Key Takeaways
- Manufacturing margin hit by one export loss: A single export order caused a significant loss, dragging segment profitability; management expects margins to improve from Q2 FY23 onward.
- Project elongation strains the balance sheet: COVID-related delays on large-duration PSU and FGD projects have pushed out milestone payments, driving up borrowings; a substantial reduction is expected over the next 10-12 months as projects complete.
- Philippines plant is a binary catalyst: Construction started in August 2022 with a 12-month timeline; management aims to either sell the plant at a reasonable value or operate it profitably, with no huge financial downside seen in either scenario.
- Learning curve in new project businesses: Acute labor shortages and difficult site conditions in newer areas like FGD and material handling have forced a strategic rethink: more upfront engineering, higher site-work cost allocation, and selective bidding.
- What to watch next quarter: Whether manufacturing margins actually normalize toward the 8-9% range, the pace of borrowing reduction as milestone payments come in, and any progress on selling the Philippines plant.
Manufacturing: The One-Off Hit & Recovery Path
- Export order loss: The manufacturing segment's profitability was dragged down entirely by a single loss-making export job; management confirmed the full impact was absorbed in the June quarter and is not inherent to the division.
- Margin normalization expected: Management guided for manufacturing margins to improve from Q2 FY23 onward, targeting a normalized range of 8-9% going forward.
- Commodity price lag: Margins on current dispatches reflect higher steel costs locked in when orders were booked; the benefit of recent commodity price declines will flow through with a lag of a couple of quarters as newer orders enter the revenue cycle.
- Order book health: Manufacturing is booked for roughly 12 months, with some short-cycle parts of the business holding 2-3 months of orders; management stated there is no shortage of orders.
Aditya Puri: "So, in manufacturing, there is no shortage of orders. The margin, this quarter has got impacted because we lost money in one export order. And we lost a lot of money over there. But we expect the margins in manufacturing to improve from this quarter onwards."
Project Business: Delays, Borrowings & Strategic Learnings
- Project elongation: Several large-duration projects, including FGD and PSU orders, have been extended by a few months due to COVID-related disruptions at both the company and customer ends, delaying milestone-linked payments.
- Borrowings spike: The working capital cycle stretched as project timelines slipped, causing borrowings to rise; management expects borrowings to come down substantially over the next year as these projects complete and milestone payments are collected.
- Labor is the core site challenge: Acute labor shortages emerged as workers migrated during COVID and found jobs closer to home; management called this "probably the single most important challenge" on project sites.
- Strategic recalibration: Having entered new areas like material handling and FGD in the last 3-4 years, the company is now allocating more money for site work, accelerating engineering to absorb customer-end delays, and will avoid bidding where site work is disproportionately high relative to project value.
- FGD outlook: The company continues to bid for FGD orders, which are now smaller in value and timeframe; management hopes for higher margins on these orders going forward, aided by the learnings.
Aditya Puri: "Getting labor is probably one of the single most important challenge."
Philippines Biofuel Plant: A Contained Binary Outcome
- Construction underway: The Cavite biofuel ethanol plant in the Philippines began construction in August 2022, with completion expected by July 2023.
- Q1 loss largely non-operational: The INR 23 crores loss in Q1 FY23 was predominantly a foreign currency translation loss driven by the Philippine peso's movement against the rupee; the actual operational loss was only INR 4-5 crores.
- Translation loss treatment: The forex loss is captured in consolidated P&L under 'other expenses', which is why consolidated PBT is lower than standalone.
- Path to value: Management's stated 12-month goal is either to sell the plant at a reasonable value (with no loss expected) or to start running it, describing operations as "quite profitable"; either way, no huge financial impact is anticipated.
- Ongoing costs: Smaller expenses of roughly INR 4-5 crores per quarter continue as revenue expenditure, while interest will be capitalized going forward now that construction has started.
Aditya Puri: "In 12 months' time, we would hope either the plant is sold, or we have started to run the plant."
Segment & Subsidiary Performance
| Segment / Entity | Trend | Commentary |
|---|---|---|
| Manufacturing | ▼ Hit | Profitability dragged by a single export order loss; margins expected to normalize to 8-9% from Q2 onward. |
| EPC | ▲ Strong | Quite strong in the quarter; margin sustainability depends on the mix of old and new orders being billed, with no major surprises seen as of now. |
| Sugar (Consolidated) | ▲ Improved | Higher sugar sales driven by exports in Q1, plus revenue and profit contribution from the ethanol plant. |
| Distillery | ▬ Normal | INR 50-55 crores quarterly revenue at full capacity; 7% EBIT described as "about normal." |
| Isgec Hitachi Zosen JV | ▼ Very low | Revenue near zero because the end customer, despite paying ~90% advance, could not pick up ready-to-ship equipment; revenue not booked. |
| Cavite Biofuel | ▼ Loss | INR 23 crores loss, overwhelmingly from peso forex translation; operational loss was only INR 4-5 crores. |
Order Book, Pipeline & Capacity
- Inquiry pipeline robust: Domestic inquiries exceed INR 10,000 crores across almost all lines of business, with some budgetary and some nearing decision; export inquiries have also picked up, particularly from developing countries, though order finalization remains slow.
- Selective order booking: Management is being careful about which orders to book, factoring in cash flow costs on PSU bids and avoiding projects with excessive site-work exposure.
- PSU exposure: The company would like to reduce PSU order book to 25-30% but cannot commit to a timeline, as it depends on market behavior and export order growth.
- Order book duration: Enough orders in hand to keep all divisions busy for the next 18 months, though a weighted duration has not been formally calculated.
- Capacity expansion: Manufacturing capacity has already been debottlenecked to almost 200%; further low-investment output increases are being explored, but management is waiting for demand stabilization before committing to more efficient, higher-cost methods.
- Isgec Hitachi Zosen: Significant investment in area expansion and capacity increase has already driven an order book increase; revenue is expected to be "certainly much higher than the last year's number" with normalization from Q2 onward as equipment ships.
Aditya Puri: "We are waiting to see if this increase will be sustained. Also, we are looking at some methods whereby with low investment we can increase the output. We are looking at that. It may not be the most efficient way of doing work, but we are looking till demand stabilizes, and we are confident of the demand stabilization."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Manufacturing margin recovery | Improve from Q2 FY23; normalize to 8-9% | From Q2 FY23 onward |
| Borrowings reduction | Come down substantially as milestone payments collected on large projects completing | Next 10-12 months |
| Philippines plant completion | Construction complete; plant either sold or operational | July 2023 (12 months from Aug 2022) |
| FY23 sales growth | Maintain 5% growth view | FY23 |
| Isgec Hitachi Zosen revenue | "Certainly much higher than the last year's number" | FY23 |
| Distillery expansion | Expanded capacity of 135-145 KLPD with <INR 10 crores investment | ~8-9 months |
| FY23 CapEx | INR 20 crores for IT system; INR 20 crores for manufacturing debottlenecking | By end of FY23 |
| Balance sheet improvement | Working capital reduction and balance sheet improvement to start | Next 10-12 months |
Key Metrics
| Metric | Q1 FY23 |
|---|---|
| Consolidated order booking | ₹1,331 cr, compared to ₹2,366 cr in Q1 FY22 |
| Consolidated orders in-hand | ₹7,736 cr as on 30 June 2022, against ₹7,924 cr as on 30 June 2021 |
| Project business share of order book | 73% of consolidated order book; product businesses 27% |
| Export orders in order book | ₹1,101 cr, just over 14% of consolidated order book |
| Isgec Hitachi Zosen order book | ₹792 cr as on 30 June 2022 |
| Consolidated borrowings | ₹1,194 cr as on 30 June 2022 |
| Philippines group borrowings | ₹273 cr, included in consolidated borrowings |
| Manufacturing capacity utilization | 95% to 100% going forward |
| PSU orders as percentage of order book | ~42% |
| Manufacturing segment normalized margin expectation | 8% to 9% going forward |
| Distillery unit EBIT margin | 7% in Q1 FY23, expected to be normal going forward |
| Distillery unit quarterly revenue expectation | ₹50–55 cr per quarter, running at full capacity |
| Distillery capacity expansion target | 135 to 145 KLPD, from current 100 KLPD, investment under ₹10 cr, timeline 8–9 months |
| Philippines plant quarterly P&L expenditure | ₹4–5 cr per quarter going forward (maintenance, salaries, insurance); Q1 included ~₹23 cr largely foreign currency translation loss |
| FY23 CapEx plan | ~₹40 cr total: ~₹20 cr for new IT system, ~₹20 cr for manufacturing debottlenecking and production increase |
| Domestic inquiry pipeline | More than ₹10,000 cr of inquiries |