering division revenue | ₹320.8 cr, +~10% YoY |
| Engineering division EBIT | ₹73.2 cr, +~31% YoY |
| Chemical division revenue | ₹151.5 cr, +~17% YoY |
| Chemical division EBIT | ₹34.5 cr, -11% YoY |
| Consumer segment revenue | ₹42.5 cr, +~13% YoY |
| Consumer segment loss | ₹1.6 cr |
| Order book (excl. Sri Lanka & UP Jal Nigam) | ~₹1,267 cr as of 31 Mar 22 |
| Total order book (incl. Sri Lanka & UP Jal Nigam) | ~₹2,674 cr as of 31 Mar 22 |
| Bid pipeline | ~₹6,700 cr |
| Chemical capacity utilization | ~75% |
| Membrane plant capacity utilization | Well over 90%; expansion expected in Q4 FY23 |
| FY23 total CAPEX guidance | ~₹60–70 cr |
| Greenfield CAPEX | Significantly upwards of ₹200 cr, awaiting environmental clearance |