Key Takeaways
- Record dispatches, margin expansion: ~1,900 machines shipped in Q2, the highest ever, while standalone EBITDA margin rose 320 bps YoY to 28% despite a higher share of entry-level machines.
- PLI scheme unlocks vertical integration: Approval for a ₹1,020 crore investment with 25% capital incentive positions Jyoti to develop in-house CNC controllers, motors and drives, a step toward becoming a mechatronics company.
- Huron ramp-up is the H2 catalyst: Dispatches from expanded Huron capacity begin in Q3, with ₹80–100 crores expected that quarter and a path to the ~₹300 crore full-year target, though end-user certificate progress remains a watchpoint.
- Order book and demand visibility support multi-year growth: A ₹5,082 crore order book plus management's stated 3-year demand confidence, anchored in auto/EV capex and import substitution, underpin the 25–30% CAGR ambition.
- What to watch next quarter: Whether Huron dispatches actually hit the ₹80–100 crore Q3 run-rate, whether the foundry commences operations on time, and whether the aerospace & defence tenders that slipped in Q2 reopen and convert.
Huron: The H2 Delivery Engine
- Q2 revenue and unrecognized backlog: Huron contributed ~₹44 crores of revenue in Q2, while ~₹65 crores of prior dispatches remain unrecognized in consolidation due to POCM accounting and pending end-user certificates.
- Capacity expansion now live: New manufacturing capacity added in November 2025; dispatches from this expanded base are expected to commence in Q3 and Q4 FY27.
- End-user certificate progress: 1–2 machines received government permissions for dispatch last week; management stated there has been no further communication from European investigative authorities since its response to the April notice.
- Q3 and full-year trajectory: Q3 dispatches are projected at ₹80–100 crores, with further ramp-up in Q4, keeping the company on track to reach close to ₹300 crores for the full year once clearance and certificate clarity arrive.
Parakramsinh Jadeja: "So the first week of April, what we received the notice and what we have response to them, and then after there is not a single communication from them, okay. And this is the same status are all other investigative company in Europe."
PLI Scheme & the Mechatronics Pivot
- PLI approval secured: Jyoti received approval under the government's PLI scheme for domestic manufacturing, committing over ₹1,020 crores of capital investment over 5 years with a 25% capital incentive (₹255 crores) to develop in-house manufacturing of CNC controllers, motors, drives, and operator interfaces.
- ECMS subsidy adds further support: The company also received a capital subsidy under the ECMS scheme for electronics component manufacturing, with phase 1 entailing a ₹400–450 crore investment and a ₹200 crore net outlay after subsidy.
- State subsidy expected soon: A Gujarat government matching grant plus an R&D subsidy are anticipated, which would take the total subsidy to over 50% of the ₹1,020 crore PLI investment.
- Controller R&D already underway: A dedicated controller division within the R&D center has been working for 1.5 years with a team of 110+ engineers; 40–50 more are expected to be added in the next ~6 months, with own controllers targeted within 2 years.
- Strategic ambition: Management aims to transform Jyoti from a mechanical company into a mechatronics company within 2 years, developing all electronics in-house, and subsequently enter industrial automation with robotics as the first priority.
- Customer acceptance risk acknowledged: Management noted the challenge of customer acceptance for own controllers but pointed to a base of 15,000+ customers, with roughly one-third described as "die-hard" customers willing to test new offerings.
Parakramsinh Jadeja: "Today, we are a mechanical company. We design the machine, we manufacture the machine, we castings, we machining the precision component, and we integrate. Now in future, we are looking to be a mechatronics company."
Margins: Expansion with a Floor
- Standalone margin strength: Standalone EBITDA margin reached 28% in Q2 FY27, up 320 bps YoY, driven by the business model's ability to sustain margins not below 25% even as the share of entry-level machines increases.
- Consolidated margin and H2 path: Consolidated EBITDA margin stood at 21.8% in Q2; management expressed confidence in reaching the guided 25% for the full year, citing H2's seasonal strength and the Huron ramp-up contribution.
- Operational leverage ahead: Close to 950 people were added in the last 6 months, with costs being booked now while associated revenue is still to come, implying margin tailwinds as those people become productive.
- R&D investment from margin gains: Margin improvements from vertical integration and operational leverage will be reinvested into R&D; cost advantages are expected from in-house manufacturing of vertically integrated components.
- Interest cost declining: Interest cost fell to ~₹14 crores in Q2 due to improved working capital utilization; management confirmed interest is fully expensed and expected to remain stable quarter-to-quarter.
Parakramsinh Jadeja: "I was always telling to you people in your past questions and in a meeting, that let's say once this our entry-level product number is also going to increase, our business model combination is such that we will not go below 25% of margin there."
Demand & Order Book
- Record order intake: Q2 order intake reached ₹800 crores, driven by strong demand from the auto sector where OEMs are adding capacity, particularly in the EV space.
- Order book visibility: A total order book of ₹5,082 crores provides strong revenue visibility for the coming quarters.
- Multi-year demand confidence: Management stated it is "very much confident" of demand visibility for the next 3 years, with the front-end business side facing no challenge; the focus is entirely on improving execution.
- Import substitution tailwind: With ~60% of India's CNC machine demand still met through imports, management sees a significant opportunity for domestic manufacturers to capture share.
- Aerospace & defence pipeline intact: Order intake from aerospace & defence declined in Q2 because some government tenders were not opened as expected; management stated no orders were lost and further orders are expected in Q3 and coming quarters.
- EMS execution improving: Execution of EMS orders improved in Q2, with further improvement expected in the next two quarters as new capacity comes online.
Parakramsinh Jadeja: "I think, momentum, what the way we are seeing the investments are coming and pipelines are what we are seeing today. We are very much confident in the next 3 years, we are clearly visibilities are there."
Capacity Build-Out & Operations
- Foundry nearing completion: The new foundry, using lost foam vacuum casting technology capable of up to 15-tonne single-piece casting, is on the last mile; equipment is under transit and expected to reach month-end, with completion expected this quarter.
- Foundry capacity expansion: Monthly capacity will expand from 1,500 tonnes to 5,000 tonnes once the new foundry is operational.
- New plant status: Machine assembly and sheet metal facilities have already been put to use; management stated there is no bottleneck for current-year targets.
- Inventory days improving: Inventory days improved from 203 days at March levels to close to 190 days currently, with further reduction expected by year-end.
- Cash flow strengthening: Operating cash flow reached 47% of EBITDA in H1, up from a very low base last year, attributed to better working capital management; management is targeting 50% OCF/EBITDA by year-end and maintained going forward.
- New product launch: The MTX 100, a compact 5-axis multitasking turn-mill center combining turning, milling, gear cutting and grinding in a single setup, was launched for aerospace, defence, automotive & EV, and oil & gas industries.
Volume & Revenue Trajectory
- FY27 volume target: 8,000 machines for the full year, with H2 implied at ~4,700+ machines; management pushed back on the characterization of this as "conservative," noting that H2 volume alone nearly equals last year's full-year figure of 5,600.
- FY27 revenue growth: 25% to 30% combined growth (Huron plus Jyoti) remains on track.
- Medium-term growth ambition: 25% to 30% CAGR targeted for the next 2–3 years.
- Average realization stability: Average realization is expected to maintain the ₹35–36 lakh range over the next 2–3 years, though the current quarter saw a reduction to about ₹32 lakhs.
- Supply chain resilience: Management credited proper planning and maintained safety-factor inventories for the ability to clock current growth despite broader supply chain challenges; own controllers are not part of the near-term supply plan.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Consolidated EBITDA margin | Reach 25% | FY27 year-end |
| Huron dispatches | ₹80–100 crores in Q3; ramp further in Q4 | Q3 and Q4 FY27 |
| Huron full-year revenue | Close to ₹300 crores total | FY27 |
| Total machine volume | 8,000 machines | FY27 |
| Combined revenue growth | 25% to 30% (Huron + Jyoti) | FY27 |
| Revenue CAGR | 25% to 30% | Next 2–3 years |
| OCF/EBITDA ratio | 50% | FY27 year-end and maintained thereafter |
| Inventory days | Reduce below 190 days | FY27 year-end |
| Capex outlay | ₹450–500 crores total | FY27 |
| Own CNC controller | Development complete and deployed | Within 2 years |
| Mechatronics company transition | Develop all electronics in-house | Within 2 years |
| PLI scheme investment | Over ₹1,020 crores capital investment | Over 5 years |
| ECMS phase 1 investment | ₹400–450 crores (₹200 crores net of subsidy) | 1 year |
| Foundry operations | Commence operations | Current quarter |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Standalone revenue | ₹588 cr, +31% YoY |
| Consolidated revenue | ₹602 cr, +18.5% YoY |
| Standalone EBITDA | ₹164 cr, margin 28%, up 320 bps YoY |
| Consolidated EBITDA | ₹131 cr, margin 21.8% |
| Standalone PAT | ₹115 cr, +46% YoY, margin 19.6% |
| Consolidated PAT | ₹73 cr, margin 12% |
| Order book | ₹5,082 cr as of Sep 30, 2026 |
| Order intake | ₹800 cr during Q2; H1 intake over ₹1,400 cr against full-year guidance of ₹2,500–3,000 cr |
| Machines dispatched | 1,911, highest quarterly dispatches in company history, vs 1,315 in Q2 FY26 |
| FY27 volume guidance | 8,000 machines; H1 delivered 3,317, H2 expected ~4,700+ |
| FY27 combined revenue growth guidance | 25% to 30% (Huron + Jyoti) |
| FY27 EBITDA margin commitment | 25%, to be reached closer to year-end |
| Huron Q2 revenue | ~₹44 cr dispatches, ₹15 cr recognized in consolidated; full-year guidance maintained at ₹300–325 cr, 5–10% EBITDA margin |
| Huron revenue pending recognition | ₹60 cr not recognized in consolidated H1; ₹65 cr reversed in Q4 FY26 still pending |
| Revenue mix | Aerospace & defence 21%, automotive & auto components 36%, general engineering 28%, electronics & manufacturing services 7%, die & molds 1%, other 7% |
| Order book industry mix | Aerospace & defence 36%, automotive & auto components 22%, general engineering 21%, electronics manufacturing services 12%, die & molds 4%, balance other |
| Inventory days | ~190 days, improved from 203 days at March 2026; expected to reduce further by year-end |
| Operating cash flow | ₹112 cr in H1, 47% of EBITDA; targeting 50% by year-end |
| PLI scheme approved investment | Over ₹1,020 cr over 5 years, 25% central subsidy (₹255 cr); state matching grant expected, total subsidy 50%+ |
| Employees added | ~950 in last 6 months |
| Foundry capacity | 1,500 tonnes/month existing, expanding to 5,000 tonnes/month |