JK Lakshmi Cement Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/eruu21to50ghaynpr2slz391.pdf

Key Takeaways


Cost Pressures & Margin Squeeze

Shukla: "I'm confident that we'll be able to kind of -- since demand will support, we'll be able to recover or pass on majority of the cost increase which we are going to have. This is what I kind of foresee as of today. But that depends on a lot of external factors, right, how demand behaves and how competitive intensity is."

Pricing & Realization

Shukla: "those price increases are not at all kind of [inaudible] with the cost increase which we are foreseeing."

Demand Environment

Shukla: "April demand was better. May when we started, there was sluggishness... But May 15 onwards, I see a little bit green shoots in demand in the month of May."

Capacity Expansion & Growth Projects


Balance Sheet & Capital Allocation

Bidkar: "We'll not get -- we are not saying that it will come in July. We are saying that the next hearing is in July. [Inaudible] today. I don't know when it will come, but we are sure it will. That's why we are sure it is recoverable."

Strategy: Brand, Adjacencies & Efficiency

Shukla: "Definitely, our effort or our thought or the strategy is to go to adjacent building material for sure, because that -- we want to give our customers portfolio of products."

Guidance & Commitments

CommitmentSpecificsTimeline
Industry volume growth~6% for FY27FY27
Company volume growthHigher than industry (~6%)FY27
Durg expansion completionClinker + grinding unitsEnd of FY28
Assam/Northeast projectClinker + grinding, size slightly above 1.5 MTPAFY29 (one year after Durg)
Kutch projectFor sure by FY30FY30
30MT cement capacityReasonably confident; on courseBy 2030
FY27 capex₹1,500-1,700 croresFY27
FY28 capexClose to ₹2,000 croresFY28
Gap reduction with leadersAt least another ₹50-75/tonFY27
Surat utilization70%+This year (FY27)
NECEM acquisition consummationEntirely completeThis quarter
Cost inflation (energy)At least ₹300/ton; ₹100-130/ton in Q1, rest in Q2Q1-Q2 FY27
AMDCL recovery hearingNext hearing in High CourtJuly

Key Metrics

MetricQ4 FY26
RevenueNot stated (non-cement revenue ₹169 cr, RMC revenue ₹82 cr)
Cement volume growth~17% QoQ
EBITDA per ton₹730-odd (quarterly)
Blended cement mix62% (Q4 and FY26)
Clinker-to-cement ratio1.44
Clinker production24.72 lakh tons
Clinker sales2.2 lakh tons
Power cost per unit5.79 (vs 5.37 in Q3)
Renewable energy share46% (at year-end)
Non-cement revenue₹169 cr
RMC revenue₹82 cr
AAC block revenue₹59 cr
Non-cement margin4%
Capacity utilization (FY26)73% (on 1.77 cr tons full-year capacity)
Clinker utilization (FY26)~93%
Surat grinding unit utilization>60% (ramp-up ahead of 18-24 month plan)
Durg project capex incurred to date~₹500 cr (including railway siding)
NECEM past liabilities settled~₹12.5 cr (settled March 2026)
AMDCL mining rights derecognized₹325 cr (intangible assets reduced from ₹329 cr to ₹5 cr)
FY27 capex guidance₹1,500 cr to ₹1,700 cr
FY28 capex guidance~₹2,000 cr
FY29 capex guidance₹1,000 cr to ₹1,500 cr
30MT capacity target by 2030On track, 9MT addition over FY27-FY30 after Durg
Durg expansion timelineEnd of FY28 (clinker + grinding units)
Northeast project timelineOne year after Durg (FY29)
Kutch project timelineBy FY30
Q1 FY27 expected energy cost increase₹100 to ₹130 per ton (pure cost inflation, before price pass-through)
Full energy cost increase expected₹300 per ton (likely by Q2 FY27)
Packaging cost increase expected₹80 to ₹100 per ton
Pet coke price increase QoQ~40% to ~$160/ton
Global coal price increase QoQ~30%
Diesel/petrol price hike impact on logistics~₹15 to ₹16 per ton (on ₹4/litre increase)
Gap reduction with leaders targeted for FY27At least ₹50 to ₹75 per ton
Pan-India cement demand growth FY26~7% to ~48 crore tons
Q4 FY26 pan-India demand growth~6% to 6.5%
Pan-India capacity utilization FY26~69% (marginally lower YoY)
Annual capacity addition FY266.4 crore tons (highest ever)
National installed capacity (end Mar 2026)71.2 crore tons
FY27 capacity addition estimate~4.5 to 5 crore tons
FY27 cement demand growth outlook~6%
Assam mines secured under auction2 mines, reserves of ~25 crore tons