JSW Energy Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/dirtv3oems07hboflrbcfozx.pdf

Key Takeaways


Capacity Build-Out & the 30 GW Target

Sharad Mahendra: "With this, India's total thermal capacity in FY32 should reach close to 300 GW."

Generation Performance & Merchant Market


PPA Environment & Bidding Strategy

Pritesh Vinay: "We have a very poor track record of calling something like this out. We would not trust our views on this, right, on a lighter note."

Supply Chain & Manufacturing Integration

Sharad Mahendra: "There definitely has been constraints in terms of timely supplies to meet the PPA timelines, from the existing suppliers for boiler turbine generator."

Financial Position & Returns

Sharad Mahendra: "Mid-to-high-teen IRR is our hurdle rate that has to be maintained. Then only we go ahead."

Guidance & Commitments

CommitmentSpecificsTimeline
Installed capacityExceed 15 GWBy end of FY26
Installed capacityReach 30 GW and 40 GWh of energy storageBy 2030
Total CAPEX₹1,30,000 crore to achieve 30 GW / 40 GWh targetBy 2030
BESS assembly plant5 GWh per annum facility operationalQ3 FY26
Tidong Hydro commissioning150 MW plant commissionedOctober 2026
Green hydrogen project3,800 TPA at Vijayanagar commissioned"Soon"
KSK Mahanadi expansionRemaining 1,800 MW completedBefore 2031
JSW Toshiba TG supplyFirst turbine generator delivered3 years from now
JSW Toshiba ramp-upTwo 800 MW TGs delivered per yearAfter first TG delivery
IRR hurdle rateMid-to-high-teen IRR maintained on all bidsOngoing
Weighted average cost of debtContinue easing as facilities reach reset datesNext couple of quarters

Key Metrics

MetricQ2 FY26
RevenueOver ₹5,300 cr, up 55% YoY
EBITDA₹3,200 cr, up 67% YoY
Profit after taxAbout ₹705 cr, down 17% YoY
Cash profitOver ₹1,500 cr, up 27% YoY
H1 EBITDAOver ₹6,200 cr, crossed entire FY25 EBITDA
H1 profit after taxClose to ₹1,450 cr, up almost 5% YoY
Net debtClose to ₹62,000 cr, up ~₹2,500 cr sequentially
Net debt in CWIPAbout ₹12,500 cr, down ~₹400 cr sequentially
Total debt to EBITDA (TTM)Just under 5x
Weighted average cost of debtUp close to 10 bps sequentially
CAPEX spent in the quarterAbout ₹3,500 cr
Net generation1,490 crore units, up 52% YoY from 980 crore units
Total installed capacity13.2 GW, up ~71% YoY from 7.74 GW
New capacity added in the quarter443 MW (Kutehr 240 MW hydro, wind 148 MW, solar 56 MW, 20 MW floating solar)
Under-construction generation portfolio12.5 GW, all fully tied up under long-term PPAs
Locked-in energy storage capacity29.4 GWh, after signing 680 MWh of BESS agreements in the quarter
Kutehr Hydro PLF58% for operational days of the quarter
Karcham-Wangtoo and BASPA design energy exceedance16% in Q2, 13% in H1 FY26
Karcham and Baspa EBITDA₹380 cr
Coal pricesAveraging $91 per tonne, down from $110 per tonne in Q2 FY25; post-quarter softened to ~$81 per tonne
Day ahead merchant pricesAveraging ₹3.92 per unit on exchanges, declining sequentially and annually
Domestic coal merchant exposure788 MW out of total merchant exposure of ~1.1 GW
Renewable LOAs pending PPA signing2.6 GW
Tidong Hydro acquisition enterprise valuation₹1,728 cr, 150 MW, expected commissioning by October 2026