JK Lakshmi Cement Ltd Q1 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/c1itdz3vyl56udcv9cl4485o.pdf

Key Takeaways


Accounting Change: UCWL Conversion Model


Costs & Margins

Management: "Not only the coal is a scarcity commodity in India but the wagons are also not being available."

Pricing & Demand Environment

Management: "I would not hesitate to say that the price fall would have been in the range of Rs. 10 a bag. Even now I don't think the prices have one can be very sure that they have stabilized"

Expansion & Capacity Vision


Balance Sheet & Corporate Structure

Management: "Moment we exhaust this MAT Guide Entitlement which will be maybe 2 to 3 years' time depending on the actual profitability in these 3 years then JK Lakshmi can also graduate to 25% and that will be the opportune time for us to collapse the structure and merge the two entities."

Guidance & Commitments

CommitmentSpecificsTimeline
Standalone net debtBecome debt-free on standalone net-debt basisEnd of FY23
Power and fuel cost peakQ2 FY23 to see peak; softening has startedQ2 FY23
Power and fuel cost QoQIncrease ~20% QoQ in Q2 FY23Q2 FY23
UCWL expansion completionClinker by Q3 (Dec); phases in 2Q and 4Q2024
UCWL balance CAPEX₹1,300 crores spread over next 2 yearsFY23–FY25
Full-year volume growth7% to 8% target, dependent on demand and fuel pricesFY23
Full-year profitabilityEndeavor to reach ₹1,000 per ton, dependent on coal and pet coke pricesFY23
Trade share increaseIncrease by 4% to 5%FY23
Group mergerMerge JK Lakshmi and UCWL after MAT credit exhaustion2–3 years
Amethi grinding unit volume~6 lakh tons cement in first 12 monthsFirst 12 months of operation

Key Metrics

MetricQ1 FY23
Standalone cement volume26.91 lakh tons, plus 0.9 lakh tons clinker, total 27.86 lakh tons
Consolidated cement volume29.37 lakh tons, plus 0.95 lakh tons clinker, total 30.32 lakh tons
Consolidated revenue per ton~₹5,400, up from ~₹4,900 last year
Consolidated cost per ton~₹4,900, up from ~₹4,300 last year
Power and fuel cost per ton₹11,700, up from ₹9,000 earlier
Power and fuel cost Q2 FY23 outlook~+20% increase expected, peak anticipated in Q2
Fuel mix46% coal, 41% pet coke, 13% alternate fuel
Domestic coal share7% to 8% of coal mix
Standalone employee cost₹92 crores quarterly run rate, normative 10-12% annual increase
Consolidated other expenses₹207 crores, vs ₹149 crores in Q4 FY22, partly volume-linked
Consolidated net debt₹662 crores, total debt ₹1,800 crores, cash ₹1,150 crores
Standalone net debt₹20 crores (per analyst's math), total debt ~₹920 crores, cash ₹900 crores
Blended cement mix67%, up from 65% in Q4 FY22
Trade mix56%
Premium cement share of total sales14% (North only)
Non-cement revenue₹118 crores, including RMC of ~₹55 crores
Lead distance393 km
UCWL expansion CAPEX spent~₹350 crores of total ₹1,650 crores
UCWL clinker line timelineQ3 FY24 (December)
Amethi grinding unit expected volume~6 lakh tons in first 12 months, capacity ~0.1 crore tons per year
MAT credit entitlement~₹250 crores, expected to exhaust in 2-3 years
Full-year volume growth target7% to 8% (prior guidance)
Full-year profitability target₹1,000 per ton (prior guidance)