Jindal Steel Ltd Q4 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/wpph67jyn8rj8fdtwrsvyis1.pdf

Key Takeaways


Volume & Realization Dynamics

Jha: "November '22 the prices of iron ore fines from NMDC were 2,760 and Odisha was 3,550. So, this gap has really opened up."

Cost Structure & One-Time Charges


Australia: Wollongong Asset Turnaround

Jha: "We are quite confident that within a couple of quarters we should be seeing positive reports from that side. That is where we are as of now. We are not able to say with certainty to you that this is the amount of money that we'll make or anything like that but it has probably seen its bottom."

Expansion Pipeline & Coal Security

Jha: "Hopefully we have improved as management. That is all I can say."

Capital Allocation & Balance Sheet

Jha: "Even in the down cycle I wouldn't like to violate 1.5x, I did say that and I'm sticking my neck out of it saying that yes, we'll do it."

Demand Environment & Market Positioning

Jha: "Arijit have you met a marketing guy who ever says that prices I can get much more? They always tell you that competition is not pricing…"

Guidance & Commitments

CommitmentSpecificsTimeline
Pellet plant commercializationFirst 0.6 crore ton plant full-fledged operationsWithin weeks
Capital allocation policy release3-year CAPEX program and project slate finalizedOver the next few weeks
Utkal-C coal block openingMining license stage; one last clearance awaited"Anytime"
Hot strip mill commissioningExpected in Q3Q3 FY24
Blast furnace commissioningSecond blast furnaceTowards end of FY24
Second pellet plant commissioningConcurrent with second blast furnaceTowards end of FY24
Slurry pipeline completionDelayed by elections and other issuesTowards end of current year
Net debt to EBITDA ceilingBelow 1.5x through the cycle, including down cyclesOngoing
Australia asset turnaroundPositive reports expectedWithin a couple of quarters

Key Metrics

MetricQ4 FY23
Sales volume0.2 crore tons, +7% QoQ
Production volume0.2 crore tons, -2% QoQ
Realization+3% QoQ, with current softening of 1-2%
Export share11% of volume, up from 5% in Q3
SMS cost+2% QoQ, driven by higher iron ore and pellet prices
Consolidated adjusted EBITDA₹2,240 cr, -2% QoQ
Standalone India adjusted EBITDA₹2,178 cr
Overseas subsidiaries adjusted EBITDA₹63 cr (Australia, Mozambique, South Africa)
Consolidated PAT₹466 cr, -10% QoQ
Exceptional items₹153 cr, expenses on old projects written off
Inventory write-downs and write-offs~₹250 cr, included in EBITDA
Standalone gross debt (Mar 31)₹11,874 cr
Standalone net debt (Mar 31)₹7,090 cr
Gross debt (April, post prepayment)₹8,984 cr, after prepaying ₹1,895 cr in April
Net debt to EBITDA~0.7x
Dividend₹2 per share
Full year FY23 volume0.77 crore tons, +1% YoY
Full year FY23 production0.79 crore tons, -2% YoY
Full year FY23 consolidated adjusted EBITDA₹9,700 cr
Full year FY23 PAT₹3,193 cr, after exceptional items of ₹1,369 cr
Full year FY23 standalone operating cash flow₹6,351 cr
Full year FY23 CAPEX~₹5,800 cr (JSP and JSO)
Australia subsidiary impairment (depreciation)₹250 cr
Utkal-C coal block mining plan~0.35 crore tons submitted for FY24
Gare Palma mining lease permission0.35-0.4 crore tons per annum range
Crude steel capacity0.96 crore tons
Pellet plant capacity under commissioning0.6 crore tons (first), another 0.6 crore tons to follow
JSO sanctioned debt₹15,700 cr, undrawn as of Q4
Depreciation quarterly run rate~₹600 cr