Key Takeaways
- Flat quarter, transitory headwinds: Revenue of ₹5,024 crores was flat YoY as ~₹300 crores of EPC execution was deferred by Middle East conflict and labor shortages, but management calls these challenges transitory and recoverable.
- Profitability under pressure: PBT of ₹90 crores (1.8% margin) and PAT of ₹73 crores were dragged down by Middle East logistics costs, metro project maintenance expenses (~₹10 crores/month per project), and delayed claims settlements.
- Order book and L1 pipeline provide visibility: T&D order book plus L1 exceeds ₹25,000 crores, civil plus L1 exceeds ₹10,000 crores, and full-year order inflow guidance of ₹30,000 crores is maintained.
- Debt reduction on track despite headwinds: Net debt reduced by over ₹150 crores to ₹6,568 crores; full-year target of ~₹1,200 crores reduction is backed by identified levers including Afghanistan collections, water dues, and retention releases.
- What to watch next quarter: Whether Afghanistan collections (~₹300 crores) materialize, the pace of Middle East supply normalization, and any resolution on the four stuck metro projects that are bleeding ~₹10 crores per month each.
Middle East Disruption: The Quarter's Central Drag
- Supply-side chaos: Shipments from Europe, China, and India to GCC resumed gradually but with delays; ports under attack, vessel availability constrained, and freight costs including war-related surcharges and insurance remain elevated, cascading into higher logistics, fuel, and power costs at Indian manufacturing facilities.
- Revenue deferred, not lost: ~₹300 crores of EPC execution was deferred in Q1 due to the conflict; management expects this to be recovered in subsequent quarters and is maintaining full-year revenue growth guidance of 12-15%.
- Procurement deferral risk: Project execution may get deferred until customers align on recovery of additional costs, creating both revenue and margin timing impacts that are not yet quantified.
- Spillover into Q2: Challenges from Middle East supply chain and logistics are expected to have a spillover effect on Q2, though freight costs are expected to moderate over the coming weeks.
- Order book composition: ~₹10,000 crores of Middle East orders, equally divided between Saudi and UAE; on-ground execution is normal but local operating costs are up significantly, impacting margins.
Kejriwal: "There has been some talk saying will there be scaling down? I do not think there is a scaling down because continuously projects are coming up."
Margin Trajectory: When Does It Turn?
- Current state: Standalone EBITDA margin declined to ~4% because higher-margin T&D sits largely in the consolidated entity, while Railways and Civil (both negative) sit in standalone. Overall PBT margin was 1.8%.
- Metro project bleed: Four metro projects (two DMRC, two Chennai Metro) are completed or ready for commissioning but not taken over by the client; maintenance costs of almost ₹10 crores per month per project are expensed, dragging profitability.
- Civil and Transportation margins: Still negative, putting overall numbers under pressure; old metro projects are the cause, not new orders, which are all profitable.
- T&D margins resilient: Expected to continue in double digits or very close; enough cushions exist, many contracts are hedged, and steel costs have come down.
- Cable margins: Around 5%, still ~200 bps below the market; specialty cables coming up are expected to inch margins up.
- Challenging-margin orders ending: Some older orders taken at challenging margins are now coming to an end, which should help margin improvement by year-end.
- FY27 double-digit margin ruled out: Management explicitly stated double-digit overall margin is not possible in FY27; high single digit in FY28 should be possible.
- Q2 expectations: Margins expected to remain in a similar line, maybe 50 bps here or there; no significant increase until the war situation resolves.
Kejriwal: "But do we think we will get into double digit and all in FY 2027? No, not possible. ... High single digit in 2028 should be possible."
Working Capital & Debt: The Identified Levers
- Debt reduction target: Targeting ~₹1,200 crores reduction from ~₹6,700 crores to ~₹5,500 crores by March, with multiple identified levers.
- Afghanistan collections: ~₹300 crores expected, with no associated outflow; management expects collection in Q2, or definitely Q3.
- Water old dues: ~₹300-₹400 crores expected if Jal Jeevan Mission funds are released; subsequent revenue will be regularized.
- Saudi/Middle East retention: ~₹300-₹400 crores expected from retention releases, which have been fast-tracked in Saudi and Dubai.
- Railway claims: ₹150-₹200 crores expected in FY27, depending on negotiation; awards already received for about ₹150-₹160 crores.
- Inventory unwinding: Higher Q1 inventory from delayed Dubai dispatches and raw material storage amid Middle East disruptions is expected to release ~₹200-₹250 crores.
- Working capital days: Targeting 110 days at FY27 end.
- Interest cost trajectory: Q1 interest at 3.3% was elevated because cash came in late while April-May borrowings were high; full-year expectation is around 2.3%, total interest around ₹600+ crores.
- Payment terms improving: Management sees general improvement in payment terms and cycles across civil, T&D, and private clients; Power Grid has made advances interest-free.
Kejriwal: "I think if we are lucky, let me put it, that we should get it in Q2 itself. Otherwise, definitely Q3, and that is a large amount, INR 300 crore without any outflow against it."
T&D: The Growth Engine
- Revenue and order book: Q1 T&D revenues of ₹3,217 crores, higher YoY but constrained by Middle East supply chain; order book plus L1 over ₹25,000 crores provides strong visibility.
- Full-year order intake: 60-70% of the ₹30,000 crore order inflow target expected from T&D (~₹20,000 crores); international at ₹9,000-₹10,000 crores, with a significant part from West Asia.
- HVDC breakthrough: Secured a significant order in the rapidly growing HVDC segment and participated in multiple packages in the Barmer Rajasthan HVDC scheme; additional schemes expected to be floated during the year.
- Data center opportunity: Secured the first transmission line order for evacuation of power to a data center in Western India; management sees more inquiries coming on the T&D side as data centers face power supply challenges.
- India T&D headwinds: ROW issues in Rajasthan and Gujarat (major renewable project states) causing execution headwinds; Gujarat has introduced a new compensation scheme with 2-3x market value, which is expected to improve movement.
- New developer relationships: Started bidding for three new developers during the quarter, in addition to PGCIL and other private developers.
- Africa revival: Won a significant transmission line order in Africa, strengthening regional presence.
SAE Towers & Cables: The Bright Spots
- SAE revenue growth: Revenues of ₹450 crores, 25% YoY growth; order inflows nearly 4x vs last year, including the largest ever tower supply order from the U.S.
- SAE utilization and margins: Running at almost full capacity (~100%), with current fixed assets supporting ~₹2,000 crores revenue; margins are almost double digit.
- SAE order book delivery: ₹3,800 crores order book to be delivered in ~1.5-2 years; those markets get orders at least 12 months in advance.
- Cables revenue surge: Revenue over ₹600 crores, 57% YoY growth driven by robust demand across infrastructure, power transmission, and industrial segments.
- Specialty cable ramp-up: Elastomeric cables slated to commence production in Q2 FY27; EBM plant commissioning in Q3 FY27; new products expected to add ₹300-₹400 crores revenue and inch margins up from the current ~5%.
- Cable capex: Over the last three years, ₹300 crores spent on cable capacity; normal annual spend is ₹75-₹100 crores; EHV expansion capex is on the drawing board, could happen next year or later.
- Export push: Expect increase in export market by Q4 with specialty cables coming up.
- Manufacturing capacity: Completed expansion of Butibori facility in Nagpur in Q1; global capacity now 483,800 metric tons.
Civil, Transportation & Water: The Turnaround Bets
- Civil revenues: ₹993 crores, 6% YoY growth; slightly lower due to labor shortages from the election period and customer payment delays in the water segment.
- Labor normalization: Labor situation started improving from June 26 onwards; shortages arose from the election period and impacted civil execution.
- Civil order book: Order book plus L1 over ₹10,000 crores; large tender pipeline across residential, commercial, and metals/mining sectors.
- Water projects: Most water projects (MP and Odisha) should complete within this year; projects are profitable at 8-10% margin, but large outstanding receivables are the challenge, not cost structure. Execution slowed deliberately on supply items to need-based only.
- Transportation revenues: ₹259 crores; focus on execution and completion; profitability impacted by delays in legal closure of disputes and settlement of claims.
- Railway slow-moving projects: Most are at 95-97% closure; completion depends on railway blocks or depot design approvals.
- Data center civil orders: Management hopes to secure a few orders on the civil side for data centers by next quarter.
- Renewables: Secured ₹800 crores in new orders from an existing customer in wind and solar; engaging with leading wind OEMs for strategic partnerships.
Kejriwal: "Because of that, what happens is that the client will not take over, you are supposed to maintain. So virtually, you end up spending almost INR 10 crores per month on each project. Now all these are going in the expense account. You will make a claim and all that. That is where it is continuing, and I think it is a saga which is I do not know what to say about it."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 12-15% YoY (may vary by half or 1% depending on war situation) | FY27 |
| Order inflow | ~₹30,000 crores (60-70% from T&D) | FY27 |
| Debt reduction | ~₹1,200 crores reduction, from ~₹6,700 crores to ~₹5,500 crores | By March FY27 |
| Afghanistan collections | ~₹300 crores | Q2 FY27; if not, definitely Q3 |
| Water old dues collection | ~₹300-₹400 crores, contingent on JJM fund release | FY27 |
| Railway claims realization | ₹150-₹200 crores | FY27 |
| Working capital days | 110 days | FY27 end |
| Full-year interest cost | ~2.3% of revenue (~₹600+ crores total) | FY27 |
| Elastomeric cable production | Commence production | Q2 FY27 |
| EBM plant commissioning | Commission plant | Q3 FY27 |
| Overall double-digit margin | Not possible | FY27 |
| High single-digit margin | Should be possible | FY28 |
| T&D margins | Continue in double digit or very close | Ongoing |
| Middle East supply normalization | Situation slowly normalizing; should come back | Maybe by end of Q2 FY27 |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Revenue | ₹5,024 cr, marginally higher than Q1 last year |
| PBT | ₹90 cr, with PBT margin of 1.8% |
| PAT | ₹73 cr |
| Net debt (incl. acceptances) | ₹6,568 cr, reduced by over ₹150 cr from March 2026 |
| Order intake | Over ₹6,300 cr, across T&D, civil, renewables, cables and conductors, and transportation |
| Order book | ₹37,697 cr as on date |
| Order book and L1 position | Over ₹40,000 cr, including L1 of almost ₹3,000 cr predominantly in T&D |
| T&D revenue | ₹3,217 cr, higher than last year |
| T&D order book and L1 | Over ₹25,000 cr |
| Civil revenue | ₹993 cr, growth of 6% YoY |
| Civil order book and L1 | Over ₹10,000 cr |
| Transportation revenue | ₹259 cr |
| Cables and conductors revenue | Over ₹600 cr, growth of 57% YoY |
| SAE revenue | ₹450 cr, growth of 25% YoY |
| SAE order book and L1 | Over ₹3,800 cr, a record level |
| Renewables new orders | ₹800 cr from an existing customer |
| Global manufacturing capacity | 483,800 metric tons, increased after Butibori expansion in Q1 |
| Tender pipeline | Exceeding ₹2 lakh crore |
| KAVACH implemented | 667 route kilometers completed; additional 780 RKM and over 3,000 locos under execution |
| High-rise buildings under construction | Approximately 80 for marquee clients across India |
| Solar and wind capacity under execution | Over 600 MW cumulative |
| Middle East share of order book and L1 | Approximately 25% |
| JJM receivables | Around ₹800–900 cr total, of which around ₹400–500 cr overdue; dues equally split between Odisha and MP |
| Afghanistan receivables | Roughly ₹300 cr due, expected from ADB |
| FY27 revenue growth guidance | 12–15%, maintained |
| FY27 order intake guidance | ~₹30,000 cr, with 60–65% from T&D; international expectation ₹9,000–10,000 cr |
| FY27-end working capital days target | 110 days |
| FY27 debt reduction target | ~₹1,200 cr, from about ₹6,700 cr to about ₹5,500 cr by March |
| Cable business revenue potential | Around ₹3,000 cr with present capacity |
| SAE Towers revenue potential | Around ₹2,000 cr based on current fixed assets; utilization at almost 100% |
| SAE Towers margins | Almost double digit |
| Cable business margins | Around 5%, almost 200 bps below market |
| Q1 revenue deferral from Middle East | Around ₹300 cr for the quarter |
| Railway claims expected realization in FY27 | Roughly ₹150–200 cr; awards already received for about ₹150–160 cr |
| Saudi and Middle East retention collection expected | Easily ₹300–400 cr |
| Water order book | Roughly ₹1,200–1,300 cr, about 13–14% of civil order book |
| Adani Group share of order book | Close to 5% or less |
| Full-year total interest expectation | Around ₹600+ cr |
| Specialty cable products expected revenue addition | Around ₹300–400 cr |