JK Lakshmi Cement Ltd Q4 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/phis9l4awhk15i1v20lrnazc.pdf

Key Takeaways


Demand & Pricing Environment

Shukla: "The Green Plus product which we have launched has been received quite well in all markets where we operate. So this is good news for the organization."

Cost Structure & Efficiency Levers


Capacity Expansion & Projects

ProjectStatusTimeline
Surat doubling (+0.14 cr tons)First phase under trial, soon to be commissionedHalf in June, remainder around September
Durg (clinker 2.3 mtpa + grinding)Public hearing for plant and mines completed; awaiting MoEF environment clearance; tenders floated but equipment orders not yet placedQ3 FY27 (first phase); second phase in FY28
Prayagraj grinding stationLand acquired; applied for tour; next step is public hearing~1-1.5 years
Madhubani grinding stationLand acquired; public hearing already doneNot specified
Conveyor beltBoard recommended; final ministry approval awaited; Rs. 70-80 cr additional capex; ~8-9 months to commission once approvedExpected by March '26
Gujarat/Kutch limestone minesLand acquisition in process; plant is 3-4 years away3-4 years
Management: "Even if Northeast, as I mentioned, is delayed... without Northeast also we will be able to reach 30/30 as of now as we speak."

Northeast Project (Agrani Cement): The Contingency

Management: "We are putting our foot down at the cost of even they are threatening to abandon the project and all that... we are not going to dance to their tunes the way their style of working is there, which to our utter surprise we found is not the style we are used to operate in other states."

Portfolio & Brand


Financial & Corporate Updates


Guidance & Commitments

CommitmentSpecificsTimeline
Volume growthAt least 10% vs industry growth of ~6-6.5%FY26
Cost reductionRs. 100-120 per ton12-18 months (spanning FY26 and FY27)
Renewable energy shareReach ~52-53% (from 48%)End of FY26
Thermal substitution rateAverage 12% (from 9% in FY25)FY26
Lead distanceReduce back to ~380 km averageImplied within the 12-18 month cost-reduction window
Surat expansionFull commissioningHalf in June, remainder around September
Durg expansion (first phase)0.23 cr tons clinker + 0.24 cr tons grindingQ3 FY27
Conveyor beltCommissioning, subject to ministry approvalExpected by March '26
UCL amalgamationNCLT approval and closureSooner than December
3 crore tons capacityAchievable with or without Northeast, via Nagor, Kutch and inorganic routesFY30
CAPEX~Rs. 1,300 crFY26
CAPEXRs. 1,000 cr (JK Lakshmi) + Rs. 800 cr (Northeast) = Rs. 1,800 crFY27

Key Metrics

MetricQ4 FY25
Revenue₹151 cr non-cement revenue
RMC revenue₹75 cr
EBITDA margin (non-cement)3%
Fuel cost per kcal1.53 (consolidated)
Blended cement share65%
Green power consumption50%
Lead distance393 km, up 12 km sequentially
Trade volume60%
Premium product share25% (consolidated)
Clinker-to-cement ratio1.44
Volume growth guidance (FY26)~10%
Industry demand growth estimate (FY26)6.5% to 7%
Cost reduction target₹100–120 per ton over 12–18 months
Renewable energy share target (FY26)~52% (from 48% in FY25)
Thermal substitution rate target (FY26)~12% (from 9% in FY25)
CAPEX FY25 (actual)~₹550 cr (JKLC ₹300 cr, UCWL ₹250 cr) plus ~₹50 cr Northeast
CAPEX FY26 (expected)~₹1,300 cr (JKLC ₹1,100 cr, Northeast ₹150 cr, Udaipur ₹40–50 cr)
CAPEX FY27 (expected)~₹1,800 cr (JKLC ₹1,000 cr, Northeast ₹800 cr)
Consolidated cash and equivalents₹1,150 cr as of March
Non-current financial assets₹408.9 cr, primarily bank FDs over 1 year
Surat expansion0.14 cr tons, commissioning half by June, remainder by September
Durg expansion0.23 cr tons clinker, 0.24 cr tons grinding, commissioning by Q3 FY27
Northeast project consideration paid₹130 cr of ₹325 cr total
UCL amalgamation share issuance~0.65 cr shares (4 for every 100 UCL shares)
Capacity target3 cr tons by FY30