Key Takeaways
- Revenue hit by weather and approvals, not demand: Revenue fell 12% YoY as an extended monsoon and slower-than-expected government approvals deferred billing, not because the order book shrank. Management still hopes to match last year's ~₹5,700 crores top line.
- Order inflow was the real disappointment: FY25-26 order inflow was very poor, blamed on election-related slowdown in project awards. The company targets closing the year with a ~₹4,000 crores order book and expects ₹7,000-8,000 crores of inflows in FY27.
- GMLR and VDCR bottlenecks are clearing now: Land for the GMLR shaft was acquired in August 2025, both TBMs are on site, and the VDCR general arrangement drawing was cleared by IIT just yesterday. These two large projects should start contributing revenue from Q4 and Q1 FY27 respectively.
- Margins are holding, debt is manageable: EBITDA margins are guided at 14-15% with no decline expected, and debt is seen settling at ₹600-700 crores even as term loans rise. Mobilization advances are already reducing.
- What to watch next quarter: Whether the ₹1,728 crores of L1 projects convert to order book by March, the pace of GMLR TBM lowering and capitalization, and any concrete award dates for the large pipeline of Mumbai and Delhi metro projects promised for early FY27.
Revenue & Execution Delays
- Monsoon disruption: Extended rains caused temporary site-level disruption, slower execution progress, and deferment of billing tied to milestone achievements across multiple projects. The impact was operational and time-related, not structural.
- Government approval bottlenecks: The VDCR project (₹2,500 crores) has executed only ₹100 crores because IIT approval for the general arrangement drawing took far longer than expected. Design submissions and soil investigation are still pending, so material revenue contribution will only begin in Q1 FY27.
- Seven-project package gridlock: Packages A-F, awarded to L&T, J. Kumar and others, could not even start ₹100 crores worth of work. These are interdependent projects where changes in one affect alignment of others, and the third-party IIT approval process took longer than anticipated. J. Kumar has completed 9-10 foundations on the Film City side near the highway.
- GMLR tree-cutting resolved: Tree-cutting permission required Supreme Court approval due to the area's reserved status. Approval was obtained, tree cutting was completed in one month, new plantation is ongoing, and the shaft is fully executed.
- No penalties on delays: Zero penalties have been incurred because all delays originated from the client side, not from J. Kumar's execution.
Nalin Gupta: "Such kind of things which we expect the project is given, we are mobilized, the drawings have been submitted, but it's a government process, that took time more than what we expected."
Project-Specific Updates
GMLR (Goregaon-Mulund Link Road)
- Land and variation: BMC gave a positive variation of ₹800 crores (J. Kumar's share ₹400 crores) as tunnel length increased by 600 meters. Land for the launching shaft was acquired in August 2025 after local adivasi opposition was resolved.
- TBM progress: Both tunnel boring machines have reached the job site. The first PCC (lean concrete where the TBM will be lowered) is being done, and lowering should begin by month-end. The project will now start generating a decent top line.
Nalin Gupta: "Today we are doing the first PCC, the lean concrete where the TDM will be lowered into the shaft. So by this month end, we should be starting lowering the TDM into the shaft. So it was a very quick and great job that the team has done."
VDCR (Versova-Dahisar Coastal Road)
- GAD cleared: The general arrangement drawing was cleared by IIT (third-party check) just yesterday. Changes in joints were required due to clashes between different elevated metros and flyovers being crossed, and a scope change is expected on the positive side.
- Revenue timing: Financial revenue contribution will come from Q1 FY27, not Q4.
Other Projects
- Chennai Elevated Corridor: ~9-10% financial progress, currently at foundation/substructure stage. Work is affected by sea and maritime board limitations, but the superstructure phase will not face these issues. Around two years more or less remain for completion.
- CIDCO Coastal Road (Kharghar to Nerul): Not started yet; some revenue is expected in FY26-27, but not in Q4.
- Mira-Bhayandar flyover: Management confirmed construction is as per client requirements with no flaws. The four-lane flyover drops to two lanes on the Bhayandar side due to land issues, and a 90-degree cut is an offset for future expansion. Metal crash barriers will be deployed before opening.
Nalin Gupta: "There is nothing which is wrongly constructed. It's a well-planned thing that has been done with future extension keeping in mind."
Order Book & Pipeline
- Current order book: ₹19,200 crores, with a 3-4 year execution timeline (ideally 3 years). 90% of the order book is already in the pipeline and generating revenue.
- L1 projects: ₹1,728 crores of L1 projects (Lucknow ₹1,206 crores + NBCC ₹522 crores) are expected to convert into the order book by March.
- FY27 pipeline: Management listed a large set of upcoming projects: Metro Line 8 (Golden Line), Metro Line 5 extension, Metro Line 10 for Mumbai; Delhi Metro DC06 and DC07 (~₹3,500 crores, two projects of ~₹1,700-1,800 crores each); Pune Metro (~₹1,000 crores); MSRDC and MMRDA elevated corridors and road projects; Ambernath-Kalyan-Ulhasnagar-Dombivali access control road (~₹10,000 crores); Nagpur-Gondia Shaktipeeth (~₹30,000 crores, EPC); CIDCO Metro Line 1A and 1B (~₹5,000 crores); MMRDA Uttan-Virar Coastal Road extension (~₹35,000-₹40,000 crores). All are expected to be awarded in FY27, starting from early next financial year.
- Bidding discipline: Management emphasized it is not aggressively bidding just for top line. The focus is on projects that add to the bottom line, with margins and PAT/EBITDA levels taking priority over revenue growth.
Nalin Gupta: "We want to keep our, you know, the horses under control and not to go aggressively bidding where we don't make bottom line and just for the heck of -- today, if I'm coming with some top line, where my margins are intact and where I'm able to grow at the similar profit margin and PAT and EBITDA levels, that is more acceptable than just increasing the top line and not making good bottom line."
Financials & Balance Sheet
- Interest cost: Increased from ₹39 crores to ₹44 crores QoQ despite debt reduction, because of mobilization advances taken. The average interest rate on mobilization advances is around 8%, with a range from 0% to 10%.
- Mobilization advance reduction: Reduced from ₹900 crores in Q2 to ₹800 crores in one quarter. Certain projects have already started recoveries, and some old projects are at the fag end.
- Other income: Rose to ₹21 crores in Q3 (vs a normal ₹9-10 crores) because ₹22,000 crores of projects require bank guarantees, necessitating fixed deposits that earn interest. This range will persist.
- Working capital: Expected to be 115-120 days as work progress increases.
- Capex: ₹200-300 crores expected next year.
- TBM capitalization: Both TBMs have been received and will start getting capitalized once lowered into the shaft, likely in Q1 or Q2. Management declined to provide an exact quarterly depreciation impact when asked, saying they need to work it out; depreciation will be charged on cost incurred till the date of operation.
- Fund raise (QIP): Only an enabling resolution was passed for ₹800 crores; there are no immediate plans to raise funds. Management may renew the enabling resolution for the next financial year and will take a call if financial requirements arise from good order inflows.
- Promoter pledge: Management denied any increase in pledging, stating that 80 lakh shares have been pledged for many years and the number is constant. They are working towards getting it released.
Margins
- Current and guided margins: All secured jobs carry similar margins of 14% to 15%. No decline is expected for FY26 and FY27.
- Medium-term target: A 15-16% margin improvement over the next 2-3 years remains the target. Next year, management is looking at similar or better margins with no degrowth.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 revenue | Maintain or surpass last year's top line of ~₹5,700 crores (implies flat Q4 YoY) | FY26 exit |
| FY27 revenue growth | Around 15% growth | FY26-27 |
| EBITDA margin | 14-15%, no decline expected | FY26 and FY27 |
| FY26 order inflow | Close with order book of around ₹4,000 crores | By end of March 2026 |
| FY27 order inflow | Around ₹7,000 to ₹8,000 crores of order book | FY26-27 |
| Debt level | ₹600-700 crores expected | Ongoing |
| L1 conversion | ₹1,728 crores of L1 projects to convert into order book | By March 2026 |
| VDCR revenue start | Financial revenue contribution to begin | Q1 FY27 |
| Capex | ₹200-300 crores | FY27 |
| Margin improvement target | 15-16% | Over next 2-3 years |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Revenue from operations | ₹1,311 cr, moderated 12% YoY vs ₹1,487 cr in Q3 FY25 |
| Revenue from operations (9M FY26) | ₹3,561 cr, vs ₹4,061 cr in 9M FY25 |
| EBITDA | ₹188 cr, moderated 14% YoY vs ₹219 cr in Q3 FY25 |
| EBITDA (9M FY26) | ₹599 cr, grew 1% YoY vs ₹591 cr in 9M FY25 |
| EBITDA margin | 14.3%, vs 14.7% in Q3 FY25 |
| EBITDA margin (9M FY26) | 14.5%, vs 14.6% in 9M FY25 |
| PAT | ₹83 cr, moderated 17% YoY vs ₹100 cr in Q3 FY25 |
| PAT (9M FY26) | ₹277 cr, flat YoY vs ₹277 cr in 9M FY25 |
| PAT margin | 6.3%, vs 6.7% in Q3 FY25 |
| FY26 revenue guidance | ~₹5,700 cr, flattish YoY vs FY25 |
| FY27 revenue growth guidance | ~15% over FY26 |
| EBITDA margin guidance (FY26 and FY27) | 14% to 15% band |
| Total order book | ₹19,212 cr as of 31 Dec 2025 |
| Order inflow (9M FY26) | ~₹515 cr |
| L1 projects (not yet in order book) | ₹1,728 cr |
| Net debt | Negative ₹250 cr (cash positive) as of 31 Dec 2025 |
| Debt-equity ratio | 0.2x, reduced from 0.23x in FY25 |
| Working capital days (9M FY26) | 103 days, vs 112 days for FY25 |
| Mobilization advance outstanding | ₹800 cr as of Dec 2025, interest-bearing portion ₹650 cr |
| Unbilled revenue | ₹600 cr |
| Capex (9M FY26) | ₹433 cr, full year FY26 expected ~₹533 cr |
| Tax rate (annual) | ~26.5% |