Key Takeaways
- Volume growth despite Fujairah outage: Cargo volumes rose 6% YoY to 3.1 crore tonnes, with India operations growing 11% YoY, even as Fujairah contributed nothing in the quarter.
- Guidance held, Fujairah factored in: FY27 volume guidance of 12.7 crore tonnes and EBITDA guidance of ₹3,000 crores were both reaffirmed, with the volume number explicitly excluding Fujairah and the EBITDA number including a modest ₹100–125 cr contribution from it.
- Greenfield pipeline is now funded and derisked: The ₹7,503 cr QIP closed, Moody's upgraded the company to investment grade, and key milestones at Murbe, Jatadhar, and the slurry pipeline were met, shifting the growth story from ambition to execution.
- Logistics segment turned a corner: Revenue rose to ₹237 cr from ₹138 cr and operational EBITDA jumped 3.6x, with Navkar's domestic volumes up 40% and the rail rake fleet build-out accelerating.
- What to watch next quarter: Whether Fujairah's 8 tanks come online by early August and begin contributing, the pace of the insurance claim resolution, and any update on the NCR Rail terminal bid and Navkar merger decision.
Volume & Operational Performance
- India drove the quarter: Excluding Fujairah, India operations recorded 11% YoY volume growth, significantly outpacing overall industry growth, with strength at Jaigarh, Dharamtar, Southwest Port, Ennore Bulk Terminal, and Tuticorin.
- Jaigarh delivered a one-time margin boost: QoQ port EBITDA margin improvement, after adjusting for a ~₹60 cr one-off in Q4 FY26, was primarily driven by Jaigarh handling alumina and project cargo, neither of which is recurring.
- Third-party mix held steady: Third-party cargo volumes stood at 48%, with incremental recurring LPG cargo at Jaigarh expected to continue in subsequent quarters.
- One-off costs were modest: ₹8–9 cr was incurred in Q1 for shifting a crane at Jaigarh port, expensed rather than capitalised.
- Fujairah absence was the single largest drag: The terminal was not operational in Q1, with an estimated EBITDA loss of ₹65–70 cr from its absence, and an insurance claim filed with resolution expected by end of October 2025.
Rinkesh Roy: "We have already put forward claims, and it has been told by our adviser that it's going on well. And we should expect a resolution by end of October."
Financials & Margins
- Port revenue grew, margin dipped: Port segment revenue increased 11% YoY to ₹1,208 cr, but EBITDA margin dipped to ~49.8% from 51.8% a year ago, mainly attributable to the lower contribution of volumes from Fujairah Port.
- Consolidated PAT declined on lower other income: PAT fell to ₹358 cr from ₹390 cr, driven by lower PBT (₹463 cr vs ₹473 cr) and a higher effective tax rate; the PBT decline mainly reflected lower other income given continued capex spend for growth projects.
- Other income should rebound: The QoQ decline in other income was driven by a lower treasury balance due to ongoing capex and equity contributions to projects; QIP proceeds received on 30 June will boost treasury income for the rest of FY27.
- Q4 FY26 other income contained a one-off: The prior quarter included ~₹40 cr interest received from Hiranandani, the JV partner at Jaigarh; normalized Q4 other income would have been ₹50–55 cr.
- Logistics segment profitability transformed: Overall logistics revenue rose to ₹237 cr from ₹138 cr, operational EBITDA rose 3.6x to ₹73 cr from ₹20 cr, and EBITDA margin improved to 30.6% from 14.5%.
- Rail rake margin optics explained: The apparent ~93% EBITDA margin for rail rakes reflects only premium and rebate in revenue, with haulage and freight charges netted off; if freight were included, the margin would be ~25%.
Greenfield & Expansion Projects
- Murbe is now fully cleared: Environmental clearance and approval for rail connectivity to the Dedicated Freight Corridor were received; concession agreement signing is expected in the next 2–3 months, tenders have already been invited, and construction is set to start by December.
- Murbe's competitive logic: The port will serve the Tarapur-Boisar-Palghar industrial area and the hinterland of MP, Telangana, and southern and western Maharashtra, with the Dedicated Freight Corridor connection opening North India; management's USP is an integrated logistics play enabling door-to-door services.
- Murbe cargo mix and customer split: The port will handle bulk, break bulk, containers, and fertilizers, with an expected ~20% group and ~80% third-party cargo split.
- Slurry pipeline on track: 251 km of pipeline lowering is completed (~83%), and the project remains on track for completion by March 2027.
- Jatadhar Port advancing: Construction activities are in full swing, and a novation agreement has been executed with the anchor customer following Odisha government approvals.
- Keni port delayed by regulatory vacuum: Environmental clearance is still awaited because the Karnataka Coastal Zone Management Authority was not constituted for 6–7 months, a delay management called beyond its control; clearance is now expected in another 3–4 months.
- Oman port proceeding despite geopolitics: Bids were invited in June for port construction, and the concession agreement signing is expected in another month or two; management's view is that wars will not continue indefinitely and the 2–3 year project timeline makes it a good decision to move ahead.
- Kolkata project awarded: The integrated development of the Outer Container Terminal and berths 1–5 at Netaji Subhas Dock under a PPP framework was awarded; Phase 1 steady-state EBITDA is expected at ~₹70–90 cr, with full completion by 2030 delivering ~₹300–350 cr at 75–80% capacity utilization.
Rinkesh Roy: "...these wars, we -- it's in our perception and everyone's perception. These are not going to be continuing indefinitely. So these projects will take another 2, 3 years to come into stream. So I think it's a good decision to move ahead. We'll be continuing on this."
Logistics & Navkar
- Navkar delivered a standout quarter: Domestic cargo volumes rose 40% YoY to 385,000 tonnes, EXIM volumes rose 2% to 83,000 TEUs, revenue rose 38% to ₹191 cr, operating EBITDA rose 62% to ₹33 cr, and net profit rose to ₹12 cr from ₹2 cr.
- Rail fleet build-out accelerating: In April 2026, orders were placed for an additional 25 container rigs and 15 rail rigs; the first two railway rigs from that order were delivered in July 2025, and the full 40-rake order is expected to be on stream by January/February 2026, taking the fleet to 80+ rakes.
- Medium-term fleet target: The objective is ~110 rail rigs and 140 container rigs, a combined ~250 rigs over the next 2–3 years, with a 2030 target of 250 rakes that may be revised upward if the GPWIS moratorium is lifted.
- Rake utilization split: Approximately 45% group and 55% third party.
- Logistics acquisitions in play: Management is bidding for the NCR Rail terminal, expected to close in Q1 FY27, and is eyeing a couple of logistics assets in NCLT where it would like to participate as a bidder.
- Navkar merger decision deferred: When asked about plans to merge Navkar Corporation, management said only, "We'll communicate at the right time" and "we have not taken anything on that," declining to provide any details or timeline.
Guidance & Balance Sheet
- QIP strengthened the balance sheet: The ₹7,503 cr qualified institutional placement closed with strong participation from global and domestic institutional investors; as of June 2026, the company held a net cash position of ₹2,769 cr post QIP receipts of ₹6,555 cr.
- Moody's upgrade to investment grade: Moody's assigned a Baa3 rating, up from Ba1, with a stable outlook.
- Capex plan is large but largely committed: Planned capex for FY27–FY28 is ~₹16,500 cr (~₹13,000 cr port, ~₹3,500 cr logistics); cumulative incurred up to June 2026 was ~₹6,900 cr, with a further ₹5,500 cr committed via orders already placed.
- Fujairah restart is imminent but conditional: Eight tanks are expected to be operational by late July or early August 2025, with another three tanks expected by September or October 2025, though actual operations depend on market conditions including prices and ship arrivals.
Jambunathan Nagarajan: "Stick to our guidance of INR3,000 crores, Priyankar, in terms of the EBITDA."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 volume | ~12.7 crore tonnes (includes Fujairah volume loss assumption) | FY27 |
| FY27 EBITDA | ~₹3,000 cr (includes ₹100–125 cr from Fujairah at 0.2–0.25 cr tonnes) | FY27 |
| FY28 EBITDA | ~₹5,000 cr | FY28 |
| Capacity expansion | 30 crore tonnes | By FY28 |
| Capacity expansion | 40 crore tonnes | By FY2030 or earlier |
| Slurry pipeline completion | Project on track | March 2027 |
| Kolkata full completion | ~₹300–350 cr steady-state EBITDA | By 2030 |
| Murbe construction start | Preparatory works within a month, construction by December/January | Q3 FY27 |
| Keni environmental clearance | Expected in 3–4 months (KCZMA now constituted) | ~Q2 FY27 |
| Fujairah insurance claim resolution | Claim filed, adviser indicates progress | End of October 2025 |
| Rail rake fleet | 40-rake order fully on stream, fleet reaches 80+ rakes | Jan/Feb 2027 |
| Logistics fleet target | ~250 rigs (110 rail, 140 container) | Next 2–3 years |
| NCR Rail terminal bid | At high end of closure | Q1 FY27 |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Consolidated operating revenue | ₹1,445 cr, +18% YoY |
| Operating EBITDA | ₹674 cr, +16% YoY |
| Port segment revenue | ₹1,208 cr, +11% YoY |
| Port segment EBITDA | ₹601 cr, +7% YoY; margin 49.8% vs 51.8% a year ago |
| Logistics segment revenue | ₹237 cr, vs ₹138 cr in Q1 FY26 |
| Logistics segment EBITDA | ₹73 cr, up from ₹20 cr, 3.6x increase; margin 30.6% vs 14.5% earlier |
| PAT | ₹358 cr, vs ₹390 cr in Q1 FY26 |
| PBT | ₹463 cr, vs ₹473 cr in Q1 FY26 |
| Depreciation | ₹166 cr, vs ₹143 cr in Q1 FY26 |
| Finance cost | ₹95 cr, vs ₹91 cr in Q1 FY26 |
| Cargo handled | 3.1 cr tonnes, +6% YoY; India operations +11% YoY ex-Fujairah |
| Third-party cargo share | 48% |
| FY27 volume guidance | ~12.7 cr tonnes, factoring in Fujairah loss |
| FY27 operating EBITDA guidance | ~₹3,000 cr, reaffirmed |
| FY28 operating EBITDA guidance | ~₹5,000 cr, reaffirmed |
| Net cash position | ₹2,769 cr as of June '26 |
| QIP completed | ₹7,503 cr; receipts of ₹6,555 cr into the company |
| Planned capex FY27–FY28 | ~₹16,500 cr; ~₹13,000 cr port, ~₹3,500 cr logistics |
| Q1 capex spent | ₹671 cr; cumulative ~₹6,900 cr up to June '26 |
| Committed capex (orders placed) | ₹5,500 cr |
| Navkar revenue | ₹191 cr, +38% YoY |
| Navkar EBITDA | ₹33 cr, +62% YoY |
| Navkar net profit | ₹12 cr, vs ₹2 cr in Q1 FY26 |
| Navkar domestic cargo volumes | 385,000 tonnes, +40% YoY |
| Navkar EXIM cargo volumes | 83,000 TEUs, +2% YoY |
| Total fleet strength | 42 rakes (25 rail rakes, 17 container rigs including Navkar) |
| Additional rakes ordered (April '26) | 25 container rigs and 15 rail rigs; first 2 railway rigs received |
| Medium-term fleet target | ~250 rigs (~110 rail, ~140 container) over next 2–3 years |
| Current capacity | 18.6 cr tonnes per annum |
| Capacity target | 30 cr tonnes by FY28, 40 cr tonnes by FY2030 or earlier |
| Slurry pipeline progress | 251 km lowering completed, ~83% of total; on track for completion by March 2027 |
| Fujairah estimated EBITDA loss in Q1 | ~₹65–70 cr incremental EBITDA lost; port EBITDA would have been ~₹670–675 cr |
| Fujairah EBITDA baked into FY27 guidance | ~₹100–125 cr |
| Fujairah volume baked into FY27 guidance | 0.2–0.25 cr tonnes |
| Kolkata Phase 1 steady-state EBITDA | ~₹70–90 cr |
| Kolkata all phases long-term EBITDA | ~₹300–350 cr |
| Moody's rating | Baa3 (investment grade), upgraded from Ba1, stable outlook |