Key Takeaways
- Volume-led quarter, cost spike hit margins: Double-digit volume growth was offset by a one-time employee cost surge (+25% YoY) and lower incentive income, compressing profitability.
- Expansion engine is fully funded and on track: Three projects (Jaisalmer, Bikaner, Punjab) are slated for H1 FY28 commissioning, backed by a clear ₹3,500-4,000 cr FY27 capex plan and confidence in the 5 crore ton FY30 target.
- Pricing power is being tested: A ~₹10/bag price hike was passed in April-May, but rising fuel and diesel costs, plus intensifying Rajasthan competition, will challenge margin recovery.
- Paints is the next profit pivot: The paints business is guided to hit ₹500-550 cr revenue in FY27 with marginal EBITDA, moving from investment phase to contributor.
- What to watch next quarter: Whether the pre-monsoon price hikes stick, the pace of fuel cost normalization, and any sanction letter for Bihar incentives that would lift other income.
Volume Growth & Market Position
- Double-digit volume ambition: Management expects to add a minimum 0.25 crore tons in FY27, outpacing the ~6-8% industry growth forecast, and aims to revise the annual minimum to 0.3 crore tons going forward.
- Central India ramp-up: The newly commissioned Buxar plant (0.6 cr tons) is fully operational, with management denying any dumping and attributing volume push to key account management rather than non-trade channels.
- Rajasthan defense: With three new locations serving shorter lead distances, management is prepared for intensified competition and expects to consolidate market share, having factored competition into its expansion thesis.
- Utilization buffer: Post-commissioning utilization may dip ~4-5% but will remain above the national average, cushioning the transition as new capacity comes online.
- South debottlenecked: Muddapur capacity increased by 0.1 cr tons (to 0.45 cr tons), adding 0.1 crore tons of ready capacity in the South.
Saraogi: "Now I've already revised that to say 0.25 crore. And going forward, hopefully, we'll revise it to minimum additional 0.3 crore every year. So we have to get that. We have to give the return on investment also."
Cost Structure & Margin Levers
- Employee cost shock: Staff costs rose 25% YoY due to a confluence of one-time items: commissioning of the Central India plant moved salaries from capex to opex, Labor Code reclassification, normal increments, and a one-time leave travel assistance liability.
- FY27 employee cost guide: Management expects a ~12-14% YoY increase from the FY26 base of ₹937 cr, implying a quarterly run rate of ~₹250 cr, though it declined to confirm a specific sustainable figure.
- Cost savings pipeline: An additional ₹50/ton is targeted for FY27, driven by green power and AFR initiatives at South and North plants, though this excludes benefits from new plant ramp-up or new waste heat installations.
- Fuel cost uncertainty: New fuel orders are secured only through September, with costs trending from ~₹150 toward ₹200; diesel price increases remain an unquantified risk, with management estimating a ₹50-60/ton freight impact per ₹10-11 diesel increase.
- Packing cost addressed: A ~₹30 cr packing cost increase from higher volumes and prices has been substantially reduced through alternative sourcing.
- Thermal power exit: 27.5 MW of thermal power plants at white and gray cement units were scrapped as uneconomical, with a shift to green power underway.
Saraogi: "See, as we have already achieved the major cost savings, but it's ongoing. We see another INR50 which we should get in this fiscal, mainly coming – mainly driven by, a, on the green power and some – and on AFR in the South and the North plants."
Expansion Projects & Capex Cycle
- Three H1 FY28 deliveries: The Jaisalmer integrated plant (0.7 cr tons, ₹3,630 cr total cost, ₹742 cr spent), Bikaner grinding station, and Punjab grinding unit are all on track for H1 FY28 commissioning, with civil work advanced and main equipment ordered.
- Nathdwara Wall Putty: A 6 lakh ton plant is in advanced construction and expected to commission by September, adding downstream capacity.
- Capex roadmap: FY27 capex is guided at ₹3,500-4,000 cr (₹800-1,000 cr normal/other, balance on greenfield), stepping down to ₹1,500-2,000 cr in FY28, which excludes any next-phase expansion not yet Board-approved.
- Panna project savings: The announced ₹2,850 cr capex will close at least ₹200-250 cr lower, freeing up capital.
- Next growth leg: A 50 cr ton limestone block won in Andhra Pradesh is positioned for the 2030 plan, while Telangana limestone may be the subsequent phase, though no immediate capacity addition is planned.
- 5 cr ton FY30 confidence: Management is "quite confident" in the plan and sees no current problem, though it acknowledged that a major geopolitical cash flow challenge could shelve it for ~6 months.
Saraogi: "We are quite sure that, I mean as of now, we don't see any problem. We are quite confident that we will go ahead with our plan for '28."
White Cement & Paints Diversification
- White cement pricing: Prices for both White Cement and Wall Putty were raised to pass through substantial chemical input cost increases, with management expecting profitability to stabilize after recent competitive erosion.
- White cement volume: 8-10% growth is expected, with an additional 0.06 cr tons of capacity coming by Q2.
- Paints scale-up: The paints business is guided to ₹500-550 cr top line in FY27, with improving gross margins expected to drive breakeven and marginal full-year EBITDA, marking a transition from investment to contribution.
- Saifco stabilization first: No expansion is planned for the Saifco unit until the plant stabilizes and begins earning profit.
Incentive Income & Other Income
- FY26 shortfall: Incentive income declined below the earlier ~₹75 cr/quarter guidance because Aligarh's 10-year incentive period ended, GST was reduced, and Rajasthan could not claim incentives due to input credit on project investment.
- FY27 guide: Full-year incentive income is expected at ~₹250-260 cr, though quarterly lumpiness is likely; Bihar incentives will be accrued only once the sanction letter is received, per accounting policy, despite eligibility under the scheme.
- FY28 run rate: Could reach ₹300 cr if the quarterly run rate climbs to ₹70-75 cr.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Volume growth | Double-digit; minimum 0.25 cr tons incremental | FY27 |
| Employee cost increase | ~12-14% YoY from ₹937 cr FY26 base | FY27 |
| Cost savings | Additional ₹50/ton from green power and AFR | FY27 |
| Incentive income | ~₹250-260 cr | FY27 |
| Paints revenue | ₹500-550 cr with marginal EBITDA | FY27 |
| Jaisalmer integrated plant | Commissioning | H1 FY28 |
| Bikaner grinding station | Commissioning | H1 FY28 |
| Punjab grinding unit | Commissioning | H1 FY28 |
| Nathdwara Wall Putty plant | Commissioning | By September |
| FY27 capex | ₹3,500-4,000 cr | FY27 |
| FY28 capex | ₹1,500-2,000 cr (excludes next expansion) | FY28 |
| Green power share | Increase by 2-3%, closer to 55% | FY27 |
| 5 cr ton capacity target | Confident, no change foreseen | By FY30 |
| White cement capacity addition | 0.06 cr tons | By Q2 |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Net sales | ₹3,614 cr, +15% QoQ and +11% YoY |
| Net sales (full year FY26) | ₹12,568 cr, +16% YoY |
| EBITDA | ₹670 cr, +25% QoQ and -9% YoY |
| EBITDA (full year FY26) | ₹2,318 cr, +18% YoY |
| EBITDA margin | 18.5%, vs 17.1% QoQ and 22.5% YoY |
| EBITDA margin (full year FY26) | 18.5%, vs 18.2% in FY25 |
| Profit after tax | ₹345 cr, +91% QoQ and -17% YoY |
| Profit after tax (full year FY26) | ₹1,033 cr, +21% YoY |
| Earnings per share (annual) | ₹133.70, vs ₹110.1 in FY25 |
| Proposed dividend | ₹20 per share, subject to shareholder approval |
| Gross debt | ₹5,136 cr as on 31st March |
| Net debt | ₹3,370 cr, net debt to EBITDA 1.45 and net debt to equity 0.48 |
| Volume growth guidance (FY27) | Double-digit growth, incremental volume of at least 0.25 crore tons |
| Capex guidance (FY27) | ₹3,500 cr to ₹4,000 cr |
| Capex guidance (FY28) | ₹1,500 cr to ₹2,000 cr |
| Green power share (FY27 target) | ~55%, up 2-3 ppt from current |
| Kiln fuel cost | ₹1.48 per Kcal |
| Trade channel mix (rail share) | 8% |
| Clinker-to-cement ratio | 67% |
| Paints revenue (FY26) | ₹380 cr, with EBITDA loss of around ₹40 cr |
| Paints revenue guidance (FY27) | ₹500 cr to ₹550 cr, expected EBITDA breakeven or marginally positive |
| White cement volume growth guidance (FY27) | 8% to 10% |
| Incentive income (Q4 FY26) | ₹29 cr, outstanding incentives ~₹300 cr as on 31st March |
| Incentive income guidance (FY27) | ~₹250 cr to ₹260 cr |
| Cost savings target (FY27) | ₹50 per ton, driven by green power and AFR |
| Employee cost (full year FY26) | ₹937 cr, expected 12% to 14% increase in FY27 |
| Fuel cost inflation expected | ₹150 per ton, may rise to ₹200 per ton |
| Price increase passed on (April-May) | ~₹10 per bag |