Key Takeaways
- Seasonal pain, cost squeeze, cautious recovery bet: Q2 volumes grew just 5% YoY (vs industry 9–10%) as the worst monsoon in decades hit the company’s three core geographies, while fuel costs spiked to INR1.82/kcal and power costs rose to ₹6.24/unit. Management expects demand and pricing to improve post-Diwali.
- Fuel cost is the near-term villain: Q3 fuel cost is guided to INR2/kcal, Q4 to INR2.15–2.2/kcal if current conditions persist, driven by rising coal and petcoke prices and domestic coal auctions clearing above 200%. Mitigation via fuel mix changes has process limits.
- Capacity ambition reset for balance-sheet discipline: The FY30 target has been revised down from 3 crore tons to 2.5 crore tons, with a firm commitment that net debt to EBITDA will not cross 3.5x. The Durg, Madhubani and Prayagraj projects remain on track for March 2028.
- Pricing power is returning, slowly: October saw a ~INR10/ton increase on average vs Q2; management expects another INR10/ton in November and INR10–15/ton in December as the season turns favourable.
- What to watch next quarter: Whether the promised INR2/kcal fuel cost materialises and whether post-Diwali price hikes stick, the pace of the INR1,460 crores working-capital release, and any update on the Northeast project incentives that management declined to discuss.
Volume & Demand
- Monsoon hit hard: Q2 volumes grew only 5% YoY against an industry growth of 9–10%, with H1 at 7%. The company’s three major geographies (Gujarat, Rajasthan, Chhattisgarh) suffered the worst rainfall, and Chhattisgarh was particularly inundated.
- H2 recovery expected: Management is confident of matching industry growth of 7–8% in the coming six months, citing historical H2 strength in both demand and pricing across FY25 and FY26. Post-Diwali, there are no major festivities or rain to disrupt construction activity.
- Trade share steady, trade growth strong: Trade share has held at 58–59% for three quarters; trade volume growth in H1 was 14–15%, outpacing overall growth and reflecting the company’s long-term channel focus.
- Premium product share at 27%: Management expects this to remain around 27–28%, with 30% as an aspirational target but ~28% seen as the likely level. Premiumisation is also being used to anchor mother product pricing and narrow the gap with the market leader.
Arun Shukla: “I am hopeful that part of this cost increase definitely we are going to recover from the market. We are going to see good demand and also price momentum going forward, because after Diwali, there is no, I would say, impediment in terms of external factors.”
Costs & Margins
- Fuel cost spike: Q2 fuel cost rose to INR1.82 per 1,000 kcal from INR1.54 in Q1, driven by coal and petcoke. The company tried to mitigate this by changing the fuel mix at its North integrated plant, but ash content and sulfur constraints in the pyro process limit how far that can go.
- Power cost up on shutdowns and rain: Blended power cost rose to ₹6.24/unit in Q2 from ₹5.52 in Q1, because planned shutdowns (scheduled in the low-demand monsoon months) raised auxiliary consumption and lower solar output during the rainy season reduced renewable contribution.
- Domestic coal also getting dearer: Recent auction prices have cleared at more than 200%, adding pressure even on the domestic coal basket. Management hopes the geopolitical situation may settle things out.
- Q3 cost relief, but not on fuel: Power costs should improve as solar output rises post-rainy season, shutdowns end, and WHRS and operating leverage kick in. Fuel and bag costs remain the uncertain variables.
- Non-cement margin thin: The blended margin on RMC, AAC blocks and other non-cement revenue was 5% in Q2.
Arun Shukla: “Q3, we see around INR2, and Q4 around INR2.15–INR2.2 if situation is going to persist like this.”
Pricing & Competitive Position
- Price increases underway: September saw some increases, particularly in non-trade. October brought increases in both trade and non-trade, averaging about INR10/ton over Q2. Management expects another INR10/ton in November post-Diwali and around INR15/ton in December.
- Gap with market leader narrowing in some markets: The pricing gap has reduced in East and West Gujarat but remains higher in some North markets. The company is using premiumisation (selling more premium products) to anchor the mother product price by pitching its premium product in the market.
- Trade-first strategy unchanged: Even though non-trade is currently as good as trade, or better in some markets, management’s focus remains on trade for its long-term consistency and stability.
Arun Shukla: “We are not spreading ourselves thin. We are consolidating ourselves in North, we are consolidating in East, we have consolidated in West also. ... Rather than looking at competition which is coming, we are consolidating our position and trying to place in the market in a way that we are going to really face them with the capacity, channel, and our selling strategy.”
Expansion Projects
| Project | Status | Timeline |
|---|---|---|
| Durg (clinker + WHRS) | >50% civil complete; fabrication 20–25% done; all contractors mobilised | March 2028 |
| Madhubani, Bihar (split grinding) | All clearances in place; 80% piling done; silo work progressing | March 2028 |
| Prayagraj (split grinding) | All clearances incl. environment clearance in place; boundary wall done; equipment ordered; contractors mobilised | March 2028 |
| Mejia, West Bengal (replaces Patratu) | Land and clearances already available; reconfigured after Patratu faced delays and cost challenges under the Chota Nagpur Tenancy Act | FY29–30 |
| Northeast plant | Equipment ordering begun; commissioning targeted around March 2029; capex ~INR1,800 crores | March 2029 |
- Patratu to Mejia shift: The Patratu (Jharkhand) site faced delays and cost challenges due to the Chota Nagpur Tenancy Act, so capacity was reconfigured to Mejia (West Bengal) where land and clearances were already available. Mejia is expected to be much quicker than Patratu and Raebareli.
- Northeast as future supply hub: Management sees the Northeast plant eventually becoming a supply point for eastern India (North Bengal, Bihar) after seven to ten years, and Mejia could take clinker from the Northeast going forward, creating synergy.
- Northeast incentives undisclosed: Management declined to discuss what incentives have been approved for the Northeast expansion on the call, offering a separate discussion instead.
Balance Sheet & Capital Allocation
- Capacity target revised down for discipline: The FY30 target has been cut from 3 crore tons to 2.5 crore tons. Management was explicit that maintaining balance-sheet discipline is more important than hitting a volume figure, and net debt to EBITDA will not be allowed to cross the prudential norm of 3.5x.
- Net debt peak: Expected to peak at around ₹2,500 crores by end of FY27.
- Capex trajectory: INR1,500 crores in FY27 (of which INR1,000 crores is for Durg, with the remainder for land acquisition at Kutch and Nagaur, the Northeast project, and normal capex), then INR2,000 crores for each of the next two years.
- Working capital to release: INR1,460 odd crores got blocked in working capital in H1; management expects this to release in H2.
- ₹130 crores receivable: No provision has been made; management believes it has a good case for recovery. [12–13]
Sudhir Bidkar: “We wanted to make sure that our balance sheet does not go haywire. ... maintaining balance sheet discipline is more important than just reaching a figure of 30 by 30.”
Green Power & Sustainability
- Green power share to inch up: Expected to rise to 49% from 48% as additional solar capacity comes online and production improves post-rainy season.
- Solar capacity additions underway: Udaipur (40 MW), Durg (20–25 MW) and Sirohi (40 MW) are in progress. Partial benefit is expected in Q4 FY27; the full advantage will not accrue this year.
- CC ratio rose: The clinker-to-cement ratio increased to 1.48 from 1.43 in Q1 because blended cement share went up to a higher percentage.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Fuel cost | INR2/kcal in Q3; INR2.15–2.2/kcal in Q4 if current conditions persist | Q3 and Q4 FY27 |
| Volume growth | Match industry growth of 7–8% | H2 FY27 |
| Price increases | INR10/ton in November, INR10–15/ton in December (on top of ~INR10/ton in October vs Q2) | Nov–Dec 2025 |
| Net debt to EBITDA | Will not cross 3.5x | Ongoing |
| Net debt peak | ~₹2,500 crores | End of FY27 |
| Durg, Madhubani, Prayagraj completion | All three projects complete | By March 2028 |
| Northeast plant commissioning | Commissioning targeted | Around March 2029 |
| Mejia plant commissioning | Commissioning along with Northeast | FY29–30 |
| Capacity target | 2.5 crore tons (revised from 3 crore tons) | By FY30 |
| Green power share | Inch up to 49% | As solar additions come online |
| Working capital | Release of INR1,460 crores blocked in H1 | H2 FY27 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue | Not stated |
| Operating EBITDA per ton | ₹510–520 (per an analyst's math, not confirmed by management) |
| Volume growth | 5% YoY |
| H1 FY27 volume growth | 7% YoY |
| Fuel cost per 1,000 kcal | ₹1.82, up from ₹1.54 in Q1 FY27 |
| Q3 FY27 fuel cost outlook | ~₹2.00 per 1,000 kcal |
| Q4 FY27 fuel cost outlook | ₹2.15–2.20 per 1,000 kcal, if current situation persists |
| Blended power cost | ₹6.24 per unit, up from ₹5.52 in Q1 FY27 |
| Trade share | 58–59%, stable for last three quarters |
| Premium product share | 27% of sales |
| Green power share | 48%, expected to inch up to 49% |
| Lead distance | 363 km |
| Clinker conversion ratio | 1.48, up from 1.43 in Q1 FY27 |
| Non-cement revenue | ₹183 cr, blended margin 5% |
| Net debt to EBITDA ceiling | 3.5x, management's stated prudential norm |
| FY27 capacity | 1.8 crore tons (1.8 crore tons) |
| FY30 capacity target | 2.5 crore tons, revised from 3 crore tons |