Key Takeaways
- Strategy pivot underway, near-term drag: Management has deliberately stopped booking long-duration EPC projects, a structural shift that will improve margins and cash flow over time but currently leaves ~INR2,000-2,200 crores of legacy low-margin orders to work through.
- Double-digit revenue growth guided: Standalone revenue growth is guided at "closer to 15%" for FY25, supported by a shift to shorter-cycle, higher-technology orders and better payment terms from customers.
- Philippines plant commissioned, contribution deferred: The bioethanol plant began commercial production in April 2024 but will not run at full capacity or make a real contribution until the sugarcane season starting November 2024.
- Cash flow structurally improving: Customer advances have risen significantly, a trend management says is not a one-off but reflects the changing nature of orders toward more technology-intensive projects with better payment terms.
- What to watch next quarter: Whether the guided 15% standalone revenue growth translates into order book numbers, the pace at which legacy low-margin orders run off, and any clarity on Eagle Press order inflow.
Strategy Shift: Away from Long-Duration Projects
- Structural decision made: The company has deliberately stopped booking long-duration EPC projects, particularly in exports where significant site work, construction, or civil work is involved. Site works carry uncertainties outside the company's control: labour shortages, weather, and logistics.
- New order profile: Going forward, larger export orders will be structured so ISGEC supplies machinery and equipment, with the customer handling installation at their own cost and risk under ISGEC's supervision. This reduces execution risk and shortens the order-to-cash cycle.
- FGD projects exemplify the problem: Flue gas desulphurization projects typically took much longer than their initial 3-3.5 year timeline. The company is no longer booking fresh FGD orders.
- Receivables benefit: As the EPC order book shifts to lower-duration orders, receivables classified as milestone or retention payments will keep coming down. Of the INR2,928 crores receivables, ~INR400 crores relates to two large FGD orders completing this year.
Aditya Puri: "we have adopted a strategy of not going into very long-duration projects because there are lots of uncertainties associated with them. The site works are not totally in our control, the labour shortages, weather problems all those sorts of things. So we have decided deliberately to go into low duration projects and high-technology linked projects on the project site."
Margins: The Legacy Overhang and the Recovery Path
- Legacy low-margin orders: About INR2,000-2,200 crores of legacy low-margin orders remain in the order book. Most long-duration projects are near completion and almost all should finish in the next few quarters.
- Hard floor on new orders: Management is explicit: it will not take any future order yielding less than 7-8% EBITDA margin in the project business. The objective for fresh orders is to target 8% margins.
- Recovery trajectory: Margins will increase as legacy orders complete, but the improvement will not look like a step jump this year. It may look like a step jump in the next financial year (FY25-26), when a difference in project business margins should become visible.
- Manufacturing margins: The manufacturing business runs at 10-12% margins. The ISGEC Hitachi Zosen JV booked good orders at better margins, with profits in percentage terms up substantially, and is expected to reach normal ISGEC standalone manufacturing margins.
- Medium-term aspiration: Management is aspiring for 11-12% EBITDA margin in a 3-4 year timeframe, which it says "looks to be practically possible."
Kishore Chatnani: "There is going to be an increase in margins. It's not going to look like a step jump this year, it might look like a step jump in the next year."
Aditya Puri: "We are very clear that we will not take any future order, which will give a margin of less than 7%-8% on an EBITDA basis. In the project business."
Revenue Growth & Order Book
- FY24 performance: Standalone revenue grew 5% YoY; consolidated revenue fell 2.6% YoY, dragged by the sugar business (government restricted sugar releases and exports) and project revenue that slipped into April/May due to shipping problems.
- FY25 guidance: Management expects "much higher growth" and "closer to 15%" standalone revenue growth for the current year. Manufacturing output is expected to grow more than 5-10%.
- Order booking momentum: The company has booked better-than-normal orders in April and May of the current year and expects order booking during the year to be "certainly much more" than last year. Specific numbers were not disclosed.
- Export traction: More than 50% of JV orders this year were from overseas, and good traction is expected in exports even outside the JV in the main company.
Philippines Bioethanol Plant
- Status: The plant was commissioned and commenced commercial production in April 2024. Peripheral work (boundary wall, internal roads) remains but is unrelated to plant operations.
- Feedstock constraint: The plant will run on molasses until the next sugarcane season, probably not at full capacity. Real production and contribution will come when the sugarcane season starts around end-October/early-November 2024, when it shifts to sugarcane as feedstock.
- Strategic flexibility: Management is open to both running the plant and selling it if a reasonable price is obtained, though the stated intention is to recover the investment by operating it.
- Financial disclosure deferred: Management declined to provide contribution numbers for this year or the upcoming year, saying it would share closer to the next season. Cumulative investment and gross block addition figures were also unavailable, with capitalization to be completed in the current quarter.
Cash Flow & Balance Sheet
- Cash flow from operations improved: Driven largely by an increase in other current liabilities (INR2,359 crores vs INR1,401 crores), reflecting better payment terms and higher customer advances.
- Advances structurally higher: Customer advances have gone up significantly, and management says this is not a one-off. The nature of orders being booked and their payment terms are changing, with advances appearing as unearned revenue on the balance sheet.
- Receivables expected to decline: Management expects receivables to come down substantially during the current year as the EPC order book shifts to lower-duration orders.
Other Businesses & Developments
- New products in boilers: Three new products developed: tail gas fired boilers, flue gas coolers, and ongoing development in air pollution control technologies. The company also completed one of the biggest cement waste heat boilers in the world for an Indian customer.
- Energy conservation: Working on waste heat recovery and reducing energy consumption in the sugar industry.
- Green ammonia: The company is in the value chain for green ammonia and is consciously evaluating what it can manufacture in that capability.
- Eagle Press: Continues to face a problem in booking orders. Some orders are being seen, but the situation remains uncertain; better guidance is expected next quarter.
- CapEx: Expected in the region of INR50 crores plus for FY25.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Standalone revenue growth | "Closer to 15%" | FY25 |
| Manufacturing output growth | More than 5-10% | FY25 |
| Order booking | "Certainly much more" than last year | FY25 |
| Project margin floor | No new order below 7-8% EBITDA margin | Effective immediately |
| Legacy order completion | Almost all long-duration projects completed | Next few quarters |
| Project margin visibility | Difference in project business margins becomes visible | FY25-26 |
| Receivables reduction | Come down substantially | FY25 |
| Philippines plant contribution | Real production on sugarcane feedstock | Sugarcane season starting Nov 2024 |
| EBITDA margin aspiration | 11-12% | 3-4 year timeframe |
| CapEx | ~INR50 crores plus | FY25 |
Key Metrics
| Metric | Q4 FY24 |
|---|---|
| Standalone revenue | ₹4,906 cr, +5% YoY |
| Consolidated revenue | ₹6,245 cr, -2.6% YoY |
| Standalone profit before tax | ₹304 cr, +30% YoY |
| Consolidated profit before tax | ₹354 cr, +22% YoY |
| Standalone net fund position | Net surplus of ₹45 cr, vs net borrowing of ₹308 cr as of 31st March 2023 |
| Consolidated net borrowing | ₹594 cr, -43% YoY from ₹1,032 cr |
| Consolidated order book | ₹7,905 cr, 71% project business, 29% manufacturing |
| International orders in order book | ₹1,047 cr, about 13% of consolidated order book |
| ISGEC Hitachi Zosen order book | ₹1,048 cr, doubled from ~₹500 cr a year ago |
| Project division EBITDA margin | 3.9% for FY24 |
| Legacy low-margin orders in order book | ₹2,000-2,200 cr, of which ₹1,400-1,500 cr to complete in FY25 |
| Receivables | ₹2,928 cr, including ~₹400 cr from two large FGD orders |
| Other current liabilities | ₹2,359 cr, vs ₹1,401 cr, driven by higher customer advances and unearned revenue |
| Philippines plant ethanol produced | 0.3 cr litres sold up to now, at average rate of ~₹120 per litre |
| Philippines plant annual capacity | 4.2 cr litres |
| Revenue growth guidance (standalone, FY25) | Closer to 15% |
| Project business target EBITDA margin | 7-8% on fresh orders |
| Manufacturing business target margin | 10-12% |
| FY25 capex plan | ₹50 cr plus |