Key Takeaways
- Capacity-led earnings surge: Revenue and EBITDA rose 55% and 67% YoY respectively, driven by the integration of KSK and O2 Power acquisitions and organic commissioning, taking installed capacity from 7.7 GW to 13.2 GW.
- PAT down on financing costs: Net profit declined 17% YoY as higher interest and depreciation from newly capitalized assets outweighed strong operating performance.
- Thermal PPA visibility is low: Management admitted it has a poor track record of forecasting state-level thermal PPA demand and offered no timeline for converting 2.6 GW of outstanding LOAs, though the 30 GW target is not contingent on them.
- Backward integration into manufacturing: The GE Power boiler acquisition and SANY wind turbine partnership signal a strategic move to secure supply chains, while the decision to pause solar module manufacturing shows capital discipline.
- What to watch next quarter: The pace of PPA signings for the 2.6 GW LOA book, the commissioning of the 5 GWh BESS assembly plant in Q3, and any further softening in merchant power prices.
Capacity Build-Out & the 30 GW Target
- Installed capacity nearly doubled YoY: From 7.7 GW to 13.2 GW, with the KSK and O2 Power acquisitions contributing the bulk, supplemented by organic additions including Kutehr Hydro (240 MW), wind (148 MW), and solar (56 MW plus 20 MW floating solar at Vijayanagar).
- 12.5 GW under construction, fully tied up: All under-construction capacity is secured under long-term PPAs, and upon completion, total installed capacity will nearly double again to approximately 26 GW.
- Targeting over 15 GW by fiscal year-end: Close to 2 GW of further capacity additions are expected in H2 FY26.
- 30 GW and 40 GWh storage by 2030: The plan requires total capital expenditure of ₹1,30,000 crore through the end of the decade.
- KSK Mahanadi expansion: Plans are in place to complete the remaining 1,800 MW before 2031.
- Tidong Hydro acquisition: Signed a definitive agreement to acquire the 150 MW under-construction plant from Statkraft at an enterprise valuation of ₹1,728 crore, with commissioning expected by October 2026 and a 22-year PPA with UPPCL already in place for 75 MW.
Sharad Mahendra: "With this, India's total thermal capacity in FY32 should reach close to 300 GW."
Generation Performance & Merchant Market
- Net generation up 52% YoY in Q2: The 60% H1 increase was driven by acquired and newly commissioned assets.
- Hydro portfolio outperformed design: Karcham-Wangtoo and BASPA plants exceeded design energy generation by 16% in Q2 and 13% in H1, while the newly commissioned Kutehr plant achieved a 58% PLF on its operational days by capitalizing on the high-generation season.
- Merchant prices softened further: Day-ahead market prices averaged ₹3.92 per unit, declining both sequentially and annually, pressured by record capacity additions and muted demand.
- Coal price tailwind: Imported coal averaged $91 per tonne in Q2, down from $110 a year ago, and has since softened further to approximately $81 per tonne, which should improve dark spreads for imported coal-based thermal capacity.
- Karcham Baspa EBITDA lower: A Supreme Court order on free power meant incremental free power previously sold in the merchant market is now supplied to the Himachal Pradesh government under the implementation agreement.
- Ind-Barath EBITDA dipped QoQ: The decline was solely due to a scheduled annual maintenance shutdown, with no other operational issues; demand is normally better in H2.
- Mytrah renewable EBITDA declined slightly: Despite higher wind speeds, the portfolio consists of older, small machines (850 kW) that limit incremental EBITDA from wind, while the solar portion (422 MW) underperformed due to lower radiation and extended monsoons.
- Barmer EBITDA fluctuates on regulatory mechanics: In regulated return businesses, depreciation rates change after 12 years as debt is repaid, reducing the capacity charge; quarterly variations also arise from backdowns, PLF changes, and station heat rate consumption.
PPA Environment & Bidding Strategy
- State PPA uptick driven by localisation: States including Bihar, MP, West Bengal, Assam, UP, and Maharashtra are signing thermal PPAs with a preference for in-state plants to encourage investment, employment, and address grid challenges. In renewables, states like Karnataka and Maharashtra are driving in-state projects to insulate from ISTS connectivity challenges and avoid incremental transmission charges implemented from 1st June.
- Bidding volumes expected lower this fiscal: Plain vanilla solar and wind bids have nearly disappeared; the majority of current bids are for solar paired with battery energy storage for evening discharge.
- 2.6 GW of LOAs await PPA conversion: The 400 MW LOA for the Utkal plant, once converted, will reduce open capacity from 8% to 5%, but management cannot provide any timeline for signing the broader LOA book, stating the company is well on track to reach 30 GW without them.
- PPA signing slowdown persists: No specific improvement has been observed in the last six months; thermal uptake is visible, and there is more keenness on solar-plus-BESS in both C&I and utility segments.
- Mid-to-high-teen IRR hurdle rate is non-negotiable: Management reiterated this as the benchmark for any bid and stated it will not build the portfolio just for the sake of building.
- Thermal PPA pipeline visibility is absent: States that have not yet bid may return in one or two years, but management offered no guidance, noting that the return of greenfield long-term thermal PPAs in the last 18 months surprised the market itself.
Pritesh Vinay: "We have a very poor track record of calling something like this out. We would not trust our views on this, right, on a lighter note."
Supply Chain & Manufacturing Integration
- GE Power India boiler manufacturing acquisition: Entered via a Scheme of Arrangement, the acquisition directly addresses constraints in timely boiler supplies that have threatened PPA timelines from existing suppliers. The Salboni boiler will now be manufactured in-house using these assets.
- SANY partnership for wind turbine manufacturing: A new partnership aimed at securing wind turbine supply, complementing the boiler acquisition.
- Solar module manufacturing paused: A capital-disciplined decision, contrasting with the push into boiler and wind manufacturing.
- JSW Toshiba JV to supply turbine generators: The existing joint venture, which has already supplied 800 MW TGs to NTPC and others, will supply the Salboni turbine generator. The ramp-up timeline targets the first TG delivery three years from now, with a capacity of two 800 MW TGs per year thereafter.
- BESS assembly plant in Pune: A 5 GWh per annum facility expected to be operational in Q3 FY26, open to both captive needs and external customers, with full capacity expected by the second year of operation. Management cited MNRE's focus on ALMM for solar and wind as a driver, anticipating a similar Make in India push for battery storage.
Sharad Mahendra: "There definitely has been constraints in terms of timely supplies to meet the PPA timelines, from the existing suppliers for boiler turbine generator."
Financial Position & Returns
- Cash profits up 27% YoY: Cash profits exceeded ₹1,500 crores, even as PAT declined 17% on higher interest and depreciation from newly capitalized assets.
- Net debt rose sequentially by ~₹2,500 crores: The increase was driven by CAPEX spend of ₹3,500 crores in the quarter, partially offset by the capitalization of ongoing projects.
- Weighted average cost of debt expected to ease: More facilities are reaching their reset dates in the next couple of quarters, which should bring the cost of debt down further.
- ROE is back-end loaded in renewables: In the RE business, ROE is lower in initial years because debt is still being repaid; after 10-12 years, as debt is paid down faster, PAT rises and ROE bunches up toward the back end of the asset's economic life. Capital allocation decisions are based on long-term cash flow forecasting, not backward-looking ROE.
- Economic life exceeds depreciation: With nominal R&M CAPEX and proper O&M and overhauls, the economic life of assets can be elongated well beyond the straight-line depreciation period.
- Vijayanagar plant de-risked: The imported coal-based plant has been proactively tied up with JSW Steel, insulating it from merchant market volatility.
Sharad Mahendra: "Mid-to-high-teen IRR is our hurdle rate that has to be maintained. Then only we go ahead."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Installed capacity | Exceed 15 GW | By end of FY26 |
| Installed capacity | Reach 30 GW and 40 GWh of energy storage | By 2030 |
| Total CAPEX | ₹1,30,000 crore to achieve 30 GW / 40 GWh target | By 2030 |
| BESS assembly plant | 5 GWh per annum facility operational | Q3 FY26 |
| Tidong Hydro commissioning | 150 MW plant commissioned | October 2026 |
| Green hydrogen project | 3,800 TPA at Vijayanagar commissioned | "Soon" |
| KSK Mahanadi expansion | Remaining 1,800 MW completed | Before 2031 |
| JSW Toshiba TG supply | First turbine generator delivered | 3 years from now |
| JSW Toshiba ramp-up | Two 800 MW TGs delivered per year | After first TG delivery |
| IRR hurdle rate | Mid-to-high-teen IRR maintained on all bids | Ongoing |
| Weighted average cost of debt | Continue easing as facilities reach reset dates | Next couple of quarters |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue | Over ₹5,300 cr, up 55% YoY |
| EBITDA | ₹3,200 cr, up 67% YoY |
| Profit after tax | About ₹705 cr, down 17% YoY |
| Cash profit | Over ₹1,500 cr, up 27% YoY |
| H1 EBITDA | Over ₹6,200 cr, crossed entire FY25 EBITDA |
| H1 profit after tax | Close to ₹1,450 cr, up almost 5% YoY |
| Net debt | Close to ₹62,000 cr, up ~₹2,500 cr sequentially |
| Net debt in CWIP | About ₹12,500 cr, down ~₹400 cr sequentially |
| Total debt to EBITDA (TTM) | Just under 5x |
| Weighted average cost of debt | Up close to 10 bps sequentially |
| CAPEX spent in the quarter | About ₹3,500 cr |
| Net generation | 1,490 crore units, up 52% YoY from 980 crore units |
| Total installed capacity | 13.2 GW, up ~71% YoY from 7.74 GW |
| New capacity added in the quarter | 443 MW (Kutehr 240 MW hydro, wind 148 MW, solar 56 MW, 20 MW floating solar) |
| Under-construction generation portfolio | 12.5 GW, all fully tied up under long-term PPAs |
| Locked-in energy storage capacity | 29.4 GWh, after signing 680 MWh of BESS agreements in the quarter |
| Kutehr Hydro PLF | 58% for operational days of the quarter |
| Karcham-Wangtoo and BASPA design energy exceedance | 16% in Q2, 13% in H1 FY26 |
| Karcham and Baspa EBITDA | ₹380 cr |
| Coal prices | Averaging $91 per tonne, down from $110 per tonne in Q2 FY25; post-quarter softened to ~$81 per tonne |
| Day ahead merchant prices | Averaging ₹3.92 per unit on exchanges, declining sequentially and annually |
| Domestic coal merchant exposure | 788 MW out of total merchant exposure of ~1.1 GW |
| Renewable LOAs pending PPA signing | 2.6 GW |
| Tidong Hydro acquisition enterprise valuation | ₹1,728 cr, 150 MW, expected commissioning by October 2026 |