K2 Infragen Ltd Guidance Report - SOIC x StockScans Report

as of Nov 2026

  1. Machine/equipment fleet expansion - add more machines in FY27 Pending - At the Q4 FY26 call, management said it plans to add more machines/equipment this year beyond the existing 64+ fleet and is generating capital for it. No fleet-count update has been disclosed in the cited Q2 FY27 sources, so the outcome remains unverified as of 17th November 2026.
  2. Direct government contracts - increase share in order book On track - At the Q4 FY26 call, management said increasing the share of direct government contracts in the order book will remain an important strategy focus area going forward. Since December 2025, K2 secured approximately ₹412 cr of new orders directly from government bodies across energy, T&D, railway and renewables, and H1 FY27 new orders are direct orders from authorities.
  3. TBCB and HAM - build stable annuity-based revenue stream On track - At the Q4 FY26 call, management said it intends to explore TBCB and hybrid annuity model opportunities to build a stable annuity-based revenue stream over the long term. It bid one HAM project with a ₹273 cr comfort letter from Kotak and appointed a Senior Vice President for the HAM vertical.
  4. NHAI ₹48.34 cr road order - credential for larger 500 Cr+ road projects Partial - In the 15th January 2025 announcement, the ₹48.34 cr NHAI road order was intended to earn credentials for direct or JV bidding for larger road projects in the coming year, paving the way for 500 Cr+ road projects. K2 secured a ₹142.14 cr NHAI PBMC contract at Jetpur-Somnath, its largest Roads & Transport order, with roads around 77% of the order book as of Q4 FY26; no 500 Cr+ road win is disclosed.
  5. HAM project association - eyeing a road infrastructure major Partial - In the 28th May 2024 announcement, management was eyeing an association with a road infrastructure major for a road development project under the HAM model in India. It bid one HAM project with a ₹273 cr Kotak comfort letter, also confirmed by Union Bank, and appointed a Senior Vice President for the HAM vertical; no completed association with a road infrastructure major is disclosed.
  6. Revenue target - surpass ₹450 cr by FY26 Missed - In the 24th August 2024 announcement, management aimed to surpass ₹450 cr in revenue by FY26, fuelled by strategic expansion across India and key regions including Africa and the Middle East. FY26 revenue was ₹184.68 cr or ₹185 cr, growth of \~26% YoY - far below the ₹450 cr target.
  7. AEPL acquisition - Tranche II to complete 100% ownership Pending - In the 19th October 2025 announcement, Tranche II of the AEPL acquisition - the balance 5,100 equity shares (51%) - was to be completed upon satisfaction of mutually agreed conditions, making AEPL a wholly owned subsidiary with 100% ownership and control. Tranche I was completed: 4,900 equity shares (49%) acquired for ₹20,00,000/-; no Tranche II completion is disclosed.
  8. North Western Railways ₹262 cr order - execution within 36 months On track - In the 1st January 2026 announcement, the ₹262 cr North Western Railways order (traction substation/SCADA, LUNI-Bhildi section, via JV with K2 as lead majority partner) was to be executed within 36 months. The Railway Electrification Bhildi Section (2x25 kV), Jodhpur Division - ₹262.1 cr - remained in the active projects list as of Q4 FY26 with ₹228.4 cr unexecuted in the Railway vertical.
  9. Rewari-Kathuwas OHE project - completion by October 30, 2025 Missed - In the 17th July 2024 announcement, the Rewari-Kathuwas OHE project (₹33.41 cr, NWR) was scheduled for completion within 15 months, expected by October 30, 2025, with management committing to on-time, within-budget completion. The (2x25 KV) AC HIGHRISE OHE works project (₹28.3 cr in Q4 FY25 PPT; ₹31.3 cr in Q4 FY26 PPT) remained in the active projects list as of Q4 FY26, with no completion disclosure by October 30, 2025.
  10. Solar EPC - major breakthrough expected soon (stated Feb 2025) Partial - In the 3rd February 2025 announcement, management was actively exploring solar EPC opportunities, expecting a "major breakthrough soon". K2 decided not to proceed with the 67.61 MWp solar EPCC project at Khavda, Gujarat (PO received 20th March 2025), citing scope changes and failed pricing negotiation, and entered renewables via a first 2 MW solar plant order in Haryana with ₹8.1 cr unexecuted renewables order book.
  11. Order book expansion - ₹800 cr new orders in FY24-25, cumulative ₹1,000 cr+ by year end Missed - In the 28th May 2024 announcement, management guided new orders in Water Supply, Road and T&D expected to add ₹800 cr to the order book in FY 24-25, creating a cumulative order book of ₹1,000 cr+ by the financial year end. Order book as of 1st March 2025 was ₹547.43 cr under execution with ₹327 cr unexecuted, and FY25 order acquisition surpassed ₹452.5 cr, the highest in the company's history.
  12. International expansion - Africa & Middle East projects commencing FY24-25 Missed - In the 28th May 2024 announcement, management guided international expansion into Africa & Middle East infrastructure projects, with initial projects to commence in FY 24-25; in October 2024 it aimed to surpass ₹450 cr revenue by FY26 fuelled by expansion including Africa and the Middle East. No Africa or Middle East project commencement or revenue is disclosed, and at the Q4 FY26 call management said it is planning to enter the international market "very soon".
  13. State footprint expansion - add 1-2 states in FY28 Pending - At the Q2 FY27 call, management said 1-2 more states could be added to the current 10-state footprint, "could be in the FY28 but not in this financial year" (Pankaj Sharma). The company currently operates across 10 states; no FY28 state addition disclosure exists yet.
  14. Renewable energy portfolio mix - increase to 20-25% On track - At the Q2 FY27 call, management is targeting increasing the portfolio mix toward renewable energy "up to 20-25%" (Pankaj Sharma). Renewables unexecuted order book was ₹8.1 cr, described as early scale-up, entered via a first 2 MW solar plant order in Haryana, and K2 bid for 3-4 BESS projects in Rajasthan and signed an MOU with MAP Power.
  15. Order book execution - \~₹907 cr completed within 36 months On track - At the Q2 FY27 call, management said the \~₹907 cr order book will be completed "on the tune of, you can say, 36 months maximum", with a few railway and transmission orders within 24 months, reiterating a target of around ₹580-600 cr within 24 months (Pankaj Sharma). Unexecuted order book stood at approximately ₹907 cr as of September 2026, a 114% increase over March 2026, with new direct orders at initial stages of execution.
  16. Credit rating - to be shared in June 2026 Delivered - At the Q4 FY26 call, management said a credit rating will be shared "in the month of June" (Pankaj Sharma). At the Q2 FY27 call, management disclosed Acuity Ratings and Research assigned an investment-grade Acuity A-/stable rating for long-term bank facilities and Acuity H3 for short-term facilities, covering approximately ₹200 cr.
  17. EBITDA margin - maintain 13-14% going forward Missed - At the Q4 FY26 call, management indicated FY26 full-year EBITDA margin landed "in the range of 13%, 14%" and that "13%, 14%... can be maintained very easily" going forward (Pankaj Sharma). FY26 EBITDA margin was approximately 12.5% or 12.37%, and H1 FY27 EBITDA margin was approximately 2% with Q2 FY27 OPM at 1.92%; management expects margins in "an upward direction... in the coming year".
  18. Main board migration - by mid-2027 or January 2028 On track - At the Q4 FY26 call, management said the company expects to be on the main board "in mid of 2027 or January '28" (Pankaj Sharma); at the Q2 FY27 call this was restated as "within, I think by 2 years". No main board migration filing or disclosure exists as of 17 Nov 2026, and the company remains on the NSE SME platform.
  19. On-time project delivery rate - raise from 83% to 90%+ in FY27 On track - At the Q4 FY26 call, management targeted raising the on-time project delivery rate from 83% to "83 to 90 plus" in the current year (FY27) (Pankaj Sharma). FY26 on-time delivery rate was approximately 83%; no FY27 read on the rate is disclosed yet.
  20. FY27 revenue growth - more than 25% On track - At the Q4 FY26 call, management guided FY27 revenue growth of "more than 25%", noting the standard had been maintained for the last three years and "it will be maintained", reiterated as an "aspiration of 25%, 26% of year-on-year growth which is very much easily possible" (Pankaj Sharma). H1 FY27 revenue was approximately ₹63 cr versus ₹91 cr in H1 FY26, a \~31% YoY decline, attributed to war-related supply chain disruptions and execution delays, with management expecting significant improvement in H2 FY27.