J Kumar Infraprojects Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/oaz46p44rybvibpj8nzeg3x8.pdf

Key Takeaways


Revenue: The Monsoon Math

Kamal Gupta: "So, Shravan, as you are aware, this year, the monsoon has extended till October, in fact. So, we just want to give a conservative figure. And as you know, we always intend to do more than what we say."

Order Book & Bid Pipeline


Project Progress: What Is Moving, What Is Stuck

ProjectStatusKey Detail
Chennai Elevated Corridor▲ Execution in full swingCasting yard fully operational; foundations and piling ~40–45% done; substructure and pillars underway; only hindrance was extended Chennai monsoon.
MMRDA Anand Nagar-Saket (INR1,800 cr)▲ Revenue startedPiling, pile caps and pillar works underway; revenue already flowing.
NBCC Silicon Valley, Noida▲ Revenue startedWork in full swing; revenue has started pouring in.
GMLR Tunneling▬ Preparatory phaseTBM has reached the job site; ~700 rings cast at the casting yard; main shaft excavation for lowering the TBM ongoing; tree cutting done.
CIDCO (INR1,020 cr)▼ Awaiting clearanceEnvironmental clearances expected in November; management expects to start by December.
Versova-Dahisar Coastal Road▬ Permitting stageStage 1 permissions received; Stage 2 at final verge; MPCB and CRZ permissions in hand; tree-cutting permissions awaited; six foundations completed on roadside; IIT suggested one more ramp addition submitted for approval; casting yard land identified.

Margins & Balance Sheet

Kamal Gupta: "In H1 also, as you must have seen, we have done EBITDA margin of 14.6%. So, we'll be able to maintain this 14% to 15% of margin in this year as well. There's absolutely no issue. And going forward also, we are intending to go 1% notch higher and trying to do it like 15% to 16% in the coming two years."

Capital Raising: QIP on Standby

Kamal Gupta: "It all depends upon the nature of work that we bag, means whether how capex oriented it is, what is the working capital requirement. So, it's a very dependable discussion. But yes, we are keeping ourselves in preparedness to be ready for it, but with no immediate plans to be precise."

Strategic Positioning & H2 Outlook

Kamal Gupta: "Where others see complexity, we see opportunity. Technically demanding, first-of-their-kind projects are not obstacles, they are catalysts that push us to innovate, adapt and lead."

Guidance & Commitments

CommitmentSpecificsTimeline
FY26 revenueINR6,200–6,300 crores (~11% YoY growth)FY26 full year
FY26 EBITDA marginMaintain 14–15%FY26 full year
Medium-term EBITDA marginLift to 15–16%Coming two years
FY26 order inflowINR5,000–6,000 croresFY26 full year
Closing order bookINR20,000–23,000 croresMarch 2026
Revenue growth ambition16–17%Going ahead (no year specified)
Net working capital~INR800 crores (120–130 days)FY26 year-end
FY26 capex~INR500 crores (incl. INR100 cr maintenance)FY26 full year
FY27 capex~INR200 croresFY27 full year
CIDCO project startAfter environmental clearancesExpected December 2025
GMLR substantial revenue contributionMaterial top-line contributionFrom next year onward
TBM depreciation startPro-rata from Q2 FY27FY27 Q2

Key Metrics

MetricQ2 FY26
Revenue from operations (H1 FY26)₹2,826 cr, +10% YoY vs ₹2,574 cr in H1 FY25
EBITDA (H1 FY26)₹411 cr, +10% YoY vs ₹373 cr in H1 FY25
EBITDA margin (H1 FY26)14.6%, vs 14.5% in H1 FY25
PAT (H1 FY26)₹195 cr, +10% YoY vs ₹177 cr in H1 FY25
PAT margin (H1 FY26)6.9%
FY26 revenue guidance₹6,200–₹6,300 cr, ~11% YoY growth, revised from ₹6,500 cr
FY26 EBITDA margin guidance14% to 15%, maintained; aiming 15%–16% in coming two years
Total order book (30 Sep 2025)₹20,160 cr
Order inflow in H1 FY26~₹150 cr
L1 position₹1,200 cr, conventional centre in Lucknow
FY26 order inflow target₹5,000–₹6,000 cr
Closing order book target (Mar 2026)₹20,000–₹23,000 cr
Gross debt~₹75 cr
Net debtnegative ₹124 cr
Working capital₹775 cr, expected ~₹800 cr by year-end; target 120–130 days
Mobilization advance~₹900 cr, of which ~₹500 cr interest-bearing
Unbilled revenue~₹695 cr
Retention money~₹389 cr
Non-fund based limit utilization~75% of ₹5,000 cr limit
Capex in H1 FY26₹398 cr
Full year FY26 capex target~₹500 cr, including ~₹100 cr maintenance capex