J Kumar Infraprojects Ltd Q2 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/h9j57pziv0bx65zdpmvf4b57.pdf

Key Takeaways


Financial Performance

Gupta: "Of course, we have been giving consistent margins throughout the year, and this year also and going forward also, whatever our order book is there is with secured 14% to 15% of EBITDA margin, Alokji. We are very confident to deliver these similar margins going forward because as you must be aware, all these contracts are covered with price escalation clause so that any increase or decrease in the commodity prices does not impact on our margins."

Order Book & Bid Pipeline

Gupta: "Jiten, as I told you, this is a golden period for India infrastructure industry. In the coming 7 to 10 years, there will be a huge inflow."

Project Progress & Milestones

ProjectCompletion StatusExpected Milestone
Mumbai Metro Line 2 & 7Partially operational since AprilFully operational by January 2023
Mumbai Metro Line 3 (Phase 1: SEEPZ to BKC)87% complete; tunneling fully doneOpen by December 2023
Mumbai Metro Line 3 (Phase 2)In progressOpen by June 2024
Dwarka Expressway (Package 2)63% completeOpen by May 2023
Dwarka Expressway (Entire project)In progressComplete by November 2023
Line 2b18–20% work completedNot specified
Line 664% completeNot specified
Pune Metro80% completeNot specified
SCLR75% completeNot specified
CIDCO Coastal RoadOff-site work started (casting yard, designs)On-site river work expected to start after December, by January, subject to forest and mangrove permissions
Ircon Tunnel (Vadodara-Mumbai)Setup ready, excavation begunAppointed date expected in coming weeks

Geographic & Segment Expansion


Income Tax Search

Gupta: "Alokji, I think this is a routine course of business. And the same question I asked them - why have you come? They told, you guys are growing too fast. I think the companies which are growing, this is the normal course of business, and I am sure there will be no impact on the Company's growth operations or financials on this behalf."

Guidance & Commitments

CommitmentSpecificsTimeline
Revenue₹4,000–4,200 croresFY23
Revenue growth15% growth over FY23FY24
Revenue visionBecome a $1 billion revenue companyBy FY27
Order bookReach ₹12,000–13,000 croresBy March 2023
Order inflowSecure ₹4,000–5,000 crores in new ordersFY23
EBITDA marginSustain 14–15%Ongoing, across all future bids
Gross debtKeep within ₹500 croresBy March 2023 and maintain thereafter
CAPEX₹90–100 crores (routine, including one TBM)FY23
Order book executionExecute ₹6,500–7,000 crores from current order bookComing 1–1.5 years
Mumbai Metro Line 2 & 7Fully operationalJanuary 2023
Mumbai Metro Line 3 (Phase 1)Open SEEPZ to BKCDecember 2023
Dwarka Expressway (Package 2)Open to trafficMay 2023
CIDCO Coastal RoadStart on-site river workAfter December, by January, subject to permissions

Key Metrics

MetricQ2 FY23
Revenue from operations₹1,013 cr, up 31% YoY from ₹772 cr
EBITDA₹146 cr, up 32% YoY from ₹110 cr
EBITDA margin14.4%, vs 14.3% in Q2 FY22
PAT₹68 cr, up 64% YoY from ₹41 cr
PAT margin6.7%, vs 5.3% in Q2 FY22
H1 FY23 revenue₹2,007 cr, up 39% YoY from ₹1,447 cr
H1 FY23 EBITDA margin14.3%
H1 FY23 PAT₹129 cr, up 77% YoY from ₹73 cr
Order book₹11,439 cr as of Sep 30, 2022; Metro 55%, flyovers/bridges/tunnels/roads 33%
FY23 order inflow to date₹1,688 cr
FY23 order inflow target₹4,000–5,000 cr
Target order book by Mar '23₹12,000–13,000 cr
FY23 revenue guidance₹4,000–4,200 cr; H1 achieved ₹2,007 cr
FY24 revenue growth expectation15% growth; ₹6,500–7,000 cr execution from order book in 1–1.5 years
Gross debt target by Mar '23Within ₹500 cr; reduced by ₹23 cr in Q2
Unbilled revenue₹548 cr as of Sep 30, 2022
Mobilization advance₹541 cr as of Sep 30, 2022
Borrowing cost9–10%
Sanctioned limits utilization₹2,800 cr out of ₹3,800 cr; non-fund-based ₹2,390 cr, rest fund-based
Retention money receivable₹225 cr as of Sep 30, 2022
FDR₹423 cr as of Sep 30, 2022
H1 FY23 CAPEX₹52 cr (cash flow shows ₹90.25 cr including capital WIP payments)
Full-year FY23 CAPEX guidance₹90–100 cr (routine maintenance CAPEX, includes 1 TBM at ~₹60 cr for Delhi project)
Mumbai Metro Line 3 Phase 1 completion87% work completed; tunneling fully completed
Dwarka Expressway completion63% work completed; entire project by Nov '23
Revenue vision$1 billion revenue company by FY27 with order book of ~₹20,000 cr
Bid pipeline₹70,000–75,000 cr of projects to participate in over 6–9 months
Projects already bid~₹6,500 cr (Kerala NHAI ~₹2,000 cr, bullet train ~₹4,000 cr, Bengaluru depot, ROB Sanpada, others)