Jindal Steel Ltd Q1 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/0udwqvwftqkn2852zehstd3z.pdf

Key Takeaways


The Export Duty Shock & Strategic Pivot

Sharma: "We are now entering in to niche markets where the products are sold in terms of thousands of tons not in lakhs of tons... we have found a great market as a vacuum because all of these products are being supplied by either Ukraine or by Russia so since they are under war so we have the opportunity."

Cost Structure & Margin Dynamics

Sharma: "Volatile time is when you produce something which cannot be sold. The volatility in terms of prices going down one-sidedly it is not volatile... I would say it is not volatile situation it is a down sliding and that is good for reduction in the input costs."

Volume, Production & Demand


Balance Sheet & Working Capital


Capex, Expansion & Coal Integration

Sharma: "We will be spending only that amount which we can afford to accrue from our existing business... we would not be under debt burden once again and we do not want to be."

Geopolitical Framing & Policy Stance

Sharma: "It is very difficult to predict today's market because the world is melting down we do not know where the world will settle. So the first and foremost issue is the Russian and Ukrainian war."

Guidance & Commitments

CommitmentSpecificsTimeline
Production volume0.82-0.84 Cr tons for FY23; ~0.21 Cr tons/quarter run-rateFY23
Sales turnoverMore than ₹55,000 CrFY23
Export shareMaintain more than 20% of total productionFY23
Input cost reliefLower coking coal, thermal coal and iron ore costs flow through after pipeline clearsAfter ~Aug 15, 2022
Coking coal priceApproximately $230-240/tonQ2 FY23
Steam coal priceApproximately $200-210/ton C&F IndiaQ2 FY23
Working capital reversalRealize ₹2,500-3,000 Cr buildupCurrent quarter (Q2 FY23)
Capex spend~₹6,000-7,000 Cr/year; ~₹18,000+ Cr totalNext 2-2.5 years
Leverage1x to 1.5x through the cycleOngoing
First coal mine openingUtkal mine, OdishaBefore March 31, 2023
Maintenance shutdownsNo planned shutdownsThrough March 31, 2023
Thermal coal availabilitySituation expected to normalizeWithin 1-10 days

Key Metrics

MetricQ1 FY23
Net income₹12,869 cr, declined 7% QoQ
Adjusted EBITDA₹2,865 cr, +8% QoQ
Adjusted EBITDA margin~19%
Adjusted PAT₹1,626 cr, +28% QoQ
Standalone net debt₹7,413 cr, 0.54x EBITDA, reduced ~₹1,000 cr QoQ
Steel production volume0.2 crore tons, -6% QoQ
Steel sales volume0.17 crore tons, -16% QoQ
Domestic sales volume change-12% QoQ
Export sales volume change-28% QoQ
Realization change+12% QoQ; softening 15–16% in June–July
Cost increase+10% QoQ; coking coal cost +33%, thermal coal cost +27%
FY23 production volume target0.82–0.84 crore tons
FY23 sales turnover targetMore than ₹55,000 cr
Export share targetMore than 20% of total production
Capex plan~₹18,000+ cr over next 2–2.5 years; ~₹700 cr spent in Q1
Working capital buildup₹2,500–3,000 cr during the quarter
Cash and equivalents~₹3,000+ cr on balance sheet
JPL divestment proceeds received₹3,015 cr
Mozambique subsidiary EBITDA₹334 cr
South Africa subsidiary EBITDA₹84 cr
Australia subsidiary EBITDA₹24 cr
Coking coal external dependence40–42%; 58% from own mines
Kasia iron ore mine production~500,000 tons per month
Unrealized forex gain₹446 cr, on ~$1.6 bn overseas loan to subsidiary
Export duty paid₹113 cr
Credit ratingAA-, unchanged