KEC International Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/as-a51a7756c7d3506bb81909bc.pdf

Key Takeaways


Middle East Disruption: The Quarter's Central Drag

Kejriwal: "There has been some talk saying will there be scaling down? I do not think there is a scaling down because continuously projects are coming up."

Margin Trajectory: When Does It Turn?

Kejriwal: "But do we think we will get into double digit and all in FY 2027? No, not possible. ... High single digit in 2028 should be possible."

Working Capital & Debt: The Identified Levers

Kejriwal: "I think if we are lucky, let me put it, that we should get it in Q2 itself. Otherwise, definitely Q3, and that is a large amount, INR 300 crore without any outflow against it."

T&D: The Growth Engine


SAE Towers & Cables: The Bright Spots


Civil, Transportation & Water: The Turnaround Bets

Kejriwal: "Because of that, what happens is that the client will not take over, you are supposed to maintain. So virtually, you end up spending almost INR 10 crores per month on each project. Now all these are going in the expense account. You will make a claim and all that. That is where it is continuing, and I think it is a saga which is I do not know what to say about it."

Guidance & Commitments

CommitmentSpecificsTimeline
Revenue growth12-15% YoY (may vary by half or 1% depending on war situation)FY27
Order inflow~₹30,000 crores (60-70% from T&D)FY27
Debt reduction~₹1,200 crores reduction, from ~₹6,700 crores to ~₹5,500 croresBy March FY27
Afghanistan collections~₹300 croresQ2 FY27; if not, definitely Q3
Water old dues collection~₹300-₹400 crores, contingent on JJM fund releaseFY27
Railway claims realization₹150-₹200 croresFY27
Working capital days110 daysFY27 end
Full-year interest cost~2.3% of revenue (~₹600+ crores total)FY27
Elastomeric cable productionCommence productionQ2 FY27
EBM plant commissioningCommission plantQ3 FY27
Overall double-digit marginNot possibleFY27
High single-digit marginShould be possibleFY28
T&D marginsContinue in double digit or very closeOngoing
Middle East supply normalizationSituation slowly normalizing; should come backMaybe by end of Q2 FY27

Key Metrics

MetricQ1 FY27
Revenue₹5,024 cr, marginally higher than Q1 last year
PBT₹90 cr, with PBT margin of 1.8%
PAT₹73 cr
Net debt (incl. acceptances)₹6,568 cr, reduced by over ₹150 cr from March 2026
Order intakeOver ₹6,300 cr, across T&D, civil, renewables, cables and conductors, and transportation
Order book₹37,697 cr as on date
Order book and L1 positionOver ₹40,000 cr, including L1 of almost ₹3,000 cr predominantly in T&D
T&D revenue₹3,217 cr, higher than last year
T&D order book and L1Over ₹25,000 cr
Civil revenue₹993 cr, growth of 6% YoY
Civil order book and L1Over ₹10,000 cr
Transportation revenue₹259 cr
Cables and conductors revenueOver ₹600 cr, growth of 57% YoY
SAE revenue₹450 cr, growth of 25% YoY
SAE order book and L1Over ₹3,800 cr, a record level
Renewables new orders₹800 cr from an existing customer
Global manufacturing capacity483,800 metric tons, increased after Butibori expansion in Q1
Tender pipelineExceeding ₹2 lakh crore
KAVACH implemented667 route kilometers completed; additional 780 RKM and over 3,000 locos under execution
High-rise buildings under constructionApproximately 80 for marquee clients across India
Solar and wind capacity under executionOver 600 MW cumulative
Middle East share of order book and L1Approximately 25%
JJM receivablesAround ₹800–900 cr total, of which around ₹400–500 cr overdue; dues equally split between Odisha and MP
Afghanistan receivablesRoughly ₹300 cr due, expected from ADB
FY27 revenue growth guidance12–15%, maintained
FY27 order intake guidance~₹30,000 cr, with 60–65% from T&D; international expectation ₹9,000–10,000 cr
FY27-end working capital days target110 days
FY27 debt reduction target~₹1,200 cr, from about ₹6,700 cr to about ₹5,500 cr by March
Cable business revenue potentialAround ₹3,000 cr with present capacity
SAE Towers revenue potentialAround ₹2,000 cr based on current fixed assets; utilization at almost 100%
SAE Towers marginsAlmost double digit
Cable business marginsAround 5%, almost 200 bps below market
Q1 revenue deferral from Middle EastAround ₹300 cr for the quarter
Railway claims expected realization in FY27Roughly ₹150–200 cr; awards already received for about ₹150–160 cr
Saudi and Middle East retention collection expectedEasily ₹300–400 cr
Water order bookRoughly ₹1,200–1,300 cr, about 13–14% of civil order book
Adani Group share of order bookClose to 5% or less
Full-year total interest expectationAround ₹600+ cr
Specialty cable products expected revenue additionAround ₹300–400 cr