Jash Engineering Ltd Q3 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/gb7wd6nbh7lp4fykjuhfvlg9.pdf

Key Takeaways


Competitor Exits & Global Market Shift

Pratik Patel: "One of the biggest competitor in UK have shut down. I think we are the reason for it shutting down or closing down."

Domestic Market Inflection

Pratik Patel: "Finally it looks like domestic market is also coming in line with the global market, so in years to come we are looking at very strong domestic order book position and this should propel the company along with our total export position which is also becoming stronger."

Rodney Hunt: The US Problem & Fix


Capacity Build-Out


Profitability & Margin Mechanics

Pratik Patel: "We expect 11% but let us keep our fingers crossed if you are happy at and I'm also happy at 10%."

Capital Allocation & Governance

Pratik Patel: "I believe that the more transparent you are, more positive you are in your reporting the shareholder as well as all the stakeholder are better place in our company. We do not want something like what happened currently, you are all aware what happened and something like that happens with us and so we are very vigilant and we will try to be more vigilant and transparent."

Guidance & Commitments

CommitmentSpecificsTimeline
Consolidated revenue₹430 crores, may go down by ₹20 crores or soFY23 (current year)
Rodney Hunt revenueAchieve more than $20 million (up from $12 million currently); would be quite profitable at that levelBy end of FY23
Unit II new product lineCommission the new product lineQ3 of coming financial year (FY24)
Shivpad plantConstruction start April 2023, completeBy March 2024
Chennai new plantNew plant operationalBy March 2024
Rodney Hunt Houston expansionPlant completedBy March 2025
CapacityIncrease from ₹500 crores to ₹650 croresAcross the three-plant build-out through March 2025
Revenue target₹650 crores (does not include any revenue from acquisition of the competitor who closed down)Within 4 years, by 2025-26, definitely by 2027
PAT margin11% aspiration, happy at 10%Ongoing
DividendGradually increase to at least ₹7.2 per share (72% of par)Over next 2-3 years
US large project bid$18 million single job, Jash the only Gate company named; results expectedWithin next 2-3 months
US bonding solutionFinal talks with a willing US citizen when management visits USNext week

Key Metrics

MetricQ3 FY23
Consolidated revenue (9M FY23)₹241 cr, up from ₹214 cr in 9M FY22
Revenue from outside India (9M FY23)₹126 cr, 54% of total revenue of ₹233 cr
Comprehensive income (9M FY23)More than ₹22 cr
EPS (9M FY23)Nearly doubled versus same period last year
Order bookNearly ₹720 cr, comprising ₹471 cr outside India and ₹249 cr within India
Rodney Hunt order book₹269 cr, close to $33 million
Shivpad order book₹12.47 cr
Orders negotiated, awaiting finalisation₹33 cr negotiated, ₹25-26 cr under final negotiation
FY23 sales outlook₹430 cr, may reduce by ₹20 cr or so
Rodney Hunt expected Q4 FY23 revenueMore than $20 million, up from $12 million in 9M
Rodney Hunt net profit (FY22)$0.5 million
Combined plant turnover capability₹500 cr, expanding to ₹650 cr in coming years
Revenue capacity expansion timeline₹650 cr by FY26, definitely by FY27
Finished goods awaiting dispatch or delivery (Jash standalone)₹33 cr, including ₹14 cr delivered but not reached site and ₹19 cr at plant
Singapore order bookAround ₹100 cr
Domestic business growth expectation100-150% more than domestic turnover of last few years
Rodney Hunt billing in January 2023More than $3 million
US single-job bid size$18 million, company named as sole gate supplier
Rodney Hunt expansion capex$2-3 million, plus $0.5 million for land
Dividend distribution target72% of par value (₹7.2 per share on ₹10 par) over next 2-3 years
Revenue concentration in Q460% of annual revenue