Key Takeaways
- H1 hits a historical revenue high: Revenue reached a record for any first half, driven by capacity expansion and debottlenecking.
- Transmission supercycle thesis intact: Management called a supercycle for the next decade or so in power transmission, and the segment now contributes 20% of revenue with a clear path to increase share from next year.
- Margins under freight pressure, relief expected: Q2 EBITDA margin improved ~100 bps QoQ to ~11.9% but was held back by elevated global freight costs; management expects to pass most of these on to customers, with positive impact visible in H2.
- Order book builds, US dominates: The order book grew to ₹6,500 crores, with the US contributing over 57%, and a single ₹550 crore US transmission order was won just before the call.
- What to watch next quarter: Whether freight cost pass-throughs actually lift margins as promised, the pace of Saudi trial production starting in December, and any further large US or Canada order wins.
Demand & Revenue Trajectory
- H1 seasonality: The business historically books ~45% of annual revenue in H1, with H2 contributing 55–58% as infrastructure deliveries accelerate after the monsoon; H1 FY27 performance should be read in that context.
- Base effect acknowledged: Revenue grew from ₹1,000 crores to ₹4,300 crores last year; continuing 30–35% growth on a much larger base means absolute revenue increments keep growing materially, a dynamic management flagged explicitly.
- International tilt: International revenue stood at 70% of H1 revenue, up sharply from 45% YoY, reflecting strong demand across the US, Europe, and Australia, and the company’s deliberate geographic diversification across 50 countries.
- Australia opening up: Anti-dumping duties on Chinese products are creating a new opportunity in Australia, adding another leg to the export story.
- AI demand risk dismissed: Management argued that even if AI investment slows, the renewable and grid build-out requirements countries have already committed to are independent of AI demand and will sustain.
Rajiv Singh: "Whether there is a slowdown in AI, really doesn't matter, it may not accelerate it further but I don't think that what is on the anvil and what the requirements, which all the countries are asking for today, they are despite the requirement for AI."
Transmission: The Supercycle Bet
- Decade-long thesis: Management believes power transmission is in a supercycle for the next decade, driven by renewable project rollout requiring evacuation infrastructure, grid strengthening from 220/400 kV to 765 kV, and power demand growth in countries like India at 7–8%+.
- Current share and trajectory: Transmission contributed ~20% of Q2 revenue; this share is expected to stay at about 20% for FY27, then improve from next year onwards as India domestic and Saudi Arabia transmission towers come online.
- Export tilt to persist: The transmission business is currently tilted more toward export because capacity was previously constrained and moved toward solar; even next year, export will dominate, with the domestic-international mix expected to start leveling out only after that.
- India domestic approach: The company is not participating in tenders; it is doing negotiated, price-based closures with developers, with three large jobs currently underway in India.
- US competitive moat: Limited local US production for transmission towers means the main suppliers are India and Turkey; few companies are qualified, and Karamtara benefits from a long track record, consistent quality delivery, and backward/forward integration (rolling mills, galvanizing) that enables on-time delivery. High replacement costs and supply-chain criticality make clients risk-averse with new suppliers.
Rajiv Singh: "I think power transmission, we are in a supercycle for the next decade or so, and I think the demand is going to be very, very robust."
Order Book & Key Wins
- Order book build: The order book increased from ~₹6,000 crores (June 30) to ₹6,500 crores (September 30), with ₹2,100–2,200 crores of fresh intake during the quarter.
- Execution visibility: ~60% of the ₹6,500 crore order book (~₹4,000 crores) is expected to be executed in the current financial year.
- US concentration: The US contributes over 57% of the ₹6,500 crore order book, reflecting the strength and depth of demand in that market.
- Large US order: A single large transmission order worth ~₹550 crores in the US was won on November 5, 2026, the day before the call.
- Large Canada order: One very large order from Canada was also secured, adding another North American anchor.
- October inflow: ₹1,200 crores of orders were announced in the previous month (October 2026), signaling sustained intake momentum.
Rajiv Singh: "It's a very sensitive market where you need to have quality product, which you've delivered consistently over the years for people to have confidence in giving you those orders. Because if you delay the work, the costs the client can incur are quite huge."
Capacity Expansion & New Facilities
- Bhachau facility: The large manufacturing facility at Bhachau has recently commenced production, increasing capacity for transmission line towers and offering more tonnage to offer customers.
- Saudi Arabia progress: The plant is almost fully constructed; sheds are up, concreting of bays is done, and machines and cranes are arriving. Trial production is expected by December-end 2026, with galvanizing trials targeted for March 2027.
- Saudi local content requirement: Local manufacturing is a must in Saudi Arabia due to preconditions of local content in all energy infrastructure projects; local requirements cannot be served through exports from India or other countries.
- Saudi as regional platform: The facility will provide a platform to serve neighboring markets and North Africa, not just Saudi domestic demand.
- Saudi demand drivers: Management cited huge demand coming from Expo 2030 and World Cup 2034 as key catalysts once capacity is up and running.
- New rolling mill and PEB facility: A new rolling mill for transmission towers and solar tracker piles, plus a dedicated PEB facility for data centers, is being built at Bhachau and expected to be ready around the beginning of next financial year.
- PEB timeline: Sheds are up, concreting of bays is ongoing; machines are expected to arrive January–February, with trials starting March–April. The PEB business head and design team have already joined.
- Post-CAPEX capacity: Sellable capacity is expected to reach ~0.14 crore tons (0.14 crore tonnes) once Saudi and Kutch CAPEX are complete, excluding captive profile mill and galvanizing capacity.
- Defense subsidiary: A subsidiary has been formed for defense and aerospace; management is in discussions on three or four possible scenarios and building out the team, but declined to provide any revenue guidance, asking for a few months before returning with specifics.
Rajiv Singh: "Local manufacturing is a must in the kingdom of Saudi Arabia due to the preconditions of local content in all energy infrastructure projects. Therefore, the local requirements cannot be served through exports from India or other country."
Margins & Working Capital
- Q2 margin walk: EBITDA margin improved ~100 bps QoQ to ~11.9%, but was impacted by increased freight costs (both ocean and land freight globally) and production holds on some Middle East/Africa dispatches.
- Freight pass-through expected: Management expects to pass on most increased freight costs to customers, with positive impact visible in Q3 and Q4. In large North American contracts, freight is a pass-through on actuals with client approval before dispatch; some Middle East contracts are on actuals, some partially passed through, and some absorbed.
- Freight pricing strategy shift: Going forward, since freight is near peak, all new quotes include those peak prices, reducing future exposure.
- Working capital improvement: The working capital cycle reduced to 37 days in H1 FY27, and debtor days decreased QoQ from 100 days to 94 days.
- Debtor days mix effect: Debtor days increased YoY due to a shift in geographical mix: international sales rose to 73% from 45% YoY, and international sales carry a longer working capital cycle than domestic. The Middle East crisis also increased transit days.
- Segment margins undisclosed: Management declined to provide segment-level margins, stating they package products and cross-sell and do not look at margins of one product or two products.
Sunil Rustagi: "Last year in the same quarter if you see our international sales were 45%, but in this quarter we have done 73% as international sales. So, in international sales, there is a longer working capital cycle as compared to the debtor days in the domestic market."
Competitive Positioning & Risk Management
- China limited as competitor: Chinese products are restricted in the US and some European countries due to national security concerns and inability to meet welding and quality requirements for qualification.
- US tariff pass-through: Tariffs are a pass-through to the customer; management noted there is still a 30% upside in the selling price versus what US manufacturers charge, and tariffs get factored in.
- Currency risk management: Forex risk is mitigated via PCFC or natural hedge by importing raw material for export orders; no currency risk is taken on projects.
- US market outlook: The forecast for the next 4–5 years is quite strong; the company will continue working there but remains open to pivoting to other markets if better pricing, penetration, or terms emerge.
- Global manufacturing footprint: The company is positioning as a global manufacturer with facilities in Saudi Arabia, Italy, and India serving local and global markets.
Rajiv Singh: "Tariffs, it really doesn't matter where the tariffs go because it's all a pass through to us... the difference between our product that we are supplying out of India and what is being sold by the US manufacturers, there's still a 30% upside on that in the selling price and the tariffs get factored in."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue growth | 60% to 65% growth over FY26, broad-based across solar, wind, transmission, and fasteners | FY27 full year |
| Transmission revenue share | Remain at ~20% for FY27, then improve from next year onwards | FY27; improvement from FY28 |
| Saudi trial production | Trial production by December-end 2026; galvanizing trials by March 2027 | Dec 2026 / Mar 2027 |
| Saudi commercial production | Commercial production starting next financial year; full capacity utilization by FY29–30 | FY28 start; FY29–30 full |
| PEB facility readiness | Machines arriving Jan–Feb, trials starting Mar–Apr; ready around beginning of next financial year | Q4 FY27 / early FY28 |
| H2 FY27 CAPEX | ₹200–250 crore, funded primarily from internal accruals and IPO money | H2 FY27 |
| H2 margin improvement | Freight cost pass-throughs expected to deliver positive impact | Q3 and Q4 FY27 |
| Order book execution | ~60% of ₹6,500 crore order book (~₹4,000 crores) to be executed | Current financial year |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue from operations | ₹1,647 cr, +62% YoY |
| H1 FY27 revenue from operations | ₹3,228 cr, +67% YoY |
| EBITDA | ₹196 cr, margin of 11.9%, +46% YoY |
| H1 FY27 EBITDA | ₹370 cr, margin of 11.5%, +46% YoY |
| Profit after tax | ₹94.6 cr, margin of 5.7%, +37% YoY |
| H1 FY27 profit after tax | ₹182 cr, margin of 5.6%, +41% YoY |
| FY27 revenue growth guidance | 60% to 65% over FY26, maintained |
| International revenue share | 73% of revenue, vs 45% in Q2 FY26 |
| Renewable products revenue share | 73% of revenue; 77% in H1 FY27 |
| Transmission revenue share | ~20% of revenue |
| Order book | ₹6,500 cr as of Sep 30, vs ~₹6,000 cr as of Jun 30 |
| Fresh order intake during quarter | ₹2,100–2,200 cr |
| Order book execution expected in FY27 | ~60% of order book, ~₹4,000 cr |
| US share of order book | ~57% of ₹6,500 cr order book |
| Working capital cycle | 37 days in H1 FY27, reduced |
| Debtor days | 94 days, down from 100 days QoQ |
| Capacity utilization expected by FY27 year-end | 60% to 70% |
| Aggregated installed capacity | 8,79,800 metric tons per annum, excluding captive rolling and galvanizing |
| Post-CAPEX sellable capacity target | ~0.14 crore tons (0.14 crore tonnes), excluding captive profile mill and galvanizing |
| H1 FY27 CAPEX | ₹370 cr |
| H2 FY27 planned CAPEX | ₹200–250 cr |
| Gross block | ₹2,411 cr |
| Net worth | ₹2,083 cr |
| Historical H1/H2 revenue split | ~42–45% in H1, ~55–58% in H2 |
| Historical revenue CAGR | ~37%+ |
| Saudi plant full capacity utilization expected | FY29–30 |
| PEB capacity being added at Bhachau | 100,000 tonnes |