Key Takeaways
- Cost storm meets weak pricing: Fuel costs surged ~30-40% QoQ, yet company realization grew only 1% as intense competition blocked meaningful price hikes. EBITDA per ton fell to ~₹730, and management declined to give FY27 EBITDA guidance.
- Demand is holding, barely: FY26 industry demand grew ~7%, but March moderated to ~5% on geopolitical uncertainty. April was better; May showed green shoots only after mid-month. FY27 industry growth pegged at ~6%.
- Capex cycle is locked in: Durg expansion on track for FY28 completion, Assam to follow in FY29, Kutch by FY30. FY27 capex guided at ₹1,500-1,700 crores, FY28 at ~₹2,000 crores. Net debt will peak before Durg EBITDA kicks in.
- Gap with leaders narrowing, slowly: Management expects to close another ₹50-75/ton of the realization gap in FY27 through brand strategy (Green+, LC3) and product mix, but the ₹400-500 gap remains wide.
- What to watch next quarter: Whether the ₹300/ton energy cost hit landing in Q2 can be passed through, the pace of Surat ramp-up beyond 60%, and any concrete EBITDA per ton guidance when management updates next quarter.
Cost Pressures & Margin Squeeze
- Fuel costs spiked sharply: Pet coke rose ~40% QoQ to ~$160/ton; global coal up ~30% QoQ, driven by the Middle East conflict. Energy costs alone are expected to add at least ₹300/ton, with packaging adding another ₹80-100/ton.
- Cost inflation is phased: Management expects ₹100-130/ton of cost inflation in Q1, with the larger ₹300/ton energy impact landing in Q2. If the geopolitical situation persists, operating costs could rise further.
- Mitigation is partial: The company is altering its Northern plant fuel mix (pet coke vs coal proportion), improving renewable energy share, and scaling TSR. These measures will contain cost increases only "to an extent."
- EBITDA per ton collapsed: Exited Q4 at ~₹730 vs an earlier run-rate near ₹1,000. Management called ₹1,000/ton "the anchor" and an ambition, but noted even leaders have seen declines. No FY27 EBITDA per ton guidance was given, with management citing external uncertainty.
- April inventory helped: In April, the company was able to pass on cost increases thanks to inventory held, but this buffer is temporary.
Shukla: "I'm confident that we'll be able to kind of -- since demand will support, we'll be able to recover or pass on majority of the cost increase which we are going to have. This is what I kind of foresee as of today. But that depends on a lot of external factors, right, how demand behaves and how competitive intensity is."
Pricing & Realization
- Realization barely moved: Company realization grew only 1% QoQ despite healthy non-trade pricing and a 42% non-trade share. Price increases were lower in the company's core geographies (North, West, small part of East) vs other zones.
- Non-trade recovered; trade lagged: Non-trade prices partially recovered after slipping below GST pass-through levels in the preceding quarter. Trade prices are inching up but not commensurately with the cost increases foreseen.
- Geography is a headwind: East presence is limited to Chhattisgarh, the lowest-price zone in the East. Gujarat initially saw no price increases at all. Substantial capacity addition and intense competition restricted meaningful hikes across markets.
- Brand strategy as a pricing lever: The company launched Green+ (a rejuvenated legacy brand) and LC3 (Lime Calcined Clay Cement, positioned as green, durable, and as good as OPC). The stated strategy is "right product, right price, right market" to improve realization.
Shukla: "those price increases are not at all kind of [inaudible] with the cost increase which we are foreseeing."
Demand Environment
- FY26 closed decently: Pan-India demand grew ~7% for the full year (vs 5% in FY25). Q4 demand was ~6-6.5% with 17% QoQ volume growth. Demand was strong December through February (8-10%) but moderated to ~5% in March amid weak sentiment from the Middle East conflict.
- April-May mixed: April demand was better. May began sluggish due to labourers returning from elections and geopolitical uncertainty, but management saw "green shoots" from May 15 onwards. Overall Q1 expected to grow in alignment with projections.
- FY27 outlook cautious: Industry volume growth pegged at ~6%, with capacity addition estimated at 4.5-5 crore tons. The demand outlook suggests a slowdown, with pricing power staying weak despite sector consolidation.
- Company to outgrow industry: Management expects to grow faster than the 6% industry estimate, citing headroom in Surat (60%+ utilization, ramping toward 70%+), Udaipur, and Cuttack. No new capacity addition this financial year; focus is on sweating existing assets.
Shukla: "April demand was better. May when we started, there was sluggishness... But May 15 onwards, I see a little bit green shoots in demand in the month of May."
Capacity Expansion & Growth Projects
- Durg is the near-term anchor: Clinker and grinding units are on track for completion by end of FY28. Capex phasing: ₹1,500-1,700 crores in FY27, ~₹2,000 crores in FY28, and ₹1,000-1,500 crores in FY29.
- Assam follows Durg: The Northeast project will proceed alongside Durg, targeted for FY29 (one year after Durg). Size is not firmed up but may be slightly higher than 1.5 MTPA. JK Lakshmi secured 2 of 3 Assam mines under the auction route with 25 crore tons of reserves after the earlier AMDCL MDO contract was cancelled.
- Kutch by FY30: The Kutch project is confirmed for completion by FY30. The Nagaur project has been delayed due to land acquisition issues and the Aravalli Supreme Court decision; Kutch will come ahead of it.
- 30MT target intact: Management is "reasonably confident" of achieving 3 crore tons by 2030. After Durg, the plan is to add 9MT over FY27-FY30.
- Surat ramp-up ahead of plan: Commissioned end of September 2025, utilization already exceeds 60%, well ahead of the typical 18-24 month ramp-up curve. Expected to reach 70%+ this year.
- Clinker headroom exists: Without adding clinker capacity, the company can push cement volumes from ~1.4 crore tons to ~1.42 crore tons by improving the blended cement ratio (62% to 65%), increasing clinker utilization (94% to 97-98%), and reducing clinker sales (7.5 lakh tons last year).
Balance Sheet & Capital Allocation
- Net debt will rise before it falls: With large capex underway, net debt will increase. Management acknowledged it "will peak out" and return to normative levels once EBITDA from the Durg expansion starts flowing, but declined to quantify the peak or the timeline.
- AMDCL recovery uncertain in timing: ₹130 crores is reported in other non-current assets from the cancelled AMDCL contract. The next High Court hearing is in July. Management is "sure it is recoverable" but cannot say when.
- NECEM acquisition nearly done: Total consideration of ~₹19 crores plus takeover of past liabilities. Past liabilities of ₹12.5 crores settled in March. ₹1.5 crores paid for shares; ₹10 crores non-compete fee payable after full consummation. ₹3.5 crores of ₹7.5 crores capital infusion completed. Transaction expected to close entirely this quarter.
- Intangible asset write-down: ₹325 crores knocked off intangible assets due to derecognition of mining rights after the AMDCL cancellation.
Bidkar: "We'll not get -- we are not saying that it will come in July. We are saying that the next hearing is in July. [Inaudible] today. I don't know when it will come, but we are sure it will. That's why we are sure it is recoverable."
Strategy: Brand, Adjacencies & Efficiency
- Green+ and LC3 launched: Green+ rejuvenates a legacy brand to improve pricing position. LC3 is a green cement positioned as durable and equivalent to OPG, with plans to ramp up volume at the right price.
- Adjacent building materials push: AAC blocks are growing as planned. Tile adhesives and clustering solutions are growing well with high margins. RMC has not grown as planned because management consciously prioritized higher-margin products. The strategy is explicitly to offer customers a portfolio of building materials, and the company may explore other products in the future.
- Steel rods pilot at nascent stage: Management has partnered with manufacturers to pilot selling steel rods under the JK Lakshmi brand, leveraging distribution network synergy. This is at a very early stage; the company is not entering manufacturing or distribution. No quantum of income was disclosed.
- Gap with leaders narrowing: Management expects to reduce the realization gap by at least another ₹50-75/ton in FY27. The gap is measured on grey cement EBITDA vs grey cement, excluding other businesses, and without accrual-based incentive recognition.
- Digital and sustainability levers: AI/ML deployment in pyro-process and grinding aims to improve efficiency and reduce cost. Renewable energy share is planned to go beyond the current 46%. TSR Phase 1 at Sirohi is complete; Phase 2 is contemplated but not finalized due to limited alternate fuel availability around that plant.
Shukla: "Definitely, our effort or our thought or the strategy is to go to adjacent building material for sure, because that -- we want to give our customers portfolio of products."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Industry volume growth | ~6% for FY27 | FY27 |
| Company volume growth | Higher than industry (~6%) | FY27 |
| Durg expansion completion | Clinker + grinding units | End of FY28 |
| Assam/Northeast project | Clinker + grinding, size slightly above 1.5 MTPA | FY29 (one year after Durg) |
| Kutch project | For sure by FY30 | FY30 |
| 30MT cement capacity | Reasonably confident; on course | By 2030 |
| FY27 capex | ₹1,500-1,700 crores | FY27 |
| FY28 capex | Close to ₹2,000 crores | FY28 |
| Gap reduction with leaders | At least another ₹50-75/ton | FY27 |
| Surat utilization | 70%+ | This year (FY27) |
| NECEM acquisition consummation | Entirely complete | This quarter |
| Cost inflation (energy) | At least ₹300/ton; ₹100-130/ton in Q1, rest in Q2 | Q1-Q2 FY27 |
| AMDCL recovery hearing | Next hearing in High Court | July |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue | Not stated (non-cement revenue ₹169 cr, RMC revenue ₹82 cr) |
| Cement volume growth | ~17% QoQ |
| EBITDA per ton | ₹730-odd (quarterly) |
| Blended cement mix | 62% (Q4 and FY26) |
| Clinker-to-cement ratio | 1.44 |
| Clinker production | 24.72 lakh tons |
| Clinker sales | 2.2 lakh tons |
| Power cost per unit | 5.79 (vs 5.37 in Q3) |
| Renewable energy share | 46% (at year-end) |
| Non-cement revenue | ₹169 cr |
| RMC revenue | ₹82 cr |
| AAC block revenue | ₹59 cr |
| Non-cement margin | 4% |
| Capacity utilization (FY26) | 73% (on 1.77 cr tons full-year capacity) |
| Clinker utilization (FY26) | ~93% |
| Surat grinding unit utilization | >60% (ramp-up ahead of 18-24 month plan) |
| Durg project capex incurred to date | ~₹500 cr (including railway siding) |
| NECEM past liabilities settled | ~₹12.5 cr (settled March 2026) |
| AMDCL mining rights derecognized | ₹325 cr (intangible assets reduced from ₹329 cr to ₹5 cr) |
| FY27 capex guidance | ₹1,500 cr to ₹1,700 cr |
| FY28 capex guidance | ~₹2,000 cr |
| FY29 capex guidance | ₹1,000 cr to ₹1,500 cr |
| 30MT capacity target by 2030 | On track, 9MT addition over FY27-FY30 after Durg |
| Durg expansion timeline | End of FY28 (clinker + grinding units) |
| Northeast project timeline | One year after Durg (FY29) |
| Kutch project timeline | By FY30 |
| Q1 FY27 expected energy cost increase | ₹100 to ₹130 per ton (pure cost inflation, before price pass-through) |
| Full energy cost increase expected | ₹300 per ton (likely by Q2 FY27) |
| Packaging cost increase expected | ₹80 to ₹100 per ton |
| Pet coke price increase QoQ | ~40% to ~$160/ton |
| Global coal price increase QoQ | ~30% |
| Diesel/petrol price hike impact on logistics | ~₹15 to ₹16 per ton (on ₹4/litre increase) |
| Gap reduction with leaders targeted for FY27 | At least ₹50 to ₹75 per ton |
| Pan-India cement demand growth FY26 | ~7% to ~48 crore tons |
| Q4 FY26 pan-India demand growth | ~6% to 6.5% |
| Pan-India capacity utilization FY26 | ~69% (marginally lower YoY) |
| Annual capacity addition FY26 | 6.4 crore tons (highest ever) |
| National installed capacity (end Mar 2026) | 71.2 crore tons |
| FY27 capacity addition estimate | ~4.5 to 5 crore tons |
| FY27 cement demand growth outlook | ~6% |
| Assam mines secured under auction | 2 mines, reserves of ~25 crore tons |