KEC International Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/4wzmw5boc2s9bjdj2fsnfp41.pdf

Key Takeaways


T&D: The Growth Engine

Kejriwal: "In fact, we are L1 in one of them in the recent one. And that's an area where we were not there because I would not have typically bid for intrastate projects. So more than intrastate, I think intrastate is also an interesting area."

Working Capital & Debt: The Peak Thesis

Kejriwal: "I think the difference is that if you compare the major competitors and all that, most of them have done very poorly in Middle East, okay? We have a very large order book and a large revenue coming out of Saudi, where unfortunately, there is a 20% retention, okay?"

Non-T&D Margin Recovery

Kejriwal: "Margins have to improve. Otherwise, the business will have to shut down. We are very clear that unless the business reaches a margin level what we are looking for, okay, there's no fun in doing it."

Civil & Labor: The Bottleneck

Kejriwal: "I could have definitely done at least INR200 crores, INR300 crores more. I'm telling you in civil, had we had a full contingent of 30,000 people with us."

Renewables & New Engines

Kejriwal: "If you look at the last 3, 4 months or 6 months, the number of IPOs which have come from the solar companies have been phenomenal. And these are the players who have gone for a significant, I'll say, competitive intensity increase, okay? We are slowly seeing that dying down now. People have realized that they are killing themselves by doing it."

Guidance & Commitments

CommitmentSpecificsTimeline
Overall EBITDA marginAt least 8% for FY26, implying H2 above 8.5%FY26
Civil full-year revenue~₹5,000 crores, growth of 10–15%FY26
Civil marginMid-single digit this year; higher single digit next year; 9–10% targetFY26 / FY27 / "year after"
Civil growth next yearAt least 15–20%, roughly ₹6,500 croresFY27
Debt levelPeak now; expected around ₹5,000 crores by year-endFY26 year-end
NWC daysNormalize to 118–120 days, similar to last yearFY26 year-end
Interest costMaintain at 2.5% of revenueOngoing
Saudi project closures7–8 projects to complete, releasing retentionsThis financial year
Afghanistan ADB payment~$30 million expectedQ4 FY26
E-Beam margin impactPositive impact on cable marginsQ2 FY27 onwards
International renewableFirst international projects, 300–500 MWNext year
Wind EPCFirst wind EPC order announcement expectedThis year

Key Metrics

MetricQ2 FY26
Revenue₹6,092 cr, +19% YoY
H1 revenue growth+15% YoY, in line with full-year guidance
EBITDA+34% YoY in Q2; +27% YoY in H1
EBITDA margin7.1%, up 80 bps YoY from 6.3%
H1 EBITDA margin7.0%, up 60 bps YoY from 6.4%
PBT growth+88% YoY in both Q2 and H1
PBT margin3.5%, up 130 bps YoY from 2.2%
PAT₹161 cr in Q2; ₹285 cr in H1
Interest cost as % of revenue2.8% in Q2, down 50 bps YoY
YTD order intake>₹16,000 cr, +20% YoY; 75% from T&D
Order book>₹39,000 cr; including L1 of ₹5,000 cr, total ₹44,000 cr
Net debt including acceptances₹6,480 cr as of 30 Sep, vs ₹5,265 cr a year ago
T&D revenue₹4,080 cr, +44% YoY; 65% of overall revenue vs 55% in H1 last year
T&D order intake₹12,000 cr across India, Middle East, CIS, Americas
Civil revenue₹968 cr; constrained by prolonged monsoon, labor shortages, delayed water payments
Transportation revenue₹425 cr
Cables revenue₹524 cr, +19% YoY
Renewable revenue₹190 cr
SAE revenue₹429 cr, +35% YoY
Tender pipeline>₹1,80,000 cr, predominantly in T&D and Civil